DZ17A/0161
GrantedLands (site area c.0.95ha) in the townland of Laughanstown, Dublin 18
Lands (site area c.0.95ha) in the townland of Laughanstown, Dublin 18
A temporary concrete batching facility will be built on the Laughanstown site to supply concrete for the wider Cherrywood development. The plant will operate for 7 years and then be removed.
The site will include cement silos, conveyors, aggregate storage bins and bays, a batching and mixer plant, water storage tanks, fuel storage, and parking for staff and trucks. Contractor offices and welfare facilities will also be provided.
The development includes an electricity substation, backup generator, pump house, site lighting, and boundary treatments. All works are temporary and designed to support the wider Cherrywood build-out.
Summary generated by AI from the official planning description. Always refer to the original documents for authoritative details.