# Planning application DZ17A/0731 > G3 (west of Block G2), Cherrywood Business Park, Cherrywood, Loughlinstown, Co Dublin (within the Cherrywood Strategic Development Zone (SDZ) and subject to the Cherrywood Planning Scheme 2014), Cherrywood, Dún Laoghaire–Rathdown. Granted (26 Jan 2018). - **Reference:** DZ17A/0731 - **Address:** G3 (west of Block G2), Cherrywood Business Park, Cherrywood, Loughlinstown, Co Dublin (within the Cherrywood Strategic Development Zone (SDZ) and subject to the Cherrywood Planning Scheme 2014) - **Status:** Granted (26 Jan 2018) - **Decision:** GRANT PERMISSION - **Application type:** Permission (SDZ) - **Applicant:** DLR Properties Ltd - **Lodged:** 21 Dec 2017 - **Decided:** 26 Jan 2018 - **Location (lat, lng):** 53.241281, -6.141624 ## Proposal A new office development comprising 4-storey office building with plant and services at roof and undercroft level with maximum building height (including roof plant) of 19.38m and a gross floor area (GFA) of c.2,851 sqm. The application also includes proposals to make permanent a section of the temporary access road as granted under planning Reg. Ref. D16A/0124 to serve as an access to the G3 site and as an emergency access for Building 11 (existing G2 building). The development including office building and access road is proposed on a site with a total area of c.0.34ha. The proposed four storey office development is comprised of the following; ground floor level (615 sqm GSA) includes office floor space, entrance lobby, ancillary WC facilities, shower room and circulation space; first, second and third floor level each include office floor space of c.745 sqm including ancillary WC facilities, shower room and circulation space. A proposed under croft area at lower ground floor level includes waste collection area, LV switch room, substation and bicycle store. A pedestrian service access route is included to a rear surface level car park containing 28 no. car parking spaces, including 3 no. disabled car parking spaces and 3 no. car parking spaces with EV charging points. A total of 30 no. cycling parking spaces are provided in 15 no. long stay cycle parking spaces (located in covered secure parking within the undercroft area) and 15 no. short stay spaces (located adjacent to the main entrance of the proposed G3 building). The proposed office building will be accessed from street level off the existing footpath along Cherrywood Avenue to a reception lobby. A drop=off area/set down space is proposed to the front of the development. As part of the design proposal, vehicular access to serve the development will be provided via a new entrance off the existing temporary shared access road, a section of which is to be made permanent and will also provide an emergency access route to the rear of Building 11. The proposed development also includes hard and soft landscaping and boundary treatment, retaining walls, lighting, attenuation and drainage works and all ancillary development works. Proposals also make provision for a buffer area along the western and southern boundary to facilitate the proposed Luas extension. ## In plain English Builds a new four-storey office building, G3, on Cherrywood Avenue in Cherrywood Business Park. - **2,851** sq.m floor area - **4** storeys - **28** car spaces - **30** cycle spaces - **0.34** hectares ### What's planned A new office building on a **0.34**-hectare site west of Building 11. ### Commercial About **2,851** sq.m over **4** storeys, up to **19.38** m tall including roof plant. ### Transport **28** car spaces (**3** disabled, **3** EV) and **30** cycle spaces. Part of a temporary access road is made permanent, also giving emergency access to Building 11. Land is reserved for the Luas extension. ### Environment Landscaping and drainage works. _This summary was written by AI from the proposal text. Check the council record before relying on it._ ## Conditions ### Condition 2 The development to be carried out in its entirety in accordance with the plans, particulars and specifications lodged with the application, save as may be required by the other conditions attached hereto. REASON: To ensure that the development shall be in accordance with the permission and that effective control be maintained. 2. Drawings Prior to commencement of development the applicant shall submit for the written agreement of the Planning Authority, all drawings in digital format (CAD/GIS) projected to ITM (Irish Transverse Mercator). This information should include the following: • Overall site plan's in DWG format (ITM projection in metres) • Ground floor plans of buildings in DWG format (ITM projection in metres) • Site sections and elevations in PDF format Reason: To ensure consistency with Section 7.4 of the Cherrywood Planning Scheme. 3. Water Supply The detailed design of the water supply infrastructure including details of connections to individual development plots shall be in accordance with Irish Water specification and requirements. Written evidence of the design compliance with Irish Water specification and requirements and copies of the final detail design shall be provided to the Planning Authority prior to commencement of development. Reason: To ensure consistency with PI 4 and PI 5 of the Planning Scheme. NOTE: The detailed design of the water supply infrastructure for this development shall be cognisant of the upgrade of the trunk water main from Bride’s Glen Road, the detailed design of which is currently being progressed by Arup and Irish Water. The applicant shall consult with Irish Water in this regard. 4. Wastewater The detailed design of the Foul Water Drainage network including details of connections to individual development plots shall be in accordance with Irish Water specification and requirements. Written evidence of the design compliance with Irish Water specification and requirements and copies of the final detail design shall be provided to the Planning Authority for their written agreement prior to the commencement of development. Reason: To ensure consistency with PI 12 of the Planning Scheme. 