# Planning application DZ15A/0813 > Laughanstown, Dublin 18, (Tully Park), Cherrywood, Dún Laoghaire–Rathdown. Granted (13 Jul 2016). - **Reference:** DZ15A/0813 - **Address:** Laughanstown, Dublin 18, (Tully Park) - **Status:** Granted (13 Jul 2016) - **Decision:** GRANT PERMISSION - **Application type:** Permission (SDZ) - **Applicant:** Hines CDF ICAV & Wm Neville & Sons - **Lodged:** 16 Jun 2016 - **Decided:** 13 Jul 2016 - **Location (lat, lng):** 53.246522, -6.152452 ## Proposal Earthworks/reshaping of existing lands to provide areas of active and passive open space with hard and soft landscaping, public lighting, cctv, new native planting, asphalt and gravel paths (including stepped ramps), cycleways, retaining walls, roads and parking, signage and all ancillary site and development works all on a site extending to c12.9 HA. The site is within Development Area 2 (Cherrywood) identified in the Cherrywood Planning Scheme. The key elements of the Tully Park proposals include the following: 1. Active and passive open space areas include open play areas (grassed), informal playing pitch adjacent to future school site, exploration zones, fitness and play trail, plaza entrance, performance space/seating area, nature trail, biodiversity and nature zone, wildflower/meadow areas woodland spaces/copses, park seating, viewing areas, new native tree, hedgerow and shrub planting, bins, external power sources, signage (information and directional). 2. A formal outdoor playground area (c0.46HA) is proposed with junior and senior play areas, climbing walls, etc. 3. Proposed park kiosk and outdoor terrace area adjacent to playground to include cafe and public toilets (c.125 sq.m gross floor area). 4. Two Level 5 access roads and perimeter roads enclosing park area (these roads are identified on Map 4.5 of the Planning Scheme); vehicular and cycle parking including 2 no. car parking areas (40 no. spaces co-located adjacent to future school site and 16 no. spaces adjacent to play area. 5. Permanent boundary treatments area proposed including low railing (1.2m estate fencing type) to road edges and temporary fencing (1.8m) to secure park prior to opening. 6. Removal of existing vegetation / scrub from outside of perimiter wall to Tully Church and creation of planted earth embankment. Where existing trees are to be retained, additional planting is proposed. No works are proposed to Tully Church, Graveyard of within its grounds (Ref: DU026-023001-2; National Monument No. 225) and these are excluded from the application site. Similarly, no works are proposed to National Monuments including the high crosses (Ref: DU026-023003, 4. 7; National Monument No. 216) which will be maintained in situ and protected during construction. ## In plain English Creates Tully Park, a 12.9-hectare public park with a playground, café kiosk and nature trails. - **12.9** hectares - **56** car spaces - **0.46** hectare playground ### What's planned A new public park on about **12.9** hectares in Cherrywood. ### Community Open play areas, an informal pitch, a fitness and play trail, a performance space and nature trail. A **0.46**-hectare playground and a **125** sq.m café kiosk with public toilets. ### Transport Access and perimeter roads, cycleways and **56** car spaces (**40** by the future school site, **16** by the playground). ### Heritage Tully Church, its graveyard and the high crosses (national monuments) are excluded and protected during works. ### Environment New native trees, hedgerows and wildflower meadows, with a planted bank outside the church wall. _This summary was written by AI from the proposal text. Check the council record before relying on it._ ## Conditions ### Condition 1 The development to be carried out in its entirety in accordance with the plans, particulars and specifications lodged with the application on 16.12.2015 as amended on 16.06.206, save as may be required by the other conditions attached hereto. REASON: To ensure that the development shall be in accordance with the permission and that effective control be maintained. ### Condition 2 Tully Park shall be available for the use of the proposed adjoining primary and secondary schools. REASON: In the interest of clarity and amenity. ### Condition 3 Prior to the commencement of development or as otherwise agreed, the developer shall submit for the written agreement of the Planning Authority, unless otherwise agreed with the Planning Authority, the following: (i) A Signage Strategy for the Park including directional and wayfinding, shall be submitted and agreed in writing with the Planning Authority prior to commencement of development or as otherwise agreed with the Planning Authority. REASON: In order to comply with Objectives PD 32 of the Cherrywood Planning Scheme and in the interest of visual amenity. ### Condition 4 The normal working hours within the site shall be Monday to Friday between 08:00 and 19:00 hours and Saturday between 08:00 and 14:00 hours with no working on public holidays. The contractor shall not start work any day before 08:00 hours. REASON: In the interests of the residential amenity and the proper planning and sustainable development of the area. ### Condition 5 Prior to commencement of development a mechanism and structure for reporting on progress and quality control to the relevant Planning Authority departments, including the Development Agency, in relation to construction standards, materials, as-built drawings and records shall be agreed in writing. REASON: To ensure that development meets with the standards and quality required by the Planning Authority Development Works Guidance Document and to be consistent with the Cherrywood Planning Scheme. ### Condition 6 The development shall be undertaken in accordance with Section 4.3 (Detailed Mitigation) of Archaeological Assessment received by the Planning Authority on 16.06.2016. The developer shall ensure that appropriate applications for extensions to existing Ministerial Consent in relation to the National Monuments, shall be made prior to the commencement of development. REASON: In the interests of archaeology and to ensure consistency with the Cherrywood Planning Scheme. ### Condition 7 Prior to the commencement of development, the developer shall submit revised drawings for the written agreement of the Planning Authority to show the omission of trees proposed on drawing number 1647-PL-P-02.2-IFP located within the sightline from the High Cross to Lehaunstown Castle in order to re-establish this visual corridor. REASON: To ensure consistency with the Planning Scheme. ### Condition 8 The applicant shall retain the services of an accredited Conservation Architect and Conservation Engineer throughout the duration of the project and shall notify the Planning Authority of that appointment in writing prior to commencement. The Conservation Architect and Conservation Engineer shall carry out a detailed structural and archaeological survey of the boundary wall of Tully Church supervised by the Archaeology consultant. An