DZ17A/0161
GrantedLands (site area c.0.95ha) in the townland of Laughanstown, Dublin 18
Lands (site area c.0.95ha) in the townland of Laughanstown, Dublin 18
A temporary concrete batching plant will be built on the site to supply concrete for Cherrywood development construction. The facility will operate for 7 years.
The plant includes cement silos, concrete mixer equipment, aggregate storage bins, and water storage tanks. There will also be fuel storage tanks, staff and truck parking, contractor offices, welfare facilities, and covered and open storage areas.
The facility covers 0.95 hectares in Laughanstown. An electricity substation, backup generator, pump house, and site lighting will support operations.
Boundary treatments and site works will be installed to manage the temporary facility. The plant is designed to operate within the Cherrywood Strategic Development Zone planning framework.
Summary generated by AI from the official planning description. Always refer to the original documents for authoritative details.