# Planning application DZ15A/0758 > in the townlands of Cherrywood, Laughanstown, Brennanstown, Loughlinstown and Glebe, Dublin 18, Cherrywood, Dún Laoghaire–Rathdown. Granted (16 Aug 2016). - **Reference:** DZ15A/0758 - **Address:** in the townlands of Cherrywood, Laughanstown, Brennanstown, Loughlinstown and Glebe, Dublin 18 - **Status:** Granted (16 Aug 2016) - **Decision:** GRANT PERMISSION - **Application type:** Permission (SDZ) - **Applicant:** Hines CDF ICAV & Wm.Neville & Sons - **Lodged:** 22 Jun 2016 - **Decided:** 16 Aug 2016 - **Location (lat, lng):** 53.247353, -6.151769 ## Proposal Roads and infrastructure (phase 1) as approved under the Cherrywood SDZ Planning Scheme (2014) to form part of public road network providing access and services for the future development of the adjoining SDZ lands. The roads for which permission is sought, identified on Maps 4.5 and 7.2 of the Planning Scheme including junction names, are as follows:- 1. Junction A - replace the existing roundabout on Wyattville Link Road (WLR) with a signalised junction and associated upgrades and reconfiguration of the WLR including provision for bus lanes, cycle lanes and pedestrian crossings. 2. A number of Level 2-5 roads including the following road segments:- Level 2 Roads - Improvements and widening of existing Cherrywood Avenue 1-A to tie-in with new signalised junction on the WLR; widening of existing Tully Vale Road A-A1 and A1-B; construction of new road known as Grand Parade B-P2 and P2-C parallel to the Luas, with provision of pedestrian crossing at Junction L; construction of new road (part) known as Barrington's Road C-D; Level 3 Roads - Construction of new roads known as Bishop Street A1- A2 and A2-FI and section of Grand Parade A2-B; Level 4 Roads - Construction of new roads known as Castle Street D-FI and construction of Gun and Drum Hill K5-P2 connecting Castle Street to Grand Parade (proposed new roads); and Level 5 Road- Construction of new minor road between Castle Street and Mercers Road (ESB transmission infrastructure will be placed within the road corridor to facilitate the future undergrounding, by ESB, of existing overhead electricity cables and removal of the existing pylon at Laughanstown). The road proposals include junction design and provision for tie-ins to adjoining roads and greenways prescribed in the Planning Scheme. The total road length proposed is c.5.4kms, of which c.4.1kms is new road and c.1.3kms relates to works to existing roads i.e. WLR, Cherrywood Avenue and Tully Vale Road. As part of the above roads, permission is also sought for associated footpaths and pedestrian crossing points, cycle lanes, bus lanes and stops, verge and median landscaping, public lighting, traffic signals, directional signage and all associated ancillary works. 3. Provision is made within the road corridor and underground services (surface and foul water drainage and watermains supply) and ducting for public utilities and telecoms. Underground utilities ducting on Lehaunstown Lane (part of) will provide a connection from proposed Castle Street (Junction K) to the existing 110KV ESB substation at Laughanstown. A foul sewer proposed along existing residential road (Valley Drive) will connect the proposed networks to the existing Carrickmines Trunk sewer in Lehaunstown Valley. 4. In addition to surface water drainage infrastructure within the road corridor, proposed new surface water infrastructure includes an attenuation pond at Lehaunstown Valley with outfall to Cabinteely River and a detention basin at the intersection of the proposed Castle Street with Lehaunstown Lane (Juntion K). The attenuation pond will be constructed using excavated material from the site (including material from previously excavated ground in TC1, adjoining WLR). Surface water sewers are also proposed between Castle Street (Junction D1) and Grand Parade and within existing residential road north-west of Tullyvale apartments. 5. Permission is also sought for all associated ancillary site and development works associated with the above, including hard and soft landscaping, enabling works and temporary construction works (including site accommodation, site compounds, temporary boundary fencing and construction access road from WLR-J). An Environmental Impact Statement (EIS) has been prepared and will be submitted to the planning authority with this application. ## In plain English Phase 1 roads for Cherrywood: about 5.4km of new and upgraded roads including Grand Parade, Castle Street and Bishop Street. - **5.4** km of road - **25.65** hectare site ### What's planned The first phase of roads and services to open up the Cherrywood SDZ, on about **25.65** hectares. ### Transport About **5.4**km of roads (**4.1**km new): a signalised junction replacing the Wyattville Link Road roundabout, widening of Cherrywood Avenue and Tully Vale Road, and new roads including Grand Parade, Barrington's Road, Bishop Street, Castle Street and Gun and Drum Hill Road. Footpaths, cycle lanes, bus lanes and traffic signals included. ### Environment An attenuation pond in Lehaunstown Valley draining to the Cabinteely River, a detention basin at Castle Street / Lehaunstown Lane, and new sewers and water mains. Ducting will allow ESB to put overhead cables underground. _This summary was written by AI from the proposal text. Check the council record before relying on it._ ## Conditions ### Condition 1 The development to be carried out in its entirety in accordance with the plans, particulars and specifications lodged with the application on 01.12.2016 as amended on 22.06.2016, including mitigation measures identified within the EIS, save as may be required by the other conditions attached hereto. REASON: To ensure that the development shall be in accordance with the permission and that effective control be maintained. ### Condition 3 Prior to commencement of development the developer shall submit a visual illustration by way of cross section drawings, photomontage, etc. of the proposed junction between Gun and Drum Hill and Lehaunstown Lane. For the written agreement with the Planning Authority REASON: In the interests of clarity and visual amenity, to ensure that the development shall be in accordance with the permission and that effective control be maintained. ### Condition 4 A Signage Strategy for the Roads including directional and wayfinding, shall be submitted and agreed in writing with the Planning Authority prior to commencement of development or as otherwise agreed. REASON: In order to comply with Objective PD 32 of the Cherrywood Planning Scheme and in the interests of visual amenity. ### Condition 5 The proposed development shall be undertaken in accordance with Section 4.3 (Detailed Mitigation Measures) of IAC Archaeological Assessment Report (dated May 2016). REASON: In the interest of the protection and recording of archaeological material and to ensure consistency with the Cherrywood Planning Scheme. ### Condition 