DZ17A/0161
GrantedLands (site area c.0.95ha) in the townland of Laughanstown, Dublin 18
Lands (site area c.0.95ha) in the townland of Laughanstown, Dublin 18
A temporary concrete batching plant will be built on-site to produce concrete for the broader Cherrywood development. The facility will operate for 7 years and will include storage, mixing equipment, staff facilities, and parking for construction vehicles.
The plant includes cement silos, aggregate storage bins, a batching and mixer facility, water storage tanks, fuel storage, and covered and open storage areas. An electricity substation, backup generator, pump house, and site lighting will support operations. Contractor offices and welfare facilities are included for site staff.
Dedicated parking areas for staff and construction trucks are provided on-site.