5. Surface Water a) Prior to the commencement of development, the applicant or a representative nominated by the applicant shall, in writing to the Planning Authority, assume all responsibility for the ownership, operation and maintenance of the proposed pumping station and rising main. b) As part of the detailed design for the development and prior to the commencement of development, an operations and maintenance plan for the pumping station, including a monitoring regime for the pumping control system and for the temporary pond high water level monitoring system, shall be submitted for the written agreement of the Planning Authority. c) As part of the detailed design for the development and prior to the commencement of development, full details, including a timeline, for the future decommissioning of the pumping station and rising main shall be submitted for the written agreement of the Planning Authority. d) As part of the detailed design for the development and prior to the commencement of development, or as otherwise agreed by the planning authority, full details, including engineering drawings, of the future diversion of the surface water system and its gravity discharge to future regional Pond 5A-1 shall be submitted for the written agreement of the Planning Authority. e) Prior to the commencement of development or as otherwise agreed by the planning authority, the full design of the Regional Pond 5A, also referred to as Ponds 5A-1 and 5A-2, shall be completed and submitted for the written agreement of the Planning Authority. f) (i)As part of the detailed design for the development and prior to the commencement of development, the applicant shall ensure that the full contributing catchment to the existing temporary Pond 5A is accounted for and shall submit for the written agreement of the Planning Authority a revision to the Catchment Overview, drawing no. D1774-C-09, to the Planning Authority. (ii) Revised calculations for the proposed flow control device detailing the discharge limited to 1 l/s/ha and full details of the device itself shall also be submitted for the written agreement of the Planning Authority. g) Discharge from the subject site shall be limited to 1 l/s/ha unless otherwise agreed with the Planning Authority. h) As part of the detailed design for the development and prior to the commencement of development, the applicant shall submit a stage 2 Stormwater Audit for the written agreement of the Planning Authority. i) Prior to the commencement of development, full drainage details inclusive of petrol interceptor location and all SuDS measures shall be submitted for the written agreement of the Planning Authority. j) Prior to the commencement of development, an operations and maintenance plan for the proposed SuDS components, inclusive of the attenuation structures, shall be submitted for the written agreement of the Planning Authority. k) Prior to the commencement of development a stormwater management plan shall be formulated and shall be submitted for the written agreement of the Planning Authority. l) The minimum size surface water sewer serving a road gully shall be 225mm. m) All proposed hydrobrakes shall be fitted with by-pass doors to facilitate draining down of the surface water system if required. Reason: In the interests of orderly and sustainable development, to ensure consistency with the requirements of Section 4.1 of the Cherrywood Planning Scheme and to ensure long term optimum operation of the surface water management system. 6. Transportation - LUAS Prior to the commencement of the development or any construction works on site the applicant shall agree in writing the detailed design of the boundary interface with the Luas Line B2 with Transport Infrastructure Ireland (TII) and submit details of this agreed design for the subsequent agreement of the Planning Authority. Reason: To preserve the alignment of the future Luas Line B2 and for consistency with specific objective DA 40 of the Cherrywood Planning Scheme. 7. Transportation – Pedestrian & Cycle Movement Prior to the commencement of development or as otherwise agreed, the applicant shall enter into agreement with the Planning Authority to cede lands zoned green infrastructure (as identified on drawing no. 15113-PLA-G3-0001 P02 prepared by STW Architects and as stated in letter dated 21/12/17 from McCutcheon), the boundary of which is to be agreed in writing with the Planning Authority, for the purpose of providing future pedestrian/cycle connections to the existing residential area at Mullinastill/Brides Glen Road in accordance with Specific Objective DA36. Reason: For consistency with specific objective DA 36 and PI 20 of the Cherrywood Planning Scheme. 8. Transportation – Road Infrastructure The developer shall submit for the written agreement of the Planning Authority prior to the commencement of development the following: a) The detailed design of the access road. b) The design shall include the extent of the existing temporary access road, which is proposed to be retained on a permanent basis, curtailed to provide for access to the development car park only. The extent of the road beyond that which is required for access to the development permitted under this application shall be retained only if required for emergency or maintenance purposes and in this case shall be a landscaped surface capable of taking such infrequent traffic loadings and shall not be a bitumen bound asphalt surface. This related only to the section within the red line of the current application. Any agreement shall ensure that there is no impact on the future Luas line. It is recommended that prior to the submission of any detailed design that the applicant consults with the Cherrywood Development Agency Project Team. Reason: For clarity and for consistency with specific objective PI 14 of the Cherrywood Planning Scheme. 9. Transportation - Travel Plans Prior to the commencement of development or any construction works on site the applicant shall provide the Planning Authority with the details and contact information of the key contact or Travel Plan Coordinator. The nominated person shall be suitably qualified and experienced to undertake the role. Reason: To ensure implementation of the Travel Plan for the development and or consistency with specific objective PI 24 of the Cherrywood Planning Scheme. 