6 Detailed design of water supply infrastructure including details of connections to individual development plots shall be in accordance with Irish Water specification and requirements. Written evidence of the design compliance with Irish Water specification and requirements and copies of the final detail design shall be provided to the Planning Authority prior to commencement of development. The detailed design to be submitted shall include a clear and fully annotated overall drawing (at a scale of 1:2500) detailing the full extent of the proposed water supply infrastructure and connections to existing infrastructure. REASON: In the interests of orderly development the inclusion of infrastructure and connections would avoid subsequent excavation of the newly constructed roadway and in the interest of consistency with Objective PI 4 of the Planning Scheme. ### Condition 7 The developer shall undertake the following: a) The construction of the relevant attenuation ponds and associated storm infrastructure shall be completed prior to the opening of any roads. b) Prior to the commencement of any development: (i) the detailed design and the construction detail for the regional attenuation pond to the north east of Druid Valley (also referred to as pond 2B) and the detention basin off Castle Street (referred to as detention basin/pond 5A) shall be submitted to the Planning Authority for agreement in writing and in the absence of agreement the matter may be referred to An Bord Pleanala for determination. (ii) the design and construction details shall be coordinated with the developments granted under planning references DZ15A/0814 and DZ15A/0813; (iii) the detailed design and construction details of the surface water management system and attenuation storage design shall consider any necessary adaptation required to facilitate other zoned lands in the immediate area; (iv) a clear and fully annotated overall drawing (at a scale of 1:2500) detailing the full extent of the proposed surface water drainage infrastructure and connections to existing infrastructure shall be submitted to the Planning Authority. c) The minimum size storm sewer serving a road gully shall be a minimum of 225mm. d) The detailed design of the road drainage shall be submitted to the Planning Authority for agreement in writing prior to the commencement of development. e) No overland flows onto public roadways from individual sites are permitted during storm event up to the 1 in 100 year return period. f) Prior to commencement of development or as otherwise agreed with the Planning Authority, the developer shall provide full details on the proposed landscaping scheme at the attenuation pond and detention basin. The design detail and landscaping plan should be such to minimise maintenance, encourage biodiversity, address sedimentation management and an appropriate design life for such systems. These details shall be submitted to the Planning Authority for written agreement. g) Prior to commencement of development or as otherwise agreed, an operations and management plan for the proposed sustainable urban drainage components (inclusive of the attenuation ponds and basins) shall be agreed in writing with the Planning Authority. REASON: To ensure long term optimum operation of the surface water management system, in the interests of orderly and sustainable development, proper management of flood risk and master planning, to prevent blockages, in the interests of orderly development and maintaining consistency with Objectives PI 6, PI 7, PI 8 and PI 9 of the Planning Scheme. ### Condition 8 Detailed design of foul water drainage including details of connections to individual development plots shall be in accordance with Irish Water specification and requirements. Written evidence of the design compliance with Irish Water specification and requirements and copies of the agreed detail design shall be provided to the Planning Authority prior to commencement of development. The detailed design to be submitted shall include a clear and fully annotated overall drawing (to a scale of 1:2500) detailing the full extent of the proposed foul water infrastructure and connections to existing infrastructure. REASON: In the interests of orderly development the inclusion of infrastructure and connections would avoid subsequent excavation of the newly constructed roadway and in the interests of consistency with PI 12 of the Planning Scheme. ### Condition 9 The developer shall undertake the following: a) Prior to commencement of development or as otherwise agreed, the developer shall submit, for the written agreement of the Planning Authority the detailed design and specification of the following components of the road infrastructure: (i) traffic signals and signal control systems at junctions, pedestrian crossings, cycle crossings, bus gates, bus priority and others (ii) statutory and regulatory signage (iii) anti-skid surfacing (iv) bus gates (v) bus stops, shelters and RTPI b) Prior to commencement of development or as otherwise agreed, the developer shall submit the following for the written agreement of the Planning Authority: (i) the design of the section of Grand Parade between B to A2 which also caters for the future Transport Interchange. (ii) The design cross section of Gun and Drum Hill connecting Castle Street and Grand Parade. (iii) The design cross section of Grand Parade between points C and P2. c) Pedestrian facilities shall be omitted along the Wyattville Link Road to the west of its junction at ‘A’ with Tully Vale Road/Cherrywood Avenue. Reason: To ensure consistency with Objective PI 14, Map 4.5, Figure 4.4 and Section 4.2.7 of the Planning Scheme and with current revisions of the design guidance documents listed in the Planning Scheme, in the interests of orderly development and to ensure that designs shall meet with the current and future requirements of the Planning Authority, to ensure consistency with Objective PI 19 and Map 4.6 of the Planning Scheme and in the interest of discouraging pedestrian movement at-grade across the Wyattville Link Road and to ensure consistency with Objective DA 10. ### Condition 10 The developer shall undertake the following: a) Prior to commencement of development or as otherwise agreed, the developer shall consult with Transport Infrastructure Ireland (TII) and subsequently agree, in writing, with the Planning Authority any measures necessary to facilitate the use of longer trams on the Luas Green Line of approximately 55 metre length to improve Luas network capacity. b) Prior to commencement of development or as otherwise agreed, the developer shall consult with Transport Infrastructure Ireland (TII) and subsequently agree in writing with the Planning Authority the detailed design of each of the following junctions that interface with the Luas Green Line: - i. Grand Parade/Gun and Drum Hill junction ii. Bishop Street/Grand Parade junction c) Prior to commencement of development