DZ24A/1024/WEB
GrantedIn the Townlands of Laughanstown and Cherrywood, in Cherrywood,, Dublin 18
In the Townlands of Laughanstown and Cherrywood, in Cherrywood,, Dublin 18
This is a modification to a development already approved in 2022 and updated in 2024. The changes reduce car parking, increase bicycle parking, and add utility buildings—but the number of homes remains the same.
Car parking is being reduced from 312 to 213 spaces (78 at ground level, 135 underground). Bicycle parking is increasing to 391 spaces total (82 short-stay, 309 long-stay), including a new 39 sq.m bicycle store.
A new 60 sq.m combined substation, switch room and refuse building is being added. The underground parking level beneath Blocks B1–B3 is being restructured. Drainage tanks along Civic Park are being modified to manage surface water.