archaeological drawn, written and photographic survey of the graveyard wall should be carried out in addition to the structural survey. This should include measured plans and wall profiles to the level of individual stones, and including missing stones, and should be carried out following vegetation clearance. On completion of the above surveys, detailed design options/solutions shall be supplied for approval by the Planning Authority, the OPW and the Department of Arts, Heritage and the Gaeltacht. REASON: To protect the archaeological and built heritage of the area and to comply with the Planning Scheme. ### Condition 9 All public realm design details (including bins, lighting, signage etc) in the vicinity of the national / recorded monuments to be agreed with the Planning Authority and evidence of the prior agreement of the OPW and the Department of Arts Heritage and the Gaeltacht to these design details shall be provided to the Planning Authory. REASON: To comply with Objectives H3 and H7 in the Planning Scheme. ### Condition 10 Detailed design of water supply infrastructure including details of connections to individual development plots shall be in accordance with Irish Water specification and requirements. Written evidence of the design compliance with Irish Water specification and requirements and copies of the final detail design shall be provided to the Planning Authority prior to the commencement of development. REASON: In the interests of orderly development, consistency with Objective PI 4 of the Planning Scheme and the proper planning and sustainable development of the area. ### Condition 11 With regard to storm water infrastructure the developer shall undertake the following: i)The minimum size storm sewer serving a road gully shall be 225mm. ii) Prior to the commencement of development the detailed design of the road drainage shall be submitted for the written agreement of the Planning Authority. iii) No overland flows onto public roadways from individual sites are permitted during storm event up to the 1 in 100 year return period. iv) Prior to the commencement of development, an operations and management plan for the proposed sustainable urban drainage components (inclusive of the attenuation ponds and basins) shall be agreed in writing with the Planning Authority. REASON: To ensure long term optimum operation of the surface water management system, in the interests of orderly development, consistency with Objectives PI 6, PI 7, PI 8 and PI 9 of the Planning Scheme and the proper planning and sustainable development of the area. ### Condition 12 In the event that permission is not granted for the proposed regional attenuation pond (to the rear of Druid Valley) in advance of commencement of the proposed development an alternative proposal shall be agreed in writing with the Planning Authority. REASON: In the interest of the proper planning and sustainable development of the area. ### Condition 13 Detailed design of foul water drainage including details of connections to individual development plots shall be in accordance with Irish Water specification and requirements. Written evidence of the design compliance with Irish Water specification and requirements and copies of the agreed detail design shall be submitted and agreed in writing with the Planning Authority prior to commencement of development. REASON: In the interests of orderly development, consistency with Objective PI 12 of the Planning Scheme and the proper planning and sustainable development of the area. ### Condition 14 Prior to commencement of development, the developer shall submit for the written agreement of the Planning Authority the detailed design of the roads and streets in accordance with Map 4.5, Figure 4.4 and the current revisions of the design guidance documents listed in Section 4.2.7 of the Planning Scheme, namely: • Traffic Management Guidelines (DoELG, DoT and DTO – 2003) • National Cycle Manual (NTA – 2011) • Design Manual for Roads and Bridges (TII) • Manual for Streets (DfT (UK) – 2007) • Design Manual for Urban Roads and Streets (DTTAS – 2013) • Development Works Guidance Document (DLRCC) REASON: To ensure consistency with Objectives PI 14, Map 4.5 and Figure 4.4 of the Planning Scheme, in the interests of traffic safety, the amenity of the area and the proper planning and sustainable development of the area. ### Condition 15 Detailed design of the electricity supply network shall be agreed in writing with ESB Networks/ESBI. Written evidence of this agreement shall be provided to the Planning Authority prior to commencement of development. REASON: In the interest of orderly development, to ensure that design shall meet with the current and future requirements of ESB Networks/ESBI and in the interest of the proper planning and sustainable development of the area. ### Condition 16 Detailed design of the gas network shall be agreed in writing with Gas Networks Ireland. Written evidence of this agreement shall be provided to the Planning Authority prior to commencement of development. REASON: In the interest of orderly development, to ensure that design shall meet with the current and future requirements of Gas Networks Ireland and in the interest of the proper planning and sustainable development of the area. ### Condition 17 Detailed design of the telecoms network shall be agreed in writing with the telecoms providers. Written evidence of these agreements shall be provided to the Planning Authority prior to commencement of development. REASON: In the interests of orderly development, to ensure that designs shall meet with the current and future requirements of the telecoms providers, to ensure consistency with Objective PI 26 of the Planning Scheme and in the interest of the proper planning and sustainable development of the area. ### Condition 18 Detailed design of the fibre network shall be agreed in writing with the Planning Authority. REASON: In the interests of orderly development, to ensure that designs shall meet with the current and future requirements of the Planning Authority and in the interest of the proper planning and sustainable development of the area. ### Condition 19 Prior to commencement of development detailed design of public lighting complying with ‘Public Lighting Installations in Residential and Industrial Areas Guidance Document – February 2015’ (Dun Laoghaire Rathdown County Council) shall be agreed in writing with the Planning Authority. REASON: To ensure that designs shall meet with the requirements of the Planning Authority, in the interests of consistency with Objective PI 28 of the Planning Scheme, the documents listed in Section 4.2.7 of the Planning Scheme and the proper planning and sustainable development of the area. ### Condition 20 The location of charge points for electric vehicles shall be in accordance with the requirements of the Planning Authority. Prior to the commencement of development six copies of the final detail design shall be provided to the Planning Authority. REASON: To ensure that designs