or as otherwise agreed, the developer shall consult with Transport Infrastructure Ireland (TII) and subsequently agree in writing with the Planning Authority the final overall landscape strategy for the integration of the Luas. In particular: (i) Appropriate detailing in the zone adjoining the Luas swept path for the length of Grand Parade which shall include suitable integration of Cherrywood and Lehaunstown Luas stops. (ii) Safety distances to the swept path including safe distances for maintenance walkways in compliance with the Railway Safety Commission Regulations. (iii) Sufficient space for sustainability of planting. (iv) Form and widths of the footpaths, verges, medians and planting strips. (v) Height of planting bands for safety and visibility purposes. d) Prior to commencement of development or as otherwise agreed, the developer shall consult with Transport Infrastructure Ireland (TII) and subsequently agree in writing with the Planning Authority the detailed design of the triangular area located between the Luas alignment and the road junction at Grand Parade and Tully Vale Road as identified on Murray and Associates Drawing P_08-A. e) Prior to commencement of development or as otherwise agreed, the developer shall consult with Transport Infrastructure Ireland (TII) and subsequently agree in writing with the Planning Authority the detailed design of the landscaping treatment at the crossing and access/interface to the Lehaunstown Luas stop. f) Prior to commencement of development or as otherwise agreed, the developer shall consult with Transport Infrastructure Ireland (TII) and subsequently agree in writing with the Planning Authority a detailed safety analysis and risk assessment of the pedestrian crossing of the Luas along the alignment of the existing Lehaunstown Lane. ### Condition 11 Detailed design of the electricity supply network shall be agreed in writing with ESB Networks/ESBI. Written evidence of this agreement shall be provided to the Planning Authority prior to commencement of development or as otherwise agreed. REASON: In the interests of orderly development the inclusion of infrastructure and connections would avoid subsequent excavation of newly constructed roadway; to ensure that designs shall meet with the current and future requirements of ESB Networks/ESBI. ### Condition 12 Detailed design of the gas network shall be agreed in writing with Gas Networks Ireland. Written evidence of this agreement shall be provided to the Planning Authority prior to commencement of development or as otherwise agreed. REASON: In the interests of orderly development the inclusion of infrastructure and connections would avoid subsequent excavation of newly constructed roadway; to ensure that designs shall meet with the current and future requirements of Gas Networks Ireland. ### Condition 13 Detailed design of the telecoms network shall be agreed in writing with the telecoms providers. Written evidence of these agreements shall be provided to the Planning Authority prior to commencement of development or as otherwise agreed. REASON: In the interests of orderly development the inclusion of infrastructure and connections would avoid subsequent excavation of newly constructed roadway; to ensure that designs shall meet with the current and future requirements of the telecoms providers; to ensure consistency with Objective PI 26 of the Planning Scheme. ### Condition 14 Detailed design of the fibre network shall be agreed in writing with the Planning Authority prior to commencement of development or as otherwise agreed. REASON: In the interests of orderly development the inclusion of infrastructure and connections would avoid subsequent excavation of newly constructed roadway; to ensure that designs shall meet with the current and future requirements of the Planning Authority. ### Condition 15 Detailed design of public lighting complying with ‘Public Lighting Installations in Residential and Industrial Areas Guidance Document – February 2015’ (Dun Laoghaire Rathdown County Council), shall be agreed in writing with the Planning Authority prior to commencement of development or as otherwise agreed. REASON: To ensure that designs shall meet with the requirements of the Planning Authority and shall be consistent with the planning scheme Objective PI 28 and the documents listed in Section 4.2.7. ### Condition 16 The location of charge points for electric vehicles shall be in accordance with the requirements of the Planning Authority. Copies of the final detail design shall be provided to the Planning Authorityin writing prior to commencement of development or as otherwise agreed. REASON: To ensure that designs shall be in accordance with the planning scheme Objectives PI 29 and PI 31. ### Condition 17 The following shall be submitted to and agreed in writing with the Planning Authority prior to commencement of development or as otherwise agreed: a) Detailed design including samples and specifications of the hard and soft landscape areas as identified and in compliance with the relevant guidance documents. REASON: To ensure that designs, materials and specifications shall be in accordance with the Cherrywood Planning Scheme and to meet with the requirements of the Planning Authority. ### Condition 18 The following shall be submitted to and agreed in writing with the Planning Authority prior to commencement of development or as otherwise agreed; • Detailed design of the streetscape finishes within the Village Centres including samples and specifications of all hard and soft landscape areas as identified and in compliance with the relevant guidance documents. Villages should share an identity through landscape design and as such an agreed suite of finishes and detailed design must be consistent throughout all Villages and agreed in writing with the Planning Authority. Reason: To ensure that designs, materials and specifications shall be in accordance with the Cherrywood Planning Scheme and to meet with the requirements of the Planning Authority. ### Condition 19 The following shall be submitted to and agreed in writing with the Planning Authority prior to commencement of development or as otherwise agreed ; • Loss of potential roost features in trees to be felled should be compensated for by erection of bat boxes; the number and type to be agreed with the National Parks and Wildlife Service (NPWS) or as otherwise agreed via a Bat derogation licence to be applied for from the NPWS. • Prior to the commencement of development, the developer shall engage the services of a qualified ecologist as an ecological consultant, from the commencement of construction to 5 year post-completion. The developer shall inform the Planning Authority in writing of the appointment and name of the consultant prior to commencement of development. The consultant shall ensure the implementation of the all of the relevant recommendations in the submitted EIS. Reports shall be submitted to the Planning