10. Green Infrastructure – LUAS a) Prior to commencement of development, the applicant shall submit, for the written agreement of the Planning Authority, revised landscape proposals for the western boundary interface between proposed gabion walls, landscape and Luas swept path, the applicant shall confirm the area required to be kept free from landscape proposals within the 3m set back from Luas swept path to the building elements (as noted on dwg no. 15113 PLA XX 0011 Scott Tallon Walker) the applicant shall consult with (TII - Transport Infrastructure Ireland) in this regard. b) The applicant shall engage the services of a landscape architect (or suitably qualified landscape designer) for the duration of the construction works. Prior to commencement of development the applicant shall submit the details of same for the written agreement of the Planning Authority. Reason: In the interests of consistency with GI8, GI11 and GI76 of the Planning Scheme. 11. Green Infrastructure – Trees & Hedgerows Prior to the commencement of development, the developer shall engage the services of a qualified arborist as an arboricultural consultant, for the entire period of construction activity. The applicant shall inform the Planning Authority in writing of the appointment and name of the consultant, prior to commencement of development. The consultant shall visit the site on a monthly basis, to ensure the implementation of the all of the recommendations in the submitted application. Reason: In the interests of proper planning and sustainable development and to ensure consistency with specific objective G1 42, GI 43, GI 44 and GI 45 of the Cherrywood Planning Scheme. 12. Green Infrastructure – Ecology (i) Prior to the commencement of development, the developer shall engage the services of a qualified ecologist as an ecological consultant, for the duration of construction works. The applicant shall inform the Planning Authority in writing of the appointment and name of the consultant, prior to commencement of development. (ii) The consultant shall ensure the implementation of the all of the recommendations in the submitted Ecological Impact Assessment. Reason: In the interests of proper planning and sustainable development and to ensure consistency with specific objective GI 46 of the Cherrywood Planning Scheme. 13. Green Infrastructure – Ecological Mitigation All of the environmental and construction mitigation measures set out in the Ecological Impact Assessment submitted 17th August 2017, as well as ecologist consultant’s report (i.e. Altemar report) submitted 21st December 2017 shall be implemented in full. This shall include measures related to bats and lighting. Reason: In the interests of consistency with GI 50, GI 51, BP05 of the Planning Scheme. 14. Green Infrastructure – Landscape Prior to commencement of development, the applicant shall submit for the written agreement of the Planning Authority revised landscape proposals and detailed design for the proposed rain gardens including appropriate planting specifications. Reason: To ensure consistency with GI 54, PI8 of the Planning Scheme. 15. Construction Management – Fisheries Prior to commencement of development, the applicant shall submit, for the written agreement of the Planning Authority, a revised Construction Management Plan incorporating the fishery protection measures that are set out in Appendix II “Fisheries Protection/Construction Method Statement” of the Ecological Impact Assessment Report. Reason: To ensure consistency with BP11, GI 57, GI 60 of the Planning Scheme. 16. Construction Management – Habitat Management Prior to commencement of development, the applicant shall submit to the Planning Authority for their written agreement a revised Habitat Management Plan, taking account of the frog spawning site reported in the further information response. Reason: In the interests of consistency with BP03, GI54, GI 55, GI 56, GI 60 of the Planning Scheme. 17. Construction Management – Hours of Work The normal working hours within the site shall be Monday to Friday between 08:00 and 19:00 hours and Saturday between 08:00 and 14:00 hours with no working on Sunday and public holidays. The contractor will not be permitted to start work each day before 08:00 hours. Reason: To mitigate against adverse impacts on nearby residents. 18. Wheel Wash (a) The applicant shall ensure that suitable facilities for vehicle cleansing and wheel washing, to the satisfaction of the Area Engineer, are provided on site. (b) The applicant shall maintain all footpaths and roads effected by the development works in a safe and tidy condition to the satisfaction of the Area Engineer. REASON: In the interests of the amenity, safety and maintenance of adjoining roads and footpaths. 19. That details of all external finishes including colours and textures shall be submitted for the written agreement of the Planning Authority prior to the commencement of development. REASON: In the interest of visual amenity. 20. That all necessary measures be taken by the contractor to prevent the spillage or deposit of clay, rubble or other debris on adjoining roads during the course of the works. REASON: To protect the amenities of the area. 21. The Developer shall, prior to commencement or as otherwise agreed in writing with the Planning Authority, pay the sum of € 5,787.53, to the Planning Authority as a contribution towards expenditure that was/or is proposed to be incurred by the Planning Authority in respect of the provision of Surface Water Public Infrastructure and Facilities benefiting development in the area of the Authority, as provided for in the Development Contribution Scheme made by Dún Laoghaire-Rathdown County Council on the 14th December, 2015. These rates of contribution shall be updated effective from 1 January each year during the life of the Scheme in accordance with the SCSI Tender Price Index (See Article 12 of the Scheme ) commencing from 1st January, 2018. Contributions shall be payable at the index adjusted rate pertaining to the year in which implementation of the planning permission is commenced, as provided for in Note 1 to the Table at Article 9 of the Scheme. Outstanding balances may be subject to interest charges. REASON: It is considered reasonable that the payment of a contribution be required in respect of the provision of the Surface Water Public Infrastructure and Facilities benefiting development in the area of the Planning Authority and that is provided, or that is intended will be provided, by or on behalf of the Local Authority. Note on above Condition: Please note that with effect from 1st January, 2014 Irish Water are now the statutory body responsible for both water and waste water services. Accordingly, the contribution payable has been reduced by the amount of the contribution associated with these services. Further details/clarification can be obtained from Irish Water at Tel. 1 850 278 278 . 