shall be consistent with the Planning Scheme and in the interests of the proper planning and sustainable development of the area. ### Condition 21 Prior to the commencement of development details and locations of bring centres, refuse collection points and provision for recycling and composting at suitable locations shall be agreed in writing with the Planning Authority. REASON: To ensure that designs shall be consistent with the Planning Scheme and in the interest of the proper planning and sustainable development of the area. ### Condition 22 Prior to the commencement of development the developer shall submit detailed design, including samples and specifications, of the hard and soft landscape areas including all play and sports facilities as identified and in compliance with the relevant guidance documents for the written approval of the Planning Authority or as otherwise agreed with the Planning Authority. Approved control samples to be held on site at all times. The materials shall be high quality and shall include a large percentage of natural stone. REASON: To ensure that designs, materials and specifications shall be in accordance with the Cherrywood Planning Scheme, to meet with the requirements of the Planning Authority, in the interests of the amenity and the proper planning and sustainable development of the area. ### Condition 23 Prior to the commencement of development or as otherwise agreed, the developer shall submit detailed design, including samples and specifications, of the proposed universal access route (as shown on dwg no 1647-TU_PL_P_01_IFP) including samples and specifications of the hard and soft landscape areas as identified and in compliance with the relevant guidance documents for the written approval of the Planning Authority or as otherwise agreed with the Planning Authority. REASON: To ensure that designs, materials and specifications shall be in accordance with the Cherrywood Planning Scheme, to meet with the requirements of the Planning Authority, in the interests of the amenity and the proper planning and sustainable development of the area. ### Condition 24 Prior to the commencement of development, the developer shall engage the services of a qualified ecologist as an ecological consultant, from the commencement of construction to 5 year post-completion. The developer shall inform the Planning Authority in writing of the appointment and name of the consultant, prior to commencement of development. The consultant shall ensure the implementation of the all of the recommendations in the submitted Ecological Impact Assessment and submit a report to the Planning Authority certifying that the proposed development accords with the recommendations of the submitted Ecological Impact Assessment. REASON: In the interest of the protection of the natural environment and the proper planning and sustainable development of the area. ### Condition 25 The removal of the vegetation around the wall surrounding Tully graveyard should be supervised by the ecological consultant with a brief to preserve as many as possible of the root stock of the plants currently growing in the area. Any plan subsequently adopted regarding the reconstruction of the churchyard and an embankment to surround should preserve as much of the existing vegetation occurring there (including two elm trees) as is feasible. The Prior written agreement of the Department of Arts Heritage and the Gaeltacht shall be obtained in this regard and submitted to the Planning Authority. REASON: In the interest of the protection of the natural environment and the proper planning and sustainable development of the area. ### Condition 26 Prior to the commencement of development, the developer shall engage the services of a qualified arborist as an arboricultural consultant, for the entire period of construction activity. The developer shall inform the Planning Authority in writing of the appointment and name of the consultant, prior to commencement of development. The consultant shall visit the site on a monthly basis and ensure the implementation of all of the recommendations in the planning application including all the recommendations pertaining to tree retention, tree protection and tree works, as detailed in the Arboricultural Method Statement and Tree Protection Plan in the submitted tree report. All tree felling, surgery and remedial works shall be completed upon completion of the works. All works on the trees to be retained shall comply with proper arboricultural techniques conforming to BS 3998: 2010 Tree Work – Recommendations. The clearance of any vegetation including trees and scrub should be carried out outside the bird-breeding season (1 March – 31 August inclusive) or as stipulated under the Wildlife Acts 1976 and 2000. The arborist shall carry out a post construction tree survey and assessment on the condition of the retained trees. A completion certificate is to be signed off by the arborist when all permitted development works are completed and in line with the recommendations of the tree report. The certificate shall be submitted to the Planning Authority for written agreement upon completion of the works REASON: In the interest of visual amenity and the protection of the natural environment, to ensure the protection and long-term viability of trees to be retained on the site and in the interest of the proper planning and sustainable development of the area. ### Condition 27 In order to comply with the policies set out in the Parks Biodiversity Policy, the developer shall submit, prior to Taking in Charge and for the written agreement of the Planning Authority, a hedgerow maintenance plan for the park where individual hedges are cut at 3-year intervals. REASON: To ensure that green infrastructure is consistent with the provisions of the current Parks Biodiversity Policy of the Planning Authority, consistency with Objective GI 47 of the Planning Scheme, to meet with the requirements of the Planning Authority and in the interests of visual amenity, the protection of the natural environment and the proper planning and sustainable development of the area. ### Condition 28 Prior to the commencement of development the developer shall submit, for the written agreement of the Planning Department revised drawings showing the detailed design of the proposed Greenway along the North/West omitted and replaced with an indication of the future Greenway to be provided as part of the development of the adjacent plot to the north. REASON: In order to be consistent with the Cherrywood Planning Scheme. ### Condition 29 Prior to commencement of development the developer shall submit for the written agreement of the Planning Authority, all drawings in digital format (CAD/GIS) projected to ITM (Irish Transverse Mercator). REASON: To ensure consistency with Section 7.4 of the Cherrywood Planning Scheme. ### Condition 30 The developer shall prevent any mud, dirt, debris or building material being carried onto or placed on the public road or adjoining property(s) as a