Authority at agreed intervals. Reason: In order to be consistent with Objective GI 43 of the Cherrywood Planning Scheme and in the interests of proper planning and sustainable development. ### Condition 20 The following shall be submitted to and agreed in writing with the Planning Authority prior to commencement of development or as otherwise agreed; • The developer shall engage the services of a qualified arborist as an arboricultural consultant, for the entire period of construction activity. The developer shall inform the Planning Authority in writing of the appointment and name of the consultant, prior to commencement of development. The consultant shall visit the site on a monthly basis, to ensure the implementation of all of the relevant recommendations in the submitted EIS. REASON: To ensure the protection and long term viability of trees to be retained on site. ### Condition 21 Prior to commencement of development, the developer shall submit for the written agreement of the Planning Authority details of the installation of a protective fencing, on the Hydrogeological Study zone as detailed on Appendix E of the Cherrywood Planning Scheme. The location of the fence to be agreed in writing with the Planning Authority. REASON: To ensure consistency with Objective GI 61 of the Planning Scheme and in the interests of proper planning and sustainable development. ### Condition 22 Prior to commencement of development the developer shall submit for the written agreement of the Planning Authority, all drawings in digital format (CAD/GIS) projected to ITM (Irish Transverse Mercator). REASON To ensure consistency with the Cherrywood Planning Scheme. ### Condition 23 The phasing for the completion of construction works, including finishes, shall be agreed in writing with the Planning Authority in advance of the application of the final finishes. Reason: In the interests of orderly development and visual amenity, to ensure the appropriate timing of construction works, in particular having regard to ensure that over ground finishes are not inappropriately completed in advance of their final commissioning and opening to public use. ### Condition 24 The developer shall comply with recommendations of the Quality Audit carried out by Arup (June 2016) for the proposed development. A Stage 2 independent Quality Audit including a Road Safety Audit shall be carried out for the detailed design stage at the developers’ expense in accordance with the Design Manual for Urban Roads & Streets (DMURS) guidance. The independent audit team shall be approved in writing by the Planning Authority and all measures recommended by the Auditor shall be undertaken unless the Planning Authority approves a departure in writing. A feedback report shall also be submitted providing a response to each of the items. Post construction/prior to opening a Stage 3 Road Safety Audit and a post completion Quality Audit shall be carried out at the developers’ expense in accordance with the Design Manual for Urban Roads & Streets (DMURS) and Transport Infrastructure Ireland (TII) standards. The independent audit team/s shall be agreed by the Planning Authority. All measures recommended by the Auditor shall be undertaken unless the Planning Authority agrees a departure in writing. A feedback report shall also be submitted providing a response to each of the items. REASON: In the interests of traffic and pedestrian and cyclists safety and the proper planning and sustainable development of the area. ### Condition 25 The developer shall comply with the recommendations of the Construction Management Plan by Arup (June 2016), or as otherwise agreed in writing with the Planning Authority, including preparation of a Community Liaison Plan. Prior to commencement of development the Construction Management Plan shall be submitted for agreement of the Planning Authority. REASON: In the interests of orderly development and the residential amenity of the area. ### Condition 26 Prior to commencement of development a mechanism and structure for on-site monitoring, reporting on progress and quality control to the Planning Authority in relation to construction standards, materials, as-built drawings and records shall be agreed in writing with the Planning Authority. REASON: In the interests of orderly development and the proper planning and sustainable development of the area. ### Condition 27 The developer shall arrange with the Planning Authority for the removal, required by the Planning Scheme, of paid parking along public roads. The timing and implementation of paid parking removal shall be agreed, in writing, in advance with the Planning Authority. REASON: In the interests of orderly development and the proper planning and sustainable development of the area. ### Condition 28 All development works shall be designed and constructed to meet Dún Laoghaire-Rathdown County Council's 'Taking-in-Charge' requirements 'Taking In Charge Policy Document (September, 2011 - updated April, 2013)': http://www.dlrcoco.ie/media/media,7464,en.doc and 'Taking in Charge Procedure Document': http://www.dlrcoco.ie/media/media,10719,en.pdf, and all to the satisfaction of the Planning Authority at the developers' own expense. REASON: In the interests of orderly development and the proper planning and sustainable development of the area. ### Condition 29 The developer shall ensure that prior to undertaking works to be carried out on the public road (including on footpaths) that they shall obtain a Road Opening Licence from the Planning Authority. REASON: In the interests of orderly development and the proper planning and sustainable development of the area. ### Condition 30 The retained hedges shall be protected during the course of construction by a temporary fence, in accordance with the default specification of barrier fencing shown in BS 5837: 2012 Trees in relation to design, demolition and construction – recommendations (in Figs 2, 3), or a 1.5 metre high robust timber post and rail fence or similar approved and agreed with the Planning Authority. The fence shall be installed along the inside of the hedges, so that vulnerable Root Protection Zone, as determined by the qualified arborist, is protected. Notices are to be placed on all protective fences stating that the trees within the fence are protected. REASON: In the interests of protecting the visual character and quality of the site, visual amenity and local wildlife. ### Condition 31 Prior to the commencement of development the developer shall appoint and retain the services of a qualified Landscape Architect (or qualified Landscape Designer) as a Landscape Consultant, throughout the life of the construction works and shall notify the Planning Authority of that appointment in writing prior to commencement. A Practical Completion Certificate is to be signed off by the Landscape Architect when all landscape works are fully completed to the satisfaction of the Planning Authority and in accordance