22. The Developer shall, prior to commencement or as otherwise agreed in writing with the Planning Authority, pay the sum of € 132,685.54, to the Planning Authority as a contribution towards expenditure that was/or is proposed to be incurred by the Planning Authority in respect of the provision of the Roads Public Infrastructure and Facilities benefiting development in the area of the Authority, as provided for in the Development Contribution Scheme made by Dún Laoghaire-Rathdown County Council on the 14th December, 2015. These rates of contribution shall be updated effective from 1 January each year during the life of the Scheme in accordance with the SCSI Tender Price Index (See Article 12 of the Scheme) commencing from 1st January, 2018. Contributions shall be payable at the index adjusted rate pertaining to the year in which implementation of the planning permission is commenced, as provided for in Note 1 to the Table at Article 9 of the Scheme. Outstanding balances may be subject to interest charges. REASON: It is considered reasonable that the payment of a contribution be required in respect of the provision of the Roads Public Infrastructure and Facilities benefiting development in the area of the Planning Authority and that is provided, or that is intended will be provided, by or on behalf of the Local Authority. 23. The Developer shall, prior to commencement or as otherwise agreed in writing with the Planning Authority, pay the sum of € 86,100.20, to the Planning Authority as a contribution towards expenditure that was/or is proposed to be incurred by the Planning Authority in respect of the provision of the Community & Parks Public Infrastructure, Facilities and Amenities benefiting development in the area of the Authority, as provided for in the Development Contribution Scheme made by Dún Laoghaire-Rathdown County Council on the 14th December, 2015. These rates of contribution shall be updated effective from 1 January each year during the life of the Scheme in accordance with the SCSI Tender Price Index (See Article 12 of the Scheme) commencing from 1st January, 2018. Contributions shall be payable at the index adjusted rate pertaining to the year in which implementation of the planning permission is commenced, as provided for in Note 1 to the Table at Article 9 of the Scheme. Outstanding balances may be subject to interest charges. REASON: It is considered reasonable that the payment of a contribution be required in respect of the provision of the Community & Parks Public Infrastructure, Facilities and Amenities benefiting development in the area of the Planning Authority and that is provided, or that is intended will be provided, by or on behalf of the Local Authority. 24. This development shall not be carried out without prior agreement, in writing, between the Applicant and the Planning Authority relating to the payment of development contributions. REASON: Investment by Dún Laoghaire-Rathdown County Council in Local Authority works has facilitated and will facilitate the proposed development. It is considered appropriate and reasonable that the developer should contribute to the cost of same. 25.The Developer shall, prior to commencement or as otherwise agreed in writing with the Planning Authority, pay the sum of € 17,676.20, to the Planning Authority as a contribution towards expenditure that was/or is proposed to be incurred by the Planning Authority in respect of the provision of the Roads Public Infrastructure and Facilities in the Cherrywood Planning Scheme Area. This Cherrywood Planning Scheme element of the Development Contribution shall be used solely to fund infrastructure identified in the Plan, as listed in Appendix III – Cherrywood Planning Scheme Projects List, as provided for in the Development Contribution Scheme made by Dún Laoghaire-Rathdown County Council on the 12/06/2017. These rates of contribution shall be updated effective from 1 January each year during the life of the Scheme in accordance with the SCSI Tender Price Index (See Article 12 of the Scheme) commencing from 1st January, 2018. Contributions shall be payable at the index adjusted rate pertaining to the year in which implementation of the planning permission is commenced, as provided for in Note 1 to the Table at Article 9 of the Scheme. Outstanding balances may be subject to interest charges. REASON: It is considered reasonable that the payment of a contribution be required in respect of the provision of the Roads Public Infrastructure and Facilities benefiting development in the Cherrywood Planning Scheme Area of the Planning Authority and that is provided, or that is intended will be provided, by or on behalf of the Local Authority. 26.The Developer shall, prior to commencement or as otherwise agreed in writing with the Planning Authority, pay the sum of €112,443.44, to the Planning Authority as a contribution towards expenditure that was/or is proposed to be incurred by the Planning Authority in respect of the provision of the Community & Parks Public Infrastructure Facilities & Amenities in the Cherrywood Planning Scheme Area. This Cherrywood Planning Scheme element of the Development Contribution shall be used solely to fund infrastructure identified in the Plan, as listed in Appendix III – Cherrywood Planning Scheme Area Only, as provided for in the Development Contribution Scheme made by Dún Laoghaire-Rathdown County Council on the 12/06/2017. These rates of contribution shall be updated effective from 1 January each year during the life of the Scheme in accordance with the SCSI Tender Price Index (See Article 12 of the Scheme) commencing from 1st January, 2018. Contributions shall be payable at the index adjusted rate pertaining to the year in which implementation of the planning permission is commenced, as provided for in Note 1 to the Table at Article 9 of the Scheme. Outstanding balances may be subject to interest charges. REASON: It is considered reasonable that the payment of a contribution be required in respect of the provision of the Community & Parks Public Infrastructure Facilities & Amenities benefiting development in the Cherrywood Planning Scheme Area of the Planning Authority and that is provided, or that is intended will be provided, by or on behalf of the Local Authority. 