result of the site construction works and repair any damage to the public road arising from carrying out the works. REASON: In the interests of traffic safety and residential amenity. ### Condition 31 Prior to the commencement of any permitted development or any related construction activity or tree felling on the site, the applicant shall lodge a Tree and Hedgerow Bond to the value of €100,000.00 with the Planning Authority. This is to ensure the protection of trees on and immediately adjacent to the site to make good any damage caused during the construction period. The bond lodgement shall be coupled with an Arboricultural Agreement with the developer, empowering the planning authority to apply such security, or part thereof, to the satisfactory protection of any tree/hedgerow or trees/hedgerows on or immediately adjoining the site, or the appropriate and reasonable replacement of any such trees/hedgerows which die, are removed or become seriously damaged or diseased within a period of three years from the substantial completion of the development. Any replacement planting shall use large semi-mature tree size(s) and species or similar as may be stipulated by the Planning Authority. An Arboricultural Assessment Report and Certificate is to be signed off by a qualified Arborist after the period of 3 years of completion of the works. Any remedial tree surgery, tree felling works recommended in that Report and Certificate shall be undertaken by the developer, under the supervision of the Arborist. The bond will only be refunded upon receipt by the Planning Authority of a satisfactory post-construction arboricultural assessment, carried out by a qualified arborist and provided that the retained hedges/trees are alive, and in good condition with a useful life expectancy. REASON: In the interest of visual amenity and the protection of the natural environment and to ensure the protection, safety, prudent retention and long-term viability of trees to be retained on and immediately adjacent to the site. ### Condition 32 The arborist shall carry out a post-construction assessment on the condition of the hedges, and submit a report of that assessment to the Planning Authority for written agreement upon completion of the permitted development. The hedges to be retained shall be protected during the course of construction by a temporary fence, in accordance with the default specification of barrier fencing shown in BS 5837: 2012 Trees in relation to design, demolition and construction – recommendations (in Figs 2, 3), or a 1.5 metre high robust timber post and rail fence or similar approved and agreed with the Planning Authority. The fence shall be installed along the inside of the hedges, so that vulnerable Root Protection Zones, as determined by the qualified arborist, are protected. Notices are to be placed on all protective fences stating that the trees within the fence are protected. REASON: In the interests of protecting the visual character and quality of the site and of local wildlife and the proper planning and sustainable development of the area. ### Condition 33 Prior to the commencement of any development on site the developer shall appoint and retain the services of a qualified Landscape Architect (or qualified Landscape Designer) as a Landscape Consultant throughout the life of the construction works and shall notify the Planning Authority of that appointment in writing prior to commencement. A Practical Completion Certificate is to be signed off by the Landscape Architect when all landscape works are fully completed to the satisfaction of the Planning Authority and in accordance with the permitted landscape proposals. REASON: In the interest of visual amenity, to ensure that the development shall be in accordance with the permission and that effective control be maintained. ### Condition 34 The development shall be consistent with the following requirements: a) All steel to be galvanised and powder coated (may include some stainless steel finishes) including lighting, floodlighting, fencing, street furniture etc. to an agreed ral colour. No galvanized finish will be accepted. b) Exact locations and details for Wifi hotspots, CCTV and security system shall be agreed with the Planning Authority prior to commencement of any development on site. c) All public lighting and floodlighting should be LED lighting and ducted with suitable access chambers for future maintenance to be agreed with the Planning Authority prior to commencement of any permitted development. d) Additional spare duct routes and quantities for future development to be agreed with the Local Authority and the Development Agency prior to commencement of any permitted development. e) The kick-about area should be suitably drained using a perforated land drain system with slit drains and exact details to be agreed with the Local Authority and the Development Agency prior to commencement of any permitted development. REASON: In the interest of visual amenity, to ensure that designs, materials and specifications shall meet with the requirements of the Planning Authority and in the interest of the proper planning and sustainable development of the area. ### Condition 35 Prior to the commencement of development or as otherwise agreed revised seating proposals shall be agreed with the Planning Authority which are ‘age friendly’. REASON: To comply with the ‘Dún Laoghaire Rathdown Age Friendly Strategy 2016-2020’, in the interest of the proper planning and sustainable development of the area. ### Condition 36 The playground shall be designed to incorporate natural and structured play and include a significant soft element in the form of grass areas, tree and shrub planting. The playground and outdoor gym shall be designed and constructed to EN1176 and up-to-date annual certifications complying with these requirements should be provided prior to handover/taking in charge. Detail design, schedules, samples and specifications for all play related items within the application areas to be agreed with the Planning Authority prior to commencement of development or as otherwise agreed. REASON: To ensure that designs, materials and specifications shall meet with the requirements of the Local Authority and the Development Agency and in the interests of proper planning and sustainable development. ### Condition 37 Prior to the commencement of development or as otherwise agreed in writing with the Planning Authority the following should be submitted and agreed in writing: (a) The park kiosk windows should be protected from vandalism by using an electronic roller shutter or equivalent type system. (b) The building shall be re-designed to provide toilet facilities to the café users as well as externally accessible toilets. (c) Detail design, schedules, samples and specifications of all elements of the kiosk building (including signage). REASON: To ensure that designs, materials and specifications shall meet with the requirements of the Local Authority and in the interests of proper planning and