with the permitted landscape proposals. REASON: In the interests of visual amenity and orderly development and to ensure full and verifiable implementation of the approved landscape design ### Condition 32 Prior to commencement of development the developer shall carry out an acoustic baseline noise survey which shall include continuous monitoring over a 72 hour period. The results of this survey shall be forwarded to both the Planning Authority and the Environmental Health Office of Fingal County Council. REASON: To achieve a baseline noise survey to assess future development, in the interests of residential amenity and the proper planning and sustainable development of the area. ### Condition 33 The developer shall comply with the following during the construction phase: i) No outdoor burning shall occur on site. The site must be secured to prevent access by third parties. ii) All necessary steps shall be taken to contain dust and airborne pollutants arising from the site. This shall include covering skips, covering slack heaps, netting of scaffolding, use of water spray to suppress dust, proper paved or hard standing access for trucks and vehicles to and from the site to prevent dirt and dust from the site being carried from the site onto public roads etc. iii) Use of rubble chutes and receptor skips during construction activities. iv) During dry periods dust emissions from heavily trafficked locations (on and off site) shall be controlled by spraying surfaces with water and wetting agents. v) Hard surface roads shall be swept to remove mud and aggregate materials from their surface. vi) Overloading of any tipper trucks exiting the site shall not be permitted. vii) Any aggregates transported to and from the site shall be covered out in covered trucks. viii) The site shall be dampened down at regular intervals during activities likely to create dust. ix) Water misting/sprays shall be available onsite and used at regular intervals during activities likely to create dust. x) Material stockpiles containing fine or dusty elements shall be covered with tarpaulins. xi) Wind break/barriers shall be erected when there are any activities involving drilling or pavement cutting, grinding, stone finishing operations etc. taking place. xii) Dust control measures should be active on equipment used for drilling or pavement cutting, grinding of block surfaces or similar types of stone finishing. xiii) All site vehicles and machinery shall be switched off when not in use. xiv) A temporary wheel wash facility shall be installed close to the location of the site entrance. xv) Exposed surfaces and entrances to the sites shall be dampened during dry windy conditions. xvi) Any spillage of material from vehicles departing from the site shall be promptly removed. xvii) A programme of dust monitoring shall be carried out at locations adjacent to the site boundaries and shall be made available to the Planning Authority on request. The amount of dust deposited anywhere outside the site, when averaged over a thirty day period, should not exceed 130mg/m2 per day when measured according to the BS method which takes account of insoluble components only or 350mg/m2 per day when measured according to TA Luft, which includes both. REASON: In the interests of the amenity of the area and the proper planning and sustainable development of the area. ### Condition 34 As there is the potential for undermining the boundary wall of Lehaunstown Park House the developer shall undertake a Structural/Condition Survey of the granite wall, to include elevation survey drawings along the entire length of the wall, identifying method of construction and mortar analysis, identifying areas of deterioration or loss of mortar and a Method Statement for any repairs necessitated in accordance with good conservation practice and shall submit this for the written agreement of the Planning Authority prior to the commencement of any development within a 50 metre buffer zone of the boundary of Lehaunstown Park House. REASON: In the interests of the protection of the protected structure and recorded monument, in the interests of visual amenity and the proper planning and sustainable development of the area. ### Condition 35 Prior to the commencement of development, the developer shall confirm in writing that they are satisfied that the landscape proposals comply with the Planning Authority’s Guidelines for The Development and Taking-in-Charge of Public Open Space. Upon completion of the works, the Landscape Architect (or qualified Landscape Designer) as a Landscape Consultant, shall provide a Certificate/Letter stating that all landscape works are fully completed and compliant with the Guidelines for The Development and Taking-in-Charge of Public Open Space. REASON: To ensure that designs, materials and specifications shall meet with the requirements of the Planning Authority and in the interests of proper planning and sustainable development. ### Condition 36 Upon completion of the works, the developer shall provide a Certificate/Letter stating that all works are fully completed and compliant with the Planning Authority’s Guidelines for The Development and Taking-in-Charge of Public Open Space. All Planning Authority policies and procedures must be adhered to in relation to the Taking in Charge process. A Safety File including all Operations and Maintenance Manuals and ‘as built’ drawings shall be provided upon Taking in Charge. The roads and infrastructure shall be completed in its entirety prior to it being open to the public or for any other use or as agreed with the Planning Authority. Within 12 months of completing and opening the roads and infrastructure and at the discretion of the Planning Authority, the developer shall undertake all remediation works required to bring the roads and infrastructure up to the Taking in Charge standards and hand over the roads and infrastructure to the Planning Authority. REASON: To ensure that designs, materials and specifications shall meet with the requirements of the Planning Authority and in the interests of the proper planning and sustainable development of the area. ### Condition 37 Prior to the commencement of development or any related construction activity or tree felling on the site, the applicant shall lodge a Tree and Hedgerow Bond to the value of €150,000.00 with the Planning Authority. This is to ensure the protection of trees on and immediately adjacent to the site to make good any damage caused during the construction period. The bond lodgement shall be coupled with an Arboricultural Agreement, with the developer, empowering the Planning Authority to apply such security, or part thereof, to the satisfactory protection of any tree/hedgerow or trees/hedgerows on or immediately adjoining the site, or the appropriate and reasonable replacement of any such trees/hedgerows which die, are removed or become seriously damaged or diseased within a period of three years from the