27. The Developer shall, prior to commencement or as otherwise agreed in writing with the Planning Authority, pay the sum of € 30,505.70, to the Planning Authority as a contribution towards expenditure that was/or is proposed to be incurred by the Planning Authority in respect of the provision of Surface Water Public Infrastructure and Facilities benefiting development in the Cherrywood Planning Scheme area only of the Authority, as provided for in the Development Contribution Scheme made by Dún Laoghaire-Rathdown County Council on the 12/06/2017. These rates of contribution shall be updated effective from 1 January each year during the life of the Scheme in accordance with the SCSI Tender Price Index (See Article 12 of the Scheme) commencing from 1st January, 2018. Contributions shall be payable at the index adjusted rate pertaining to the year in which implementation of the planning permission is commenced, as provided for in Note 1 to the Table at Article 9 of the Scheme. Outstanding balances may be subject to interest charges. REASON: It is considered reasonable that the payment of a contribution be required in respect of the provision of the Surface Water Public Infrastructure and Facilities benefiting development in the in the Cherrywood Planning Scheme area and that is provided, or that is intended will be provided, by or on behalf of the Local Authority. 28. That a financial contribution shall be paid by the proposer to the Council towards the cost of the extension of Luas Line B from the Sandyford Depot to Cherrywood, namely Luas Line B1. This contribution to be paid prior to the commencement of the development or in such other manner as may otherwise be agreed with the Planning Authority. The rate of contribution payable shall be that pertaining to the particular year in which implementation of the Planning Permission is commenced. The Supplementary Development Contribution Scheme provides for an annual increase in the levels of contribution payable, as outlined in the scheme, by a factor of 5% compound interest per annum. The levels of contribution will be reviewed annually on the 13th of January of each year during which the scheme is in force to take account of the aforementioned increase. The rate of contribution payable in respect of this development, at current contribution rates, is € 296,757.39, and is subject to increase as outlined above. It should be noted that contributions assessed in accordance with the Supplementary Development Contribution Scheme cannot be appealed to An Bord Pleanala unless the applicant considers the levy referred to in this condition has not been properly applied in accordance with the terms of the Scheme. REASONS FOR CONTRIBUTIONS: To part finance the extension of the Luas Line B1 from Sandyford Depot to Cherrywood, as provided for in the Supplementary Development Contribution Scheme adopted by the Council of Dun laoghaire-Rathdown on the 13th of January, 2003. (incorporating amendments to Clause 13 as adopted by the County Council at it’s meeting on 13th May, 2013 – to be effective for all decisions from 14th May, 2013). 29. This development shall not be carried out without prior agreement, in writing, between the Applicant and the Planning Authority relating to the payment of development contributions. REASON: Investment by Dún Laoghaire-Rathdown County Council in Local Authority works has facilitated and will facilitate the proposed development. It is considered appropriate and reasonable that the developer should contribute to the cost of same. NOTE: The applicant has to comply with the requirements of the TII and Irish Water. ## Nearby applications - [DZ24A/0485/WEB](https://cherrywoodplans.com/application/DZ24A-0485-WEB.md): Site Known as Block G3, Cherrywood Business Park, Cherrywood, Loughlinstown, Co. Dublin. Granted (19 Dec 2024). A 4-storey science and technology office building with labs on Block G3, Cherrywood Business Park. - [D06A/1497](https://cherrywoodplans.com/application/D06A-1497.md): Cherrywood Science & Technology Park, Loughlinstown, Co. Dublin. Granted (14 Dec 2006). Builds a new four-storey office building, Block G2, over a two-level car park at Cherrywood Business Park. - [D03A/0479](https://cherrywoodplans.com/application/D03A-0479.md): ESB, Plot M, Cherrywood Science And Technology Park, Wyatville Link Road. Granted (14 Jul 2003). Seeks to keep an ESB 38 kV line mast already installed at Cherrywood Business Park. - [DZ20A/0611](https://cherrywoodplans.com/application/DZ20A-0611.md): Site of approximately 4,730 sq m at Building 11, (formerly known as Block G2), Cherrywood Business Park, Cherrywood, Co. Dublin, D18 DH50. Granted (19 Oct 2020). Expands the day hospital in Building 11, Cherrywood Business Park, to 1,220 sq.m. - [DZ18A/1131](https://cherrywoodplans.com/application/DZ18A-1131.md): Site of approx. 4,730 sqm at Building 11 (formerly known as Block G2), Cherrywood Business Park, Cherrywood, Dublin D18 DH50. Granted (5 Feb 2019). Turns part of the ground floor of Building 11 at Cherrywood Business Park into a 922 sq.m day hospital. - [DZ17A/0649](https://cherrywoodplans.com/application/DZ17A-0649.md): Block G2, Cherrywood Business Park, Cherrywood, Co Dublin. Granted (8 Sep 2017). Adds louvred screening around rooftop plant on Block G2, Cherrywood Business Park. - [DZ16A/0935](https://cherrywoodplans.com/application/DZ16A-0935.md): Block G2, Cherrywood Business Park, Cherrywood, Co. Dublin. Granted (17 Feb 2017). Adds landscaping, a drop-off area and a sign at Block G2, Cherrywood Business Park, and keeps three glass canopies. - [D10A/0701](https://cherrywoodplans.com/application/D10A-0701.md): Cherrywood Science and Technology Park, Cherrywood, Loughlinstown, Co. Dublin.. Granted (24 May 2011). A 197-space surface park and ride car park beside the Brides Glen Luas stop. - [DZ18A/0854](https://cherrywoodplans.com/application/DZ18A-0854.md): site (c.2.62 HA) at Cherrywood Business Park, Cherrywood Avenue, Cherrywood, Co. Dublin (also Dublin 18) (lands to the south and west of Blocks G and G2, south of Cherrywood Avenue). Granted (31 Oct 2018). Builds a three-pond drainage system with a walking and cycling route