sustainable development. ### Condition 38 Prior to the commencement of development, the applicant shall confirm in writing that they are satisfied that the landscape proposals comply with DLRs’ Guidelines for The Development and Taking-in-Charge of Public Open Space. Upon completion of the works, the Landscape Architect (or qualified Landscape Designer) as a Landscape Consultant, shall provide a Certificate/Letter stating that all landscape works are fully completed and compliant with DLRs’ Guidelines for The Development and Taking-in-Charge of Public Open Space. All DLR’s policies and procedures must be adhered to in relation to the Taking in Charge process. A Safety File including all Operations & Maintenance Manuals and ‘As Built’ drawings shall be provided upon Taking in Charge. The park shall be completed in its entirety prior to it being open to the public or for any other use or as agreed with the Planning Authority. Within 12 months of completing and opening the park and at the discretion of the Local Authority, the applicant shall undertake all remediation works required to bring the park up to the Taking in Charge standards and hand over the park to the Local Authority. Upon completion of the park, the park shall immediately be made available for public use and in particular the schools in Cherrywood. REASON: To ensure that designs, materials and specifications shall meet with the requirements of the Local Authority and in the interests of proper planning and sustainable development. ### Condition 39 No development on foot of this permission shall commence until security for the provision and satisfactory completion of Tully Park in accordance with the Plans and particulars lodged with the application and to Local Authority Standards, has been given by:- a) Lodgement with the Council of an approved Insurance Company Bond in the sum of €4.78 million which shall be kept in force by the Developer until such time as Tully Park is completed to the satisfaction of the Council OR/... b) Lodgement with the Council of a Cash Sum of €4.78 million to be applied by the Council at its absolute discretion if the park is not completed to its satisfaction on the provision and completion of such services to standard specifications. REASON: To ensure that a ready sanction may be available to the Local Authority to ensure the satisfactory completion of the development of this park and in the interests of sustainable development. ### Condition 40 The Applicant shall comply with recommendations of the Quality Audit carried out by Arup (December, 2015) for the proposed development. A Stage 2 independent Quality Audit including a Road Safety Audit shall be carried out for the detailed design stage at the Applicants expense in accordance with the Design Manual for Urban Roads & Streets (DMURS) guidance. The independent audit team shall be approved in writing by the Planning Authority and all measures recommended by the Auditor shall be undertaken unless the Planning Authority approves a departure in writing. A feedback report shall also be submitted providing a response to each of the items. Post construction / prior to opening a Stage 3 Road Safety Audit and a post completion Quality Audit shall be carried out at the Applicants expense in accordance with the Design Manual for Urban Roads & Streets (DMURS) and TII (Transport Infrastructure Ireland) standards. The independent audit team/s shall be approved by Planning Authority. All measures recommended by the Auditor shall be undertaken unless the Planning Authority approves a departure in writing. A feedback report shall also be submitted providing a response to each of the items. REASON: In the interest of Traffic Safety. ### Condition 41 The Applicant shall comply with the recommendations of the submitted Construction Management Plan by Arup (December 2015) including preparation of a Community Liaison Plan. REASON: In the interest of safety. ### Condition 42 All development works (i.e. the proposed roads, street lighting, etc.) shall be designed and constructed to meet Dún Laoghaire-Rathdown County Council's 'Taking-in-Charge' requirements ‘Taking In Charge Policy Document (September, 2011 - updated April, 2013)’: http://www.dlrcoco.ie/media/media,7464,en.doc and ‘Taking in Charge Procedure Document’: http://www.dlrcoco.ie/media/media,10719,en.pdf, and all to the satisfaction of the Planning Authority (Municipal Services Department) at the Applicant’s own expense. REASON: To ensure that development is carried out in accordance with Council Standards in the interest of the proper planning and sustainable development of the area. ### Condition 43 No development on foot of this permission shall commence until security for the provision and satisfactory completion of the proposed development road works in accordance with the Plans and particulars lodged with the application and to Local Authority Standards, has been given by:- a) Lodgement with the Council of an approved Insurance Company Bond in the sum of €336,000.00 excluding VAT which shall be kept in force by the Developer until such time as the proposed development road works are completed to the satisfaction of the Council OR/... b) Lodgement with the Council of a Cash Sum of €336,000.00 excluding VAT to be applied by the Council at its absolute discretion if the road works are not completed to its satisfaction. REASON: To ensure that a ready sanction may be available to the Council to induce the provision of services and prevent disamenity in the development. ## Nearby applications - [DZ20A/0946](https://cherrywoodplans.com/application/DZ20A-0946.md): Lands known as Tully Park (c12.9HA), Laughanstown, Dublin 18. Granted (18 Feb 2021). Revises part of the permitted Tully Park, moving the café kiosk, redesigning the playground and adding a raised boardwalk. - [DZ26A/0151/WEB](https://cherrywoodplans.com/application/DZ26A-0151-WEB.md): In the Townlands of Laughanstown and Cherrywood, in Cherrywood, Dublin 18.. Granted (24 Jun 2026). 188 new homes, a mix of apartments, two-level units and houses, beside Tully Park off Bishop Street. - [DZ22A/0133](https://cherrywoodplans.com/application/DZ22A-0133.md): Townlands of Laughanstown and Cherrywood, Dublin 18. Granted (22 Nov 2022). Builds 163 homes, a mix of apartments, triplexes, maisonettes and houses, beside Tully Park. - [DZ15A/0758](https://cherrywoodplans.com/application/DZ15A-0758.md): in the townlands of Cherrywood, Laughanstown, Brennanstown, Loughlinstown and Glebe, Dublin 18. Granted (16 Aug 2016). Phase 1 roads for Cherrywood: about 5.4km of new and upgraded roads including Grand Parade, Castle Street and Bishop Street. - [DZ18A/0458](https://cherrywoodplans.com/application/DZ18A-0458.md): on lands (c.0.74 HA) in the townland of Laughanstown, Dublin 18 (Development Area 8 - Tully). Granted (11 Jul 2018). Builds a new primary school with 24 classrooms plus a special needs unit, south-west of Tully Park. - [DZ24A/0236/WEB](https://cherrywoodplans.com/application/DZ24A-0236-WEB.md): Lands in the townland of Laughanstown, between Grand Parade and Tully Park, in Domville Development Area 4, Cherrywood, Dublin 18. Refused or withdrawn (15 Apr 2024). Amends the Domville permission to raise four blocks on Grand Parade from 4 to 6 storeys, adding 58 apartments. - [DZ17A/0714](https://cherrywoodplans.com/application/DZ17A-0714.md): Lands in the townlands of Lehaunstown and Cherrywood, Dublin 18. The application relates to development in the Cherrywood Strategic Development Zone.