substantial completion of the development. Any replacement planting shall use large semi-mature tree size(s) and species or similar as may be stipulated by the planning authority. An Arboricultural Assessment Report and Certificate is to be signed off by a qualified Arborist after the period of 3 years of completion of the works. Any remedial tree surgery, tree felling works recommended in that Report and Certificate shall be undertaken by the developer, under the supervision of the Arborist. The bond will only be refunded upon receipt by the Planning Authority of a satisfactory post-construction arboricultural assessment, carried out by a qualified arborist and provided that the retained hedges/trees are alive, in good condition with a useful life expectancy. REASON: In the interest of visual amenity and to ensure the protection, safety, prudent retention and long-term viability of trees to be retained on and immediately adjacent to the site. ### Condition 38 No development on foot of this permission shall commence until security for the provision and satisfactory completion of the proposed development in accordance with the plans and particulars lodged with the application and to Planning Authority Standards, has been given by: a) Lodgement with the Council of an approved Insurance Company Bond in the sum of €3,817,470.00 which shall be kept in force by the developer until such time as the proposed development road works are completed to the satisfaction of the Council OR: b) Lodgement with the Council of a Cash Sum of €3,817,470.00 to be applied by the Council at its absolute discretion if the road works are not completed to its satisfaction. ### Condition 2 The proposed rerouting of the 450mm Foul sewer along Tully Vale Road and West Courtyard to connect with the existing Carrickmines Trunk sewer in Lehaunstown Valley shall be as per the revised drawings submitted by way of Further Information on 22nd June, 2016. REASON: In the interest of clarity. ## Nearby applications - [DZ26B/0366/WEB](https://cherrywoodplans.com/application/DZ26B-0366-WEB.md): 10 Domville Square, Cherrywood, Dun Laoghaire, Dublin 18, D18H7WA. Granted (14 Aug 2026). Adds a small glass conservatory to the rear of a house at Domville Square. - [DZ26B/0360/WEB](https://cherrywoodplans.com/application/DZ26B-0360-WEB.md): 10, Domville Square, Cherrywood, Dun Laoghaire, Dublin 18, D18H7WA. Refused or withdrawn (24 Jun 2026). A small glass conservatory added to the back of a house on Domville Square. - [DZ15A/0813](https://cherrywoodplans.com/application/DZ15A-0813.md): Laughanstown, Dublin 18, (Tully Park). Granted (13 Jul 2016). Creates Tully Park, a 12.9-hectare public park with a playground, café kiosk and nature trails. - [DZ20A/0946](https://cherrywoodplans.com/application/DZ20A-0946.md): Lands known as Tully Park (c12.9HA), Laughanstown, Dublin 18. Granted (18 Feb 2021). Revises part of the permitted Tully Park, moving the café kiosk, redesigning the playground and adding a raised boardwalk. - [DZ24A/0236/WEB](https://cherrywoodplans.com/application/DZ24A-0236-WEB.md): Lands in the townland of Laughanstown, between Grand Parade and Tully Park, in Domville Development Area 4, Cherrywood, Dublin 18. Refused or withdrawn (15 Apr 2024). Amends the Domville permission to raise four blocks on Grand Parade from 4 to 6 storeys, adding 58 apartments. - [DZ17A/0714](https://cherrywoodplans.com/application/DZ17A-0714.md): Lands in the townlands of Lehaunstown and Cherrywood, Dublin 18. The application relates to development in the Cherrywood Strategic Development Zone.(Domville site). Granted (7 Aug 2018). Builds 322 new homes, 242 apartments and 80 houses, plus a crèche on the Domville site in Cherrywood. - [DZ26A/0151/WEB](https://cherrywoodplans.com/application/DZ26A-0151-WEB.md): In the Townlands of Laughanstown and Cherrywood, in Cherrywood, Dublin 18.. Granted (24 Jun 2026). 188 new homes, a mix of apartments, two-level units and houses, beside Tully Park off Bishop Street. - [DZ22A/0133](https://cherrywoodplans.com/application/DZ22A-0133.md): Townlands of Laughanstown and Cherrywood, Dublin 18. Granted (22 Nov 2022). Builds 163 homes, a mix of apartments, triplexes, maisonettes and houses, beside Tully Park. - [DZ21A/0806](https://cherrywoodplans.com/application/DZ21A-0806.md): Lands in the townland of, Laughanstown, Dublin 18, located between Grand Parade and Tully Park. Granted (12 Aug 2022). Amends a permitted scheme between Grand Parade and Tully Park to add 60 apartments in three new 4-storey blocks. - [DZ24A/0291/WEB](https://cherrywoodplans.com/application/DZ24A-0291-WEB.md): Lands in the townland of Laughanstown, Dublin 18, located between Grand Parade and Tully Park., The application relates to development in Domville Development Area 4 of the Cherrywood Strategic Development Zone.. Granted (25 Mar 2025). Amends the Domville permission to raise four blocks on Grand Parade from 4 to 6 storeys, adding 58 apartments. - [DZ25A/0489/WEB](https://cherrywoodplans.com/application/DZ25A-0489-WEB.md): 20, Domville Court, Tullyvale, Cherrywood, Dublin 18, D18VN3A. Granted (11 Aug 2025). Permission to keep a glass conservatory permanently at the back of a house on Domville Court. - [DZ25A/0480/WEB](https://cherrywoodplans.com/application/DZ25A-0480-WEB.md): 20, Domville Court, Tullyvale, Cherrywood, Dublin 18, D18VN3A. Refused or withdrawn (19 Jun 2025). Permission to keep a glass conservatory at the back of a house on Domville Court. - [DZ26B/0030/WEB](https://cherrywoodplans.com/application/DZ26B-0030-WEB.md): 17 Domville Court, Tullyvale, Cherrywood, Dublin 18, D18 WEK6. Refused or withdrawn (28 Jan 2026). Permission to keep a glass conservatory built in the back garden of a house on Domville Court. - [DZ26B/0241/WEB](https://cherrywoodplans.com/application/DZ26B-0241-WEB.md): 17 Domville Court, Cherrywood, Dublin 18, D18WEK6. Granted (10 Jun 2026). Permission to keep a glass conservatory permanently in the back garden of a house on Domville Court. - [DZ26B/0073/WEB](https://cherrywoodplans.com/application/DZ26B-0073-WEB.md): 17 Domville Court, Cherrywood, Dublin 18, D18WEK6. Refused or withdrawn (13 Mar 2026). Permission to keep a glass conservatory built in the back garden of a house on Domville Court. - [DZ21A/1042](https://cherrywoodplans.com/application/DZ21A-1042.md): Townlands of Laughanstown, Brennanstown and Cherrywood, Dublin 18. Granted (30 May 2022). 