south of Cherrywood Avenue. - [DZ19A/0577](https://cherrywoodplans.com/application/DZ19A-0577.md): Cherrywood Avenue South adjacent to Building 11, formally known as Building G2, Cherrywood Business Park, Loughlinstown, Dublin, D18 DH50. Granted (23 Jan 2020). A new loading bay on Cherrywood Avenue South beside Building 11 in Cherrywood Business Park. - [DZ16A/0124](https://cherrywoodplans.com/application/DZ16A-0124.md): Cherrywood Business Park (to west of Block G2 and south of Block G and G2), Cherrywood, Loughlinstown, Co Dublin. Granted (21 Apr 2016). Seeks to keep a temporary access road to the Blocks G and G2 car park at Cherrywood Business Park for 7 years. - [D09A/0804](https://cherrywoodplans.com/application/D09A-0804.md): Cherrywood Science & Technology Park, Cherrywood, Loughlinstown, Co. Dublin.. Granted (14 Jan 2010). Permission to keep changes at Blocks G and G2, Cherrywood Science & Technology Park, including a larger basement car park. - [D07A/0229](https://cherrywoodplans.com/application/D07A-0229.md): Cherrywood Science Technology Park, Loughlinstown, Co. Dublin.. Granted (28 May 2007). Adds a temporary vehicle ramp to the basement car park serving Blocks G and G2 at Cherrywood Business Park. - [D07A/1243](https://cherrywoodplans.com/application/D07A-1243.md): Glencarrig, Rathmichael, Co. Dublin. Granted (25 Oct 2007). Amends an earlier permission at Glencarrig to redesign one house and add a tenth five-bedroom house. - [DZ22A/0681](https://cherrywoodplans.com/application/DZ22A-0681.md): Cherrywood Avenue, (Adjoining Cherrywood Business Park), Cherrywood, Dublin 18. Granted (28 Jun 2023). A 5-storey block of 70 apartments on Cherrywood Avenue, beside Cherrywood Business Park. - [DZ23A/0242](https://cherrywoodplans.com/application/DZ23A-0242.md): Townland of Cherrywood Dublin 18 The site is located in the Cherrywood Planning Scheme and forms part of the south eastern porti. Granted (7 Jun 2023). Changes to the permitted basement at Town Centre 3 so it can later connect to the wider TC3 basement. - [DZ21A/0785](https://cherrywoodplans.com/application/DZ21A-0785.md): c.0.95 ha townland, Cherrywood, Dublin 18 (also Co. Dublin). Granted (30 Mar 2022). An office building of up to 8 storeys with ground-floor cafés at the corner of Town Centre 3, beside the Bride's Glen Luas stop. - [D06A/0116](https://cherrywoodplans.com/application/D06A-0116.md): Glencarraig, Rathmichael, Co. Dublin. Granted (18 Aug 2006). 19 homes and a new access road linking Brides Glen Road to Cherrywood Science & Technology Park at Glencarraig. - [D05A/1083](https://cherrywoodplans.com/application/D05A-1083.md): Glencarrig (site At), Rathmichael, Co. Dublin. Refused or withdrawn (12 Oct 2005). Builds 73 apartments in two blocks at Glencarrig, with a new road and cycle route from Brides Glen Road to Cherrywood Business Park. - [DZ21A/0818](https://cherrywoodplans.com/application/DZ21A-0818.md): Site of approximately 0.43 ha at Building 10 (formerly known as Block G), Cherrywood Business Park, Cherrywood, Co. Dublin, D18 T3Y1. Granted (24 Feb 2022). New plant enclosures, flue stacks and doors at Building 10 in Cherrywood Business Park. - [D13A/0292](https://cherrywoodplans.com/application/D13A-0292.md): Site at Glencarrig, Brides Glen Road, Rathmichael, Co. Dublin. Granted (1 Aug 2013). Amends the earlier Glencarrig permission with a revised design for 10 five-bedroom detached houses. - [D22A/0964](https://cherrywoodplans.com/application/D22A-0964.md): The Old Glebe, Brides Glen Road, Dublin 18, D18Y7H7. Granted (4 Apr 2023). Alters Old Glebe House, a protected structure, and extends its coach house from one to three bedrooms. - [D04A/0232](https://cherrywoodplans.com/application/D04A-0232.md): Block H, Cherrywood Science & Technology Park, Loughlinstown, Co. Dublin. Granted (23 Apr 2004). Puts up a lit corporate logo sign at Block H, Cherrywood Business Park. - [DZ26A/0001/WEB](https://cherrywoodplans.com/application/DZ26A-0001-WEB.md): Cherrywood Avenue, (Adjoining Cherrywood Business Park), Cherrywood, Dublin 18. Granted (29 Jun 2026). Amends a permitted apartment scheme on Cherrywood Avenue to go from 67 to 70 apartments, with more parking. - [DZ25A/0983/WEB](https://cherrywoodplans.com/application/DZ25A-0983-WEB.md): Cherrywood Avenue ( adjoining Cherrywood Business Park), Cherrywood, Dublin 18. Refused or withdrawn (22 Dec 2025). Amends a permitted apartment scheme on Cherrywood Avenue to go from 67 to 70 apartments, with more parking. - [D22A/1019](https://cherrywoodplans.com/application/D22A-1019.md): Old Glebe House, Brides Glen Road, Shankill, Dublin 18, D18Y7H7. Refused or withdrawn (22 Feb 2023). Builds two four-bedroom houses in the lower grounds of the Old Glebe on Brides Glen Road. - [D13A/0534](https://cherrywoodplans.com/application/D13A-0534.md): Old Glebe House, Brides Glen Road, Townland Glebe (Rathmichael),Dublin 18. Granted (11 Feb 2014). Replaces a single-storey annex on Old Glebe House, a protected structure, with a new single-storey extension. - [D19A/0277](https://cherrywoodplans.com/application/D19A-0277.md): Old Glebe House, Brides Glen Road, Rathmichael, Dublin 18. Refused or withdrawn (19 Jun 2019). Builds three detached three-storey houses within the grounds of Old Glebe House, a protected structure, on Brides Glen Road. - [D24A/0037](https://cherrywoodplans.com/application/D24A-0037.md): The Old Glebe House, Brides Glen Road, Shankill, Dublin 18, D18Y7H7. Granted (11 Mar 2024). Changes to an approved extension at The Old Glebe House, Brides Glen Road, enlarging the ground floor from 83 to 103 sq.m. - [D23A/0820](https://cherrywoodplans.com/application/D23A-0820.md): The Old Glebe House, Brides Glen Road, Shankill, Dublin 18, D18Y7H7. Refused or withdrawn (15 Jan 2024). Changes to an approved extension at The Old Glebe House, Brides Glen Road, enlarging the ground floor from 83 to 103 sq.m. - [D23A/0392](https://cherrywoodplans.com/application/D23A-0392.md): The Old Glebe House, Brides Glen Road, Shankill, Dublin 18, D18Y7H7--a protected structure.. Granted (1 Nov 2023). Two new 4-bedroom, two-storey houses in the lower grounds of The Old Glebe House, Brides Glen Road. - [D06A/1475](https://cherrywoodplans.com/application/D06A-1475.md): Cherrywood Science & Technology Park, Loughlinstown, Co. Dublin. Granted (20 Dec 2006). Enlarges the approved Block G office building