(Domville site). Granted (7 Aug 2018). Builds 322 new homes, 242 apartments and 80 houses, plus a crèche on the Domville site in Cherrywood. - [DZ26B/0366/WEB](https://cherrywoodplans.com/application/DZ26B-0366-WEB.md): 10 Domville Square, Cherrywood, Dun Laoghaire, Dublin 18, D18H7WA. Granted (14 Aug 2026). Adds a small glass conservatory to the rear of a house at Domville Square. - [DZ26B/0360/WEB](https://cherrywoodplans.com/application/DZ26B-0360-WEB.md): 10, Domville Square, Cherrywood, Dun Laoghaire, Dublin 18, D18H7WA. Refused or withdrawn (24 Jun 2026). A small glass conservatory added to the back of a house on Domville Square. - [DZ21A/0806](https://cherrywoodplans.com/application/DZ21A-0806.md): Lands in the townland of, Laughanstown, Dublin 18, located between Grand Parade and Tully Park. Granted (12 Aug 2022). Amends a permitted scheme between Grand Parade and Tully Park to add 60 apartments in three new 4-storey blocks. - [DZ25A/0489/WEB](https://cherrywoodplans.com/application/DZ25A-0489-WEB.md): 20, Domville Court, Tullyvale, Cherrywood, Dublin 18, D18VN3A. Granted (11 Aug 2025). Permission to keep a glass conservatory permanently at the back of a house on Domville Court. - [DZ25A/0480/WEB](https://cherrywoodplans.com/application/DZ25A-0480-WEB.md): 20, Domville Court, Tullyvale, Cherrywood, Dublin 18, D18VN3A. Refused or withdrawn (19 Jun 2025). Permission to keep a glass conservatory at the back of a house on Domville Court. - [ABP30342919](https://cherrywoodplans.com/application/ABP30342919.md): Site (c.3.06ha) in the townlands of Laughanstown, Dublin 18 (lands generally bounded by Bishop Street to the south, the Luas green line to the east and Tully park to the north. Granted (18 Apr 2019). Builds 184 homes, a mix of apartments, two-level units and houses, between Bishop Street, the Luas line and Tully Park. - [DZ24A/0291/WEB](https://cherrywoodplans.com/application/DZ24A-0291-WEB.md): Lands in the townland of Laughanstown, Dublin 18, located between Grand Parade and Tully Park., The application relates to development in Domville Development Area 4 of the Cherrywood Strategic Development Zone.. Granted (25 Mar 2025). Amends the Domville permission to raise four blocks on Grand Parade from 4 to 6 storeys, adding 58 apartments. - [DZ26B/0241/WEB](https://cherrywoodplans.com/application/DZ26B-0241-WEB.md): 17 Domville Court, Cherrywood, Dublin 18, D18WEK6. Granted (10 Jun 2026). Permission to keep a glass conservatory permanently in the back garden of a house on Domville Court. - [DZ26B/0073/WEB](https://cherrywoodplans.com/application/DZ26B-0073-WEB.md): 17 Domville Court, Cherrywood, Dublin 18, D18WEK6. Refused or withdrawn (13 Mar 2026). Permission to keep a glass conservatory built in the back garden of a house on Domville Court. - [DZ26B/0030/WEB](https://cherrywoodplans.com/application/DZ26B-0030-WEB.md): 17 Domville Court, Tullyvale, Cherrywood, Dublin 18, D18 WEK6. Refused or withdrawn (28 Jan 2026). Permission to keep a glass conservatory built in the back garden of a house on Domville Court. - [DZ21A/1038](https://cherrywoodplans.com/application/DZ21A-1038.md): site 1.85 ha at Castle Street and Bishop Street, Cherrywood, Dublin 18. Granted (8 Nov 2022). Builds a new 1,000-pupil secondary school at Castle Street and Bishop Street, Cherrywood. - [DZ21A/1042](https://cherrywoodplans.com/application/DZ21A-1042.md): Townlands of Laughanstown, Brennanstown and Cherrywood, Dublin 18. Granted (30 May 2022). 122 new homes, a mix of houses, two-level units and apartments, beside Tully Park and Lehaunstown Lane. - [DZ25A/0044/WEB](https://cherrywoodplans.com/application/DZ25A-0044-WEB.md): In the Townlands of Laughanstown, and Brennanstown, Dublin 18. Granted (10 Jul 2025). Amends a permitted Lehaunstown scheme to add a storey to two buildings, taking it from 492 to 517 homes, with fewer car spaces. - [DZ21A/0334](https://cherrywoodplans.com/application/DZ21A-0334.md): Townlands of Laughanstown, Brennanstown and Cherrywood, Dublin 18. Granted (7 Apr 2022). 482 new homes, mostly apartments in five blocks up to 5 storeys, beside Barrington's Road and the Luas in Lehaunstown. - [DZ22A/0820](https://cherrywoodplans.com/application/DZ22A-0820.md): Townlands of Laughanstown, Brennanstown and Cherrywood,, Dublin 18. Granted (12 Dec 2022). Makes minor changes to the already-permitted 168-home scheme in Tully, swapping the designs of 12 houses and altering some roofs. - [DZ22A/0403](https://cherrywoodplans.com/application/DZ22A-0403.md): Townlands of Laughanstown, Brennanstown and Cherrywood, Dublin 18. Refused or withdrawn (22 Jul 2022). Makes minor changes to the already-permitted 168-home scheme in Tully, swapping the designs of 12 houses and altering some roofs. - [DZ21A/0699](https://cherrywoodplans.com/application/DZ21A-0699.md): Townlands of Laughanstown, Brennanstown and Cherrywood, Dublin 18. Granted (23 Sep 2021). Smaller first-floor bathroom windows on 33 permitted houses in Tully. - [DZ20A/0552](https://cherrywoodplans.com/application/DZ20A-0552.md): Townlands of Laughanstown, Brennanstown and Cherrywood, Dublin 18,. Granted (11 Mar 2021). 163 new homes, mostly houses, between Castle Street and Tully Park. - [DZ26A/0052/WEB](https://cherrywoodplans.com/application/DZ26A-0052-WEB.md): Townland of Laughanstown, Cherrywood, Dublin 18. Granted (24 Mar 2026). Makes minor layout and landscaping changes to a permitted Tully housing scheme, moving bin stores to the front of the two-level homes. - [DZ25A/0161/WEB](https://cherrywoodplans.com/application/DZ25A-0161-WEB.md): Lands in the townlands of Laughanstown, Dublin 18. The application relates to development in Cherrywood Strategic Development Zone. Granted (23 Apr 2025). Completion of a 145-metre stretch of Grand Parade from Tully Vale Road towards Bishop Street. - [D04A/1013](https://cherrywoodplans.com/application/D04A-1013.md): Laughanstown/Cherrywood, With Access From N11, Wyattville Road, Co. Dublin.. Refused or withdrawn (9 May 2005). Seeks to keep modified land shaping and drainage works on a 36-hectare site at Laughanstown/Cherrywood and further alter them. - [DZ25A/0325/WEB](https://cherrywoodplans.com/application/DZ25A-0325-WEB.md): In the Townlands of Laughanstown and Cherrywood, Cherrywood, Dublin 18. Granted (15 Jan 2026). 