122 new homes, a mix of houses, two-level units and apartments, beside Tully Park and Lehaunstown Lane. - [D03A/0735](https://cherrywoodplans.com/application/D03A-0735.md): Tullyvale, Druid Valley, Cherrywood, Loughlinstown, Co. Dublin.. Granted (22 Sep 2003). Changes the approved Tullyvale housing development by realigning its access road and adding a signalised pedestrian crossing. - [DZ25A/0161/WEB](https://cherrywoodplans.com/application/DZ25A-0161-WEB.md): Lands in the townlands of Laughanstown, Dublin 18. The application relates to development in Cherrywood Strategic Development Zone. Granted (23 Apr 2025). Completion of a 145-metre stretch of Grand Parade from Tully Vale Road towards Bishop Street. - [ABP30342919](https://cherrywoodplans.com/application/ABP30342919.md): Site (c.3.06ha) in the townlands of Laughanstown, Dublin 18 (lands generally bounded by Bishop Street to the south, the Luas green line to the east and Tully park to the north. Granted (18 Apr 2019). Builds 184 homes, a mix of apartments, two-level units and houses, between Bishop Street, the Luas line and Tully Park. - [D05A/1658](https://cherrywoodplans.com/application/D05A-1658.md): Tullyvale, Druids Valley, Cherrywood, Loughlinstown, Co. Dublin. Refused or withdrawn (22 Feb 2006). 396 homes in 9 buildings of 3 to 8 storeys, with a childcare facility, at Tullyvale, Druids Valley. - [DZ26A/0148/WEB](https://cherrywoodplans.com/application/DZ26A-0148-WEB.md): Townland of Laughanstown, Dublin 18, The site is bounded by Grand Parade and Western Courtyard roads. Granted (20 Jul 2026). 311 new homes and a crèche in buildings of 3 to 6 storeys between Grand Parade and Western Courtyard. - [DZ18A/0458](https://cherrywoodplans.com/application/DZ18A-0458.md): on lands (c.0.74 HA) in the townland of Laughanstown, Dublin 18 (Development Area 8 - Tully). Granted (11 Jul 2018). Builds a new primary school with 24 classrooms plus a special needs unit, south-west of Tully Park. - [DZ25A/0044/WEB](https://cherrywoodplans.com/application/DZ25A-0044-WEB.md): In the Townlands of Laughanstown, and Brennanstown, Dublin 18. Granted (10 Jul 2025). Amends a permitted Lehaunstown scheme to add a storey to two buildings, taking it from 492 to 517 homes, with fewer car spaces. - [DZ21A/0334](https://cherrywoodplans.com/application/DZ21A-0334.md): Townlands of Laughanstown, Brennanstown and Cherrywood, Dublin 18. Granted (7 Apr 2022). 482 new homes, mostly apartments in five blocks up to 5 storeys, beside Barrington's Road and the Luas in Lehaunstown. - [DZ26A/0052/WEB](https://cherrywoodplans.com/application/DZ26A-0052-WEB.md): Townland of Laughanstown, Cherrywood, Dublin 18. Granted (24 Mar 2026). Makes minor layout and landscaping changes to a permitted Tully housing scheme, moving bin stores to the front of the two-level homes. - [DZ22A/0820](https://cherrywoodplans.com/application/DZ22A-0820.md): Townlands of Laughanstown, Brennanstown and Cherrywood,, Dublin 18. Granted (12 Dec 2022). Makes minor changes to the already-permitted 168-home scheme in Tully, swapping the designs of 12 houses and altering some roofs. - [DZ22A/0403](https://cherrywoodplans.com/application/DZ22A-0403.md): Townlands of Laughanstown, Brennanstown and Cherrywood, Dublin 18. Refused or withdrawn (22 Jul 2022). Makes minor changes to the already-permitted 168-home scheme in Tully, swapping the designs of 12 houses and altering some roofs. - [DZ21A/0699](https://cherrywoodplans.com/application/DZ21A-0699.md): Townlands of Laughanstown, Brennanstown and Cherrywood, Dublin 18. Granted (23 Sep 2021). Smaller first-floor bathroom windows on 33 permitted houses in Tully. - [DZ20A/0552](https://cherrywoodplans.com/application/DZ20A-0552.md): Townlands of Laughanstown, Brennanstown and Cherrywood, Dublin 18,. Granted (11 Mar 2021). 163 new homes, mostly houses, between Castle Street and Tully Park. - [DZ21A/1038](https://cherrywoodplans.com/application/DZ21A-1038.md): site 1.85 ha at Castle Street and Bishop Street, Cherrywood, Dublin 18. Granted (8 Nov 2022). Builds a new 1,000-pupil secondary school at Castle Street and Bishop Street, Cherrywood. - [D05A/0162](https://cherrywoodplans.com/application/D05A-0162.md): Druid Valley, Cherrywood, Loughlinstown, Co, Dublin.. Refused or withdrawn (7 Apr 2005). Builds 805 apartments and homes plus a crèche across 50 buildings at Druid Valley, Cherrywood. - [DZ20A/0877](https://cherrywoodplans.com/application/DZ20A-0877.md): Bishop Street, Cherrywood, Dublin 18, Co Dublin. Granted (29 Jan 2021). Installs a small gas regulator building on Bishop Street near the Luas line. - [D04A/1013](https://cherrywoodplans.com/application/D04A-1013.md): Laughanstown/Cherrywood, With Access From N11, Wyattville Road, Co. Dublin.. Refused or withdrawn (9 May 2005). Seeks to keep modified land shaping and drainage works on a 36-hectare site at Laughanstown/Cherrywood and further alter them. - [DZ18A/0499](https://cherrywoodplans.com/application/DZ18A-0499.md): Lands (c.1.22ha) in the townlands of Cherrywood & Laughanstown, Dublin 18. Granted (11 Jan 2019). 146 apartments in four 4-storey blocks off Grand Parade on plot TC5. - [DZ24A/1030/WEB](https://cherrywoodplans.com/application/DZ24A-1030-WEB.md): In the Townlands of Laughanstown and Cherrywood, Cherrywood, Dublin 18. Granted (11 Jun 2025). Amends a permitted scheme off Tully Vale Road to add 59 apartments by raising four blocks by one or two storeys. - [DZ25A/0152/WEB](https://cherrywoodplans.com/application/DZ25A-0152-WEB.md): Land in the townland of Laughanstown, Dublin 18, located north-west of the Tullyvale residential development.The application relates to development in. Granted (11 Jul 2025). Amends an earlier housing permission to shrink the planned basement car park to 13 spaces. - [DZ21A/0414](https://cherrywoodplans.com/application/DZ21A-0414.md): Townland of Laughanstown, Dublin 18. Granted (5 May 2022). 107 new homes, a mix of apartments and houses, north-west of Tullyvale. - [DZ25A/0325/WEB](https://cherrywoodplans.com/application/DZ25A-0325-WEB.md): In the Townlands of Laughanstown and Cherrywood, Cherrywood, Dublin 18. Granted (15 Jan 2026). 121 apartments in two blocks of 3 to 5 storeys off Cherrywood Avenue in Macnebury. - [DZ25A/0102/WEB](https://cherrywoodplans.com/application/DZ25A-0102-WEB.md): In the Townlands of Laughanstown, in Cherrywood, Dublin 18. Granted (26 May 2025). Amends a permitted 200-apartment scheme in Macnebury to drop its basement and cut car parking from 241 to 160 spaces. - [DZ24A/1024/WEB](https://cherrywoodplans.com/application/DZ24A-1024-WEB.md): In the Townlands of Laughanstown and Cherrywood, in Cherrywood,, Dublin 18. Granted (1 May 2025). Amends a permitted Macnebury apartment scheme to cut car parking from 312 to 213 spaces and add bike, bin and storage buildings, with no change to the homes. - [DZ25A/0008/WEB](https://cherrywoodplans.com/application/DZ25A-0008-WEB.md): In the Townlands of Laughanstown and Cherrywood, in Cherrywood, Dublin 18. Refused or withdrawn (6 Feb 2025). Amends a permitted 200-apartment scheme in Macnebury to drop its basement and cut car parking from 241 to 160 spaces. - [DZ24A/1016/WEB](https://cherrywoodplans.com/application/DZ24A-1016-WEB.md): In the Townlands of Laughanstown and Cherrywood, in Cherrywood, Dublin 18. Refused or withdrawn (3 Jan 2025). Amends a permitted Macnebury development by removing its basement and cutting car parking from 241 to 160 spaces. - [DZ24A/0017](https://cherrywoodplans.com/application/DZ24A-0017.md): Townlands of Laughanstown and Cherrywood, Macnebury - Development Area 7 - Cherrywood, Dublin 18. Granted (11 Jun 2024). 