by filling in a front recess and extending the penthouse, adding 502 sq.m. - [D06A/0015](https://cherrywoodplans.com/application/D06A-0015.md): Cherrywood Science and Technology Park, Cherrywood, Loughlinstown, Co. Dublin.. Granted (1 Mar 2006). Adds an extra floor to the approved Block G office building at Cherrywood Business Park, taking it from three to four storeys. - [D05A/0219](https://cherrywoodplans.com/application/D05A-0219.md): Cherrywood Science & Technology Park, Cherrywood, Loughlinstown, Co. Dublin.. Granted (9 Nov 2005). Changes the approved Block G office building with a two-level underground car park and a larger floor area. - [D02A/0430](https://cherrywoodplans.com/application/D02A-0430.md): Cherrywood Science & Technology Park,, Cherrywood, Loughlinstown, Co. Dublin.. Granted (10 Jul 2002). Allows five permitted science and technology buildings at Cherrywood Business Park to be used instead for office-based industry. - [D02A/0508](https://cherrywoodplans.com/application/D02A-0508.md): Building H, Cherrywood Science & Technology Park,, Cherrywood, Loughlinstown, Co. Dublin.. Granted (22 Jul 2002). Adds 15 parking spaces to the car park serving Building H at Cherrywood Business Park. - [D08B/0452](https://cherrywoodplans.com/application/D08B-0452.md): Heather Hill, Cherrywood Road, Loughlinstown, Co. Dublin. Granted (7 Aug 2008). Extends a house at Heather Hill, Cherrywood Road, with single and two-storey additions. - [DZ20A/0052](https://cherrywoodplans.com/application/DZ20A-0052.md): 1.86 ha in the townlands of Cherrywood, Dublin 18 (also Co. Dublin)--TC3. Granted (13 Apr 2021). A mixed-use block at Town Centre 3 with an 8-storey office building and 198 build-to-rent apartments. - [D07A/1770](https://cherrywoodplans.com/application/D07A-1770.md): Cherrywood Science & Technology Park, Loughlinstown, Co. Dublin.. Refused or withdrawn (28 Jan 2008). Builds a multi-storey car park with 1,081 spaces and 10 ground-floor shops at Cherrywood Business Park. - [D22A/0079](https://cherrywoodplans.com/application/D22A-0079.md): Cherrywood Lodge, Brides Glen Road, Shankill, Dublin 18. Granted (30 Mar 2022). Converting and extending an outbuilding at Cherrywood Lodge, Brides Glen Road, into a new single-storey home. - [DZ22A/1025](https://cherrywoodplans.com/application/DZ22A-1025.md): Cherrywood Avenue, Lands within the townlands of Glebe and Cherrywood, Dublin 18. Granted (2 Nov 2023). Builds 44 homes, houses and two-level units, off Cherrywood Avenue. - [D07A/0597](https://cherrywoodplans.com/application/D07A-0597.md): Cherrywood Science Technology Park, Loughlinstown, Co. Dublin.(Blocks F and G),. Refused or withdrawn (12 Jun 2007). Three office buildings of 4 to 7 storeys at Cherrywood Science & Technology Park, with a 612-space basement car park. - [D22A/0353](https://cherrywoodplans.com/application/D22A-0353.md): Cherrywood House, Cherrywood Road, Shankill, Dublin 18 (A Protected Structure). Granted (15 Sep 2022). Restores and upgrades Cherrywood House, a protected structure, replacing its 20th-century flat-roofed extensions. - [D08A/0035](https://cherrywoodplans.com/application/D08A-0035.md): Cherrywood Science and Technology Park, Cherrywood, Loughlinstown, Co. Dublin.. Granted (26 Jun 2008). A 4–5 storey office building (Building F) and new road at Cherrywood Science & Technology Park, with 289 basement car spaces. - [DZ19A/1021](https://cherrywoodplans.com/application/DZ19A-1021.md): Blocks F1, F2 and F3 (3no. office blocks under construction) at Cherrywood Business Park, Cherrywood, Co Dublin (also Dublin 18). Refused or withdrawn (5 Feb 2020). Allows up to 229 spaces in the basement car park of office Blocks F1–F3 to be used for temporary parking for 7 years. - [DZ18A/1104](https://cherrywoodplans.com/application/DZ18A-1104.md): Lands (c.2.57ha) Cherrywood Business Park (lands including & adjoining former Block F, part of existing Block G (basement level -1 only) & lands to rear Blocks G & G2, Cherrywood, Co Dublin (also Dublin 18). Site is within Development Area 6A Brides Glen. Granted (29 Jan 2019). Builds office Block F3 and expands the shared basement car park to 658 spaces, with a new linear park, at Cherrywood Business Park. - [D16A/0361](https://cherrywoodplans.com/application/D16A-0361.md): The Orchard, Cherrywood Road, Loughlinstown, Co. Dublin. Granted (12 Sep 2016). Builds two new two-storey houses beside an existing home at The Orchard, Cherrywood Road. - [DZ19A/0186](https://cherrywoodplans.com/application/DZ19A-0186.md): c. 1.676 ha at Cherrywood Business Park (lands including former Block F), Cherrywood, Co. Dublin (also Dublin 18). Granted (9 May 2019). Adds landscaped roof terraces to permitted office Blocks F1 and F2 at Cherrywood Business Park. - [DZ17A/0122](https://cherrywoodplans.com/application/DZ17A-0122.md): Lands (c.1.6284 ha) at Cherrywood Business Park (lands including former Block F), Cherrywood, Co Dublin (also Dublin 18). Granted (7 Feb 2018). Builds two five-storey office blocks, F1 and F2, over an existing basement car park at Cherrywood Business Park. - [D02A/0660](https://cherrywoodplans.com/application/D02A-0660.md): Clanart, Cherrywoood Road, Loughlinstown, Dublin 18.. Granted (20 Aug 2002). Seeks permission to keep part of an existing single-storey bungalow on Cherrywood Road. - [D15B/0171](https://cherrywoodplans.com/application/D15B-0171.md): Clanart, Cherrywood Road, Loughlinstown, Dublin 18. Granted (10 Jul 2015). Rebuilds and extends a single-storey house at Clanart, Cherrywood Road, with a new raised roof. - [DZ22A/0591](https://cherrywoodplans.com/application/DZ22A-0591.md): C. 3.71 in the Townland of Cherrywood, Block Town Centre 3 (TC3), Dublin 18. Granted (20 Jun 2023). 418 build-to-rent apartments in four blocks of up to 5 storeys at Town Centre 3, with shops, cafés and community space. - [D09A/0501](https://cherrywoodplans.com/application/D09A-0501.md): Cherrywood Science and Technology Park, Cherrywood, Loughlinstown, Co. Dublin.. Refused or withdrawn (3 Sep 2009). 