121 apartments in two blocks of 3 to 5 storeys off Cherrywood Avenue in Macnebury. - [DZ25A/0102/WEB](https://cherrywoodplans.com/application/DZ25A-0102-WEB.md): In the Townlands of Laughanstown, in Cherrywood, Dublin 18. Granted (26 May 2025). Amends a permitted 200-apartment scheme in Macnebury to drop its basement and cut car parking from 241 to 160 spaces. - [DZ24A/1024/WEB](https://cherrywoodplans.com/application/DZ24A-1024-WEB.md): In the Townlands of Laughanstown and Cherrywood, in Cherrywood,, Dublin 18. Granted (1 May 2025). Amends a permitted Macnebury apartment scheme to cut car parking from 312 to 213 spaces and add bike, bin and storage buildings, with no change to the homes. - [DZ25A/0008/WEB](https://cherrywoodplans.com/application/DZ25A-0008-WEB.md): In the Townlands of Laughanstown and Cherrywood, in Cherrywood, Dublin 18. Refused or withdrawn (6 Feb 2025). Amends a permitted 200-apartment scheme in Macnebury to drop its basement and cut car parking from 241 to 160 spaces. - [DZ24A/1016/WEB](https://cherrywoodplans.com/application/DZ24A-1016-WEB.md): In the Townlands of Laughanstown and Cherrywood, in Cherrywood, Dublin 18. Refused or withdrawn (3 Jan 2025). Amends a permitted Macnebury development by removing its basement and cutting car parking from 241 to 160 spaces. - [DZ24A/0017](https://cherrywoodplans.com/application/DZ24A-0017.md): Townlands of Laughanstown and Cherrywood, Macnebury - Development Area 7 - Cherrywood, Dublin 18. Granted (11 Jun 2024). 200 apartments in three blocks of 4 to 5 storeys off Cherrywood Avenue in Macnebury. - [DZ23A/0811](https://cherrywoodplans.com/application/DZ23A-0811.md): In the Townlands of Laughanstown and Cherrywood. Macnebury, Development Area 7 , Cherrywood, Dublin 18. Refused or withdrawn (4 Jan 2024). 200 apartments in three blocks of 4 to 5 storeys off Cherrywood Avenue in Macnebury. - [DZ22A/1021](https://cherrywoodplans.com/application/DZ22A-1021.md): Lands within Development Area 7 - Macnebury, including part of the Res 3 plot known as M1 located south of Bishop Street, west of Cherrywood Avenue, east and north of the proposed Beckett Road, Laughanstown, Dublin 18. Granted (27 Jun 2023). 283 new homes, mostly apartments in four blocks of 4–5 storeys, plus a crèche, south of Bishop Street in Macnebury. - [DZ17A/0161](https://cherrywoodplans.com/application/DZ17A-0161.md): Lands (site area c.0.95ha) in the townland of Laughanstown, Dublin 18. Granted (12 Dec 2017). Sets up a temporary concrete plant for 7 years to supply the building of Cherrywood. - [D03A/0735](https://cherrywoodplans.com/application/D03A-0735.md): Tullyvale, Druid Valley, Cherrywood, Loughlinstown, Co. Dublin.. Granted (22 Sep 2003). Changes the approved Tullyvale housing development by realigning its access road and adding a signalised pedestrian crossing. - [REF20225](https://cherrywoodplans.com/application/REF20225.md): Lehaunstown Park House, Laughanstown, Co Dublin, (A Protected Structure). Granted (23 Jan 2026). Minor internal changes to the stable building at Lehaunstown Park House, a protected structure. - [DZ23A/0359](https://cherrywoodplans.com/application/DZ23A-0359.md): Lehaunstown Park House, Lehaunstown Co Dublin. Granted (17 May 2024). Restores Lehaunstown Park House and its tower house, converts the stables to shops, and builds a large garden centre. - [D05A/1658](https://cherrywoodplans.com/application/D05A-1658.md): Tullyvale, Druids Valley, Cherrywood, Loughlinstown, Co. Dublin. Refused or withdrawn (22 Feb 2006). 396 homes in 9 buildings of 3 to 8 storeys, with a childcare facility, at Tullyvale, Druids Valley. - [DZ20A/0877](https://cherrywoodplans.com/application/DZ20A-0877.md): Bishop Street, Cherrywood, Dublin 18, Co Dublin. Granted (29 Jan 2021). Installs a small gas regulator building on Bishop Street near the Luas line. - [DZ26A/0148/WEB](https://cherrywoodplans.com/application/DZ26A-0148-WEB.md): Townland of Laughanstown, Dublin 18, The site is bounded by Grand Parade and Western Courtyard roads. Granted (20 Jul 2026). 311 new homes and a crèche in buildings of 3 to 6 storeys between Grand Parade and Western Courtyard. - [DZ23A/0443](https://cherrywoodplans.com/application/DZ23A-0443.md): Lands in the townlands of Laughanstown, Dublin 18, (Lands within 'Development Area 7- Macnebury', including part of the Res 2 plot known as 'M4, located West & South of Castle Street, south of Lehaunstown Lane and North of Bishop Street. Granted (7 Nov 2023). Changes a condition so 66 permitted homes in Macnebury can be occupied before the Cherrywood Avenue/Beckett Road underpass is built. - [DZ21A/1085](https://cherrywoodplans.com/application/DZ21A-1085.md): Lands of Laughanstown, Dublin 18, (Lands within 'Development Area 7- Macnebury', M4, located West & South of Castle Street, south of Lehaunstown Lane and North of Bishop Street. Granted (2 Dec 2022). Builds 65 three-bed homes in five three-storey blocks in Macnebury, west of Castle Street. - [DZ20A/0585](https://cherrywoodplans.com/application/DZ20A-0585.md): on a site in the Townlands of Laughanstown and Cherrywood, Dublin 18. Refused or withdrawn (2 Jun 2021). A temporary sales and marketing suite with 8 parking spaces for just under 5 years off Gun and Drum Hill Road. - [DZ25A/0014/WEB](https://cherrywoodplans.com/application/DZ25A-0014-WEB.md): Townlands of Laughanstown & Brennanstown, Dublin 18. Granted (3 Mar 2025). Amends the permitted Tully village centre (plot T1) to shrink the basement, cutting car parking from 210 to 157 spaces. - [DZ23A/0106](https://cherrywoodplans.com/application/DZ23A-0106.md): Lands in the Townlands of Laughanstown and Brennanstown, Dublin 18. Granted (22 Sep 2023). A village centre at Tully with a supermarket, shops, cafés and 139 build-to-rent apartments in two blocks of 3–5 storeys. - [DZ26A/0580/WEB](https://cherrywoodplans.com/application/DZ26A-0580-WEB.md): Bishop Street (M3a), Laughanstown, Dublin 18 (Development Area 7 Macnebury - Res3 Plot). More information requested (22 Sep 2026). 32 new homes, mostly 3-bed two-level apartments, off Bishop Street in Macnebury. - [DZ18A/0499](https://cherrywoodplans.com/application/DZ18A-0499.md): Lands (c.1.22ha) in the townlands of Cherrywood & Laughanstown, Dublin 18. Granted (11 Jan 2019). 146 apartments in four 4-storey blocks off Grand Parade on plot TC5. - [DZ24A/1030/WEB](https://cherrywoodplans.com/application/DZ24A-1030-WEB.md): In the Townlands of Laughanstown and Cherrywood, Cherrywood, Dublin 18. Granted (11 Jun 2025). Amends a permitted scheme off Tully Vale Road to add 59 apartments by raising four blocks by one or two storeys. - [DZ26A/0032/WEB](https://cherrywoodplans.com/application/DZ26A-0032-WEB.md): Block A1, The Tully Building, Civic Street, Cherrywood Town Centre, Dublin 18, D18WDK0. Granted (13 Mar 2026). Revised plan for 24 mobile phone antennas and 9 dishes on Block A1, The Tully Building, after an earlier compliance submission was rejected. - [DZ25A/0485/WEB](https://cherrywoodplans.com/application/DZ25A-0485-WEB.md): Block A1, Tully Buildings, Cherrywood, Dublin 18. Granted (1 Aug 2025). 24 mobile phone antennas and 9 dishes on the facade and roof of Block A1, Tully Buildings. - [DZ19A/0597](https://cherrywoodplans.com/application/DZ19A-0597.md): Development Area 8 -Tully, Cherrywood SDZ, Includes the Res 2 plots ''T9'' and ''T10''. Granted (11 Mar 2020). 