200 apartments in three blocks of 4 to 5 storeys off Cherrywood Avenue in Macnebury. - [DZ23A/0811](https://cherrywoodplans.com/application/DZ23A-0811.md): In the Townlands of Laughanstown and Cherrywood. Macnebury, Development Area 7 , Cherrywood, Dublin 18. Refused or withdrawn (4 Jan 2024). 200 apartments in three blocks of 4 to 5 storeys off Cherrywood Avenue in Macnebury. - [DZ22A/1021](https://cherrywoodplans.com/application/DZ22A-1021.md): Lands within Development Area 7 - Macnebury, including part of the Res 3 plot known as M1 located south of Bishop Street, west of Cherrywood Avenue, east and north of the proposed Beckett Road, Laughanstown, Dublin 18. Granted (27 Jun 2023). 283 new homes, mostly apartments in four blocks of 4–5 storeys, plus a crèche, south of Bishop Street in Macnebury. - [DZ20A/0585](https://cherrywoodplans.com/application/DZ20A-0585.md): on a site in the Townlands of Laughanstown and Cherrywood, Dublin 18. Refused or withdrawn (2 Jun 2021). A temporary sales and marketing suite with 8 parking spaces for just under 5 years off Gun and Drum Hill Road. - [DZ25A/0014/WEB](https://cherrywoodplans.com/application/DZ25A-0014-WEB.md): Townlands of Laughanstown & Brennanstown, Dublin 18. Granted (3 Mar 2025). Amends the permitted Tully village centre (plot T1) to shrink the basement, cutting car parking from 210 to 157 spaces. - [DZ23A/0106](https://cherrywoodplans.com/application/DZ23A-0106.md): Lands in the Townlands of Laughanstown and Brennanstown, Dublin 18. Granted (22 Sep 2023). A village centre at Tully with a supermarket, shops, cafés and 139 build-to-rent apartments in two blocks of 3–5 storeys. - [DZ26A/0032/WEB](https://cherrywoodplans.com/application/DZ26A-0032-WEB.md): Block A1, The Tully Building, Civic Street, Cherrywood Town Centre, Dublin 18, D18WDK0. Granted (13 Mar 2026). Revised plan for 24 mobile phone antennas and 9 dishes on Block A1, The Tully Building, after an earlier compliance submission was rejected. - [DZ25A/0485/WEB](https://cherrywoodplans.com/application/DZ25A-0485-WEB.md): Block A1, Tully Buildings, Cherrywood, Dublin 18. Granted (1 Aug 2025). 24 mobile phone antennas and 9 dishes on the facade and roof of Block A1, Tully Buildings. - [DZ17A/0161](https://cherrywoodplans.com/application/DZ17A-0161.md): Lands (site area c.0.95ha) in the townland of Laughanstown, Dublin 18. Granted (12 Dec 2017). Sets up a temporary concrete plant for 7 years to supply the building of Cherrywood. - [D07A/1723](https://cherrywoodplans.com/application/D07A-1723.md): Lehaunstown Bungalow, Lehaunstown Lane, Cabinteely, Co. Dublin. Refused or withdrawn (11 Feb 2008). Demolishes Lehaunstown Bungalow and builds a replacement house. - [REF20225](https://cherrywoodplans.com/application/REF20225.md): Lehaunstown Park House, Laughanstown, Co Dublin, (A Protected Structure). Granted (23 Jan 2026). Minor internal changes to the stable building at Lehaunstown Park House, a protected structure. - [DZ23A/0359](https://cherrywoodplans.com/application/DZ23A-0359.md): Lehaunstown Park House, Lehaunstown Co Dublin. Granted (17 May 2024). Restores Lehaunstown Park House and its tower house, converts the stables to shops, and builds a large garden centre. - [DZ22A/0093](https://cherrywoodplans.com/application/DZ22A-0093.md): Townland of Laughanstown, Dublin 18. Granted (1 Apr 2022). Seeks to keep two advertising signs for Cherrywood housing for 3 more years. - [DZ26A/0750/WEB](https://cherrywoodplans.com/application/DZ26A-0750-WEB.md): Unit B, Mercer Way, Tully Village Centre West, Dublin 18, D18C58F. Refused or withdrawn (7 Oct 2026). Combines two permitted shop units at Tully Village Centre into one convenience store with an off-licence. - [DZ22A/0729](https://cherrywoodplans.com/application/DZ22A-0729.md): Townlands of, Laughanstown, Brennanstown and, Cherrywood, Dublin 18. Granted (22 Sep 2023). 57 new homes, houses and 3-bed two-level apartments, off Gun and Drum Hill Road in Tully. - [DZ22A/0770](https://cherrywoodplans.com/application/DZ22A-0770.md): On Lands Development Area 8 (Tully), Cherrywood SDZ, Laughanstown, Dublin 18. Granted (22 Mar 2023). 71 homes, a crèche, shops and a community room on plot T11 west of Castle Street in Tully village centre. - [DZ23A/0443](https://cherrywoodplans.com/application/DZ23A-0443.md): Lands in the townlands of Laughanstown, Dublin 18, (Lands within 'Development Area 7- Macnebury', including part of the Res 2 plot known as 'M4, located West & South of Castle Street, south of Lehaunstown Lane and North of Bishop Street. Granted (7 Nov 2023). Changes a condition so 66 permitted homes in Macnebury can be occupied before the Cherrywood Avenue/Beckett Road underpass is built. - [DZ21A/0664](https://cherrywoodplans.com/application/DZ21A-0664.md): Site in the Townlands of, Laughanstown, Brennanstown and Cherrywood, Dublin 18. Granted (5 May 2022). 47 apartments in a 4-storey block off Castle Street in Tully. - [DZ21A/1085](https://cherrywoodplans.com/application/DZ21A-1085.md): Lands of Laughanstown, Dublin 18, (Lands within 'Development Area 7- Macnebury', M4, located West & South of Castle Street, south of Lehaunstown Lane and North of Bishop Street. Granted (2 Dec 2022). Builds 65 three-bed homes in five three-storey blocks in Macnebury, west of Castle Street. - [DZ22A/0952](https://cherrywoodplans.com/application/DZ22A-0952.md): The Hunt Building, Grand Parade, Cherrywood Town Centre, Dublin 18. Refused or withdrawn (1 Feb 2023). 6 mobile phone antennas and 2 dishes on the roof of The Hunt Building, Grand Parade. - [DZ22A/0796](https://cherrywoodplans.com/application/DZ22A-0796.md): The Hunt Building, Grand Parade, Cherrywood Town Centre, Dublin 18. Refused or withdrawn (23 Nov 2022). 6 mobile phone antennas and 2 dishes, finished to look like brick, on the roof of The Hunt Building, Grand Parade. - [DZ26A/0580/WEB](https://cherrywoodplans.com/application/DZ26A-0580-WEB.md): Bishop Street (M3a), Laughanstown, Dublin 18 (Development Area 7 Macnebury - Res3 Plot). More information requested (22 Sep 2026). 32 new homes, mostly 3-bed two-level apartments, off Bishop Street in Macnebury. - [DZ19A/0597](https://cherrywoodplans.com/application/DZ19A-0597.md): Development Area 8 -Tully, Cherrywood SDZ, Includes the Res 2 plots ''T9'' and ''T10''. Granted (11 Mar 2020). 184 new homes, mainly houses plus two small apartment blocks, on plots T9 and T10 in Tully. ## Links - [This page on CherrywoodPlans](https://cherrywoodplans.com/application/DZ15A-0758) - [Council record, documents and conditions (DLR planning portal)](https://planning.agileapplications.ie/dunlaoghaire/application-details/69840) - [All Cherrywood applications](https://cherrywoodplans.com/applications.md) _Source: Dún Laoghaire–Rathdown County Council planning data, refreshed daily. CherrywoodPlans is an independent site, not run by the council._