184 new homes, mainly houses plus two small apartment blocks, on plots T9 and T10 in Tully. - [DZ26A/0750/WEB](https://cherrywoodplans.com/application/DZ26A-0750-WEB.md): Unit B, Mercer Way, Tully Village Centre West, Dublin 18, D18C58F. Refused or withdrawn (7 Oct 2026). Combines two permitted shop units at Tully Village Centre into one convenience store with an off-licence. - [DZ26B/0186/WEB](https://cherrywoodplans.com/application/DZ26B-0186-WEB.md): 4 Mercer Row,Laughanstown, Dublin 18, D18XH7P. Granted (25 May 2026). Three new roof windows added to the front of a house on Mercer Row. - [DZ26B/0153/WEB](https://cherrywoodplans.com/application/DZ26B-0153-WEB.md): 4 Mercer Row, Laughanstown, Dublin, D18XH7P. Refused or withdrawn (19 Mar 2026). Three new roof windows added to the front of a house on Mercer Row. - [DZ22A/0770](https://cherrywoodplans.com/application/DZ22A-0770.md): On Lands Development Area 8 (Tully), Cherrywood SDZ, Laughanstown, Dublin 18. Granted (22 Mar 2023). 71 homes, a crèche, shops and a community room on plot T11 west of Castle Street in Tully village centre. - [DZ26A/0579/WEB](https://cherrywoodplans.com/application/DZ26A-0579-WEB.md): Castle Street (M5), Laughanstown, Dublin 18 (Development Area 7 Macnebury - Res2 Plot). More information requested (22 Sep 2026). 40 new homes, mostly 3-bed two-level apartments, off Castle Street in Macnebury. - [D05A/0162](https://cherrywoodplans.com/application/D05A-0162.md): Druid Valley, Cherrywood, Loughlinstown, Co, Dublin.. Refused or withdrawn (7 Apr 2005). Builds 805 apartments and homes plus a crèche across 50 buildings at Druid Valley, Cherrywood. - [D06A/1016](https://cherrywoodplans.com/application/D06A-1016.md): Townland of Laughanstown, Cherrywood, Loughlinstown, Co. Dublin.. Granted (28 Nov 2006). Builds a 110 kV ESB electrical transformer station in Laughanstown. - [DZ22A/0550](https://cherrywoodplans.com/application/DZ22A-0550.md): Lehaunstown Park Open Space, Laughanstown, Dublin 18. Granted (13 Apr 2023). Turns a temporary car park into Lehaunstown Park Open Space with community gardens and a play plaza. - [DZ21A/0664](https://cherrywoodplans.com/application/DZ21A-0664.md): Site in the Townlands of, Laughanstown, Brennanstown and Cherrywood, Dublin 18. Granted (5 May 2022). 47 apartments in a 4-storey block off Castle Street in Tully. - [DZ22A/0093](https://cherrywoodplans.com/application/DZ22A-0093.md): Townland of Laughanstown, Dublin 18. Granted (1 Apr 2022). Seeks to keep two advertising signs for Cherrywood housing for 3 more years. - [DZ22A/0729](https://cherrywoodplans.com/application/DZ22A-0729.md): Townlands of, Laughanstown, Brennanstown and, Cherrywood, Dublin 18. Granted (22 Sep 2023). 57 new homes, houses and 3-bed two-level apartments, off Gun and Drum Hill Road in Tully. - [DZ23A/0423](https://cherrywoodplans.com/application/DZ23A-0423.md): On lands (c.17.03 a) in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18 (Also Co. Dublin). Granted (10 Aug 2023). Amends the Cherrywood Town Centre permission to add two 2-bed apartments to Block A1. - [DZ22A/0690](https://cherrywoodplans.com/application/DZ22A-0690.md): Townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18, (also Co Dublin). Granted (12 May 2023). Facade and balcony design changes to Cherrywood Town Centre apartment Blocks A1, A2 and A3. - [DZ22A/0747](https://cherrywoodplans.com/application/DZ22A-0747.md): Townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18, (also Co Dublin). Granted (30 Mar 2023). Changes of use and merging of units in Town Centre Blocks C1 and C2 to create a larger 723 sq.m shop with off-licence. - [DZ22A/0846](https://cherrywoodplans.com/application/DZ22A-0846.md): Lands (c. 17.03 ha) in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18 (also Co. Dublin). Granted (22 Dec 2022). Removes a planned viewing platform at Block F1 in Cherrywood Town Centre, replacing it with a glass balustrade. - [DZ22A/0138](https://cherrywoodplans.com/application/DZ22A-0138.md): (c. 17.03ha) in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18, (also Co Dublin). Granted (30 Aug 2022). Minor changes of use between shop and restaurant-type units in Town Centre Blocks C1 and C2, and a slightly larger crèche. - [DZ21A/0807](https://cherrywoodplans.com/application/DZ21A-0807.md): Lands (c. 17.03 ha), in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18, (also Co Dublin). Granted (8 Jul 2022). Amends the Cherrywood Town Centre permission to cut residential parking from 1,363 to 1,169 spaces and add 41 car-sharing spaces. - [DZ21A/0713](https://cherrywoodplans.com/application/DZ21A-0713.md): Lands (c. 17.01 ha) in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18, (also Co Dublin). Granted (3 Oct 2021). Design changes to the three apartment blocks A1–A3 in Cherrywood Town Centre, including taller windows and smaller roof terrace. - [DZ19A/1024](https://cherrywoodplans.com/application/DZ19A-1024.md): 17.01 ha in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18 (also Co. Dublin). Granted (9 Sep 2020). Amends the Cherrywood Town Centre plan to shrink the basement under Blocks A1–A3 and reassign parking. - [DZ20A/0002](https://cherrywoodplans.com/application/DZ20A-0002.md): Lands (c.17.01ha) in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18 (also Co. Dublin). Granted (9 Sep 2020). Makes minor changes to electrical rooms and landscaping in Town Centre Blocks F1 and F3. - [DZ19A/0458](https://cherrywoodplans.com/application/DZ19A-0458.md): 17.01 ha in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18 (also Co. Dublin). Granted (19 Jun 2020). Major redesign of Cherrywood Town Centre plot TC1, adding two supermarkets, an 11-screen cinema and much more retail space. - [DZ22A/0623](https://cherrywoodplans.com/application/DZ22A-0623.md): On Lands Development ,Plot T 11, Area 8 (Tully), Cherrywood SDZ, Laughanstown, Dublin 18. Granted (18 Jan 2023). 49 new houses on plot T11 west of Castle Street in Tully. - [DZ25A/0152/WEB](https://cherrywoodplans.com/application/DZ25A-0152-WEB.md): Land in the townland of Laughanstown, Dublin 18, located north-west of the Tullyvale residential development.The application relates to development in. Granted (11 Jul 2025). Amends an earlier housing permission to shrink the planned basement car park to 13 spaces. - [DZ21A/0414](https://cherrywoodplans.com/application/DZ21A-0414.md): Townland of Laughanstown, Dublin 18. Granted (5 May 2022). 107 new homes, a mix of apartments and houses, north-west of Tullyvale. ## Links - [This page on CherrywoodPlans](https://cherrywoodplans.com/application/DZ15A-0813) - [Council record, documents and conditions (DLR planning portal)](https://planning.agileapplications.ie/dunlaoghaire/application-details/70000) - [All Cherrywood applications](https://cherrywoodplans.com/applications.md) _Source: Dún Laoghaire–Rathdown County Council planning data, refreshed daily. CherrywoodPlans is an independent site, not run by the council._