112 apartments, offices and shops in three buildings of 5–6 storeys at Cherrywood Science & Technology Park. - [DZ21A/0029](https://cherrywoodplans.com/application/DZ21A-0029.md): Site of approximately 1,094 sq m at Building 8 (formerly known as Block E), Cherrywood Business Park, Cherrywood, Co. Dublin, c. Granted (29 Apr 2021). Rebuilds the front entrance of Building 8 at Cherrywood Business Park with a slightly larger lobby. - [DZ24A/0366/WEB](https://cherrywoodplans.com/application/DZ24A-0366-WEB.md): Building 8, Cherrywood Business Park, Dublin 18, D18W319. Granted (17 Jul 2024). Adds tenant signage and a wayfinding totem at Building 8, Cherrywood Business Park. - [DZ23A/0283](https://cherrywoodplans.com/application/DZ23A-0283.md): Building 8, Cherrywood Business Park, Cherrywood, Loughlinstown, Co. Dublin, D18 W319. Granted (11 Aug 2023). Turns Building 8 at Cherrywood Business Park from offices into a private medical clinic. - [DZ17A/0171](https://cherrywoodplans.com/application/DZ17A-0171.md): Cherrywood Business Park, Cherrywood, Dublin 18. Granted (21 Apr 2017). Seeks to keep the existing entrance and wayfinding signs at Cherrywood Business Park. - [DZ19A/0808](https://cherrywoodplans.com/application/DZ19A-0808.md): Cherrywood Business Park, Cherrywood & Loughlinstown, Co. Dublin, (Also Dublin 18). Granted (17 Dec 2019). Installs a small gas pressure regulator building in Cherrywood Business Park. - [DZ19A/0647](https://cherrywoodplans.com/application/DZ19A-0647.md): Cherrywood Business Park, Cherrywood & Loughlinstown, Co. Dublin, (Also Dublin 18). Refused or withdrawn (18 Sep 2019). Installs a small gas pressure regulator building in Cherrywood Business Park. - [DZ19A/0523](https://cherrywoodplans.com/application/DZ19A-0523.md): Cherrywood Business Park, Cherrywood & Loughlinstown, Co. Dublin, (Also Dublin 18). Refused or withdrawn (23 Aug 2019). Installs a small gas pressure regulator building in Cherrywood Business Park. - [DZ24A/1007/WEB](https://cherrywoodplans.com/application/DZ24A-1007-WEB.md): ‘Red Zone’ temporary surface car park, and Blocks F1-F3, ‘The Campus’, Cherrywood Avenue,, Cherrywood (Glebe Townland), Co. Dublin, Dublin 18. Granted (18 Feb 2025). Shrinking the temporary Red Zone car park on Cherrywood Avenue to about 398 spaces for another 5 years, and opening 226 basement spaces at The Campus. - [DZ22A/0728](https://cherrywoodplans.com/application/DZ22A-0728.md): Red Zone car park, Cherrywood Avenue, Cherrywood (Glebe Townland), Co Dublin/Dublin 18. Granted (14 Mar 2023). Keeping the temporary Red Zone surface car park for about 740 cars on Cherrywood Avenue for another 5 years. - [DZ20A/0477](https://cherrywoodplans.com/application/DZ20A-0477.md): Blocks F1,F2 & F3 (3no. office blocks under construction), Cherrywood Business Park, Cherrywood, Co. Dublin (also Dublin 18) & at the temporary surface car park at Cherrywood (Glebe Townland) Co. Dublin (also Dublin 18). Granted (28 Aug 2020). Allows up to 229 spaces in the basement car park of office Blocks F1–F3 to be used for temporary parking for 7 years. - [DZ17A/0417](https://cherrywoodplans.com/application/DZ17A-0417.md): Cherrywood Glebe Townland, Co Dublin ( Dublin 18) (Lands within Dev Area 6-Bride's Glen-bounded by M50 west, Cherrywood Ave & undeveloped lands to north undeveloped lands & Glencarrig res. estate east & res prop. & undev. lands off Brides Glen to south. Granted (7 Nov 2017). Uses land off Cherrywood Avenue as a temporary car park for about 740 cars for 5 years. - [DZ17A/0326](https://cherrywoodplans.com/application/DZ17A-0326.md): Cherrywood, Glebe Townland, Co Dublin (Also Dublin 18) (Lands within Dev Area 7-Macnebury-bounded by M50 to west, Cherrywood Ave & undeveloped lands to north, undeveloped lands & Glencarrig res. estate to east & undeveloped lands off Brides Glen to south. Refused or withdrawn (26 Apr 2017). Uses land off Cherrywood Avenue as a temporary car park for about 740 cars for 5 years. - [D06A/0911](https://cherrywoodplans.com/application/D06A-0911.md): Block D, Cherrywood Science & Technology Park, Cherrywood, Loughlinstown, Co. Dublin. Granted (23 Aug 2006). Makes internal changes to the Block D office building, enclosing its entrance and adding a fire escape stairs. - [D08A/0687](https://cherrywoodplans.com/application/D08A-0687.md): Cherrywood Science & Technology Park, Loughlinstown, Co. Dublin. Refused or withdrawn (7 Aug 2008). Replacing Block D with a 5-storey office building with a large ground-floor shop at Cherrywood Science & Technology Park. - [DZ16A/0530](https://cherrywoodplans.com/application/DZ16A-0530.md): Units 2 & 4 Building 7 (previously 'Block D'), Cherrywood Business Park, Cherrywood, Loughlinstown, Co Dublin. Granted (9 Sep 2016). Changes two vacant units in Building 7, Cherrywood Business Park, into medical and dental use. - [D06A/0630](https://cherrywoodplans.com/application/D06A-0630.md): Spar Retail Unit, Block D, Cherrywood Science & Technology Park, Loughlinstown, Dublin 18. Granted (12 Jul 2006). An off-licence counter added to the Spar shop in Block D of Cherrywood Science & Technology Park. - [D05A/1672](https://cherrywoodplans.com/application/D05A-1672.md): Block D, Cherrywood Science & Technology Park, Loughlinstown, Co. Dublin. Granted (13 Feb 2006). Makes small changes to Block D, enlarging a ground-floor shop and trimming the offices. - [DZ25A/0066/WEB](https://cherrywoodplans.com/application/DZ25A-0066-WEB.md): Building 7 The Campus, Cherrywood Avenue, Cherrywood (Glebe Townland), Co Dublin, Dublin 18, D18T8Y6. Granted (20 Mar 2025). Part of Building 7 at The Campus changes from offices to medical and dental use. - [D05A/0419](https://cherrywoodplans.com/application/D05A-0419.md): Block D, Cherrywood Science & Technology Park, Loughlinstown, Co. Dublin. Granted (26 Oct 2005). Extends the existing Block D building at Cherrywood Business Park, adding 790 sq.m of shop and office space. - [D07A/0604](https://cherrywoodplans.com/application/D07A-0604.md): Cherrywood Science Technology Park,(Block D1), Loughlinstown, Co. Dublin.. Granted (2 Apr 2008). Replacing a crèche with a 4-storey office building and restaurant (Block D1) at Cherrywood Science & Technology Park. - [D08A/0952](https://cherrywoodplans.com/application/D08A-0952.md): Cherrywood Science & Technology Park,(Block D1), Cherrywood, Loughlinstown, Co. Dublin. Refused or withdrawn (15 Oct 2008). Design changes to the approved Block D1 office building at Cherrywood Science & Technology Park. - [D21B/0118](https://cherrywoodplans.com/application/D21B-0118.md): Saint Michael's Lodge, Cherrywod Road, Shankill, Dublin 18, D18F7AR. Granted (16 Jul 2021). Seeks to keep a rear dormer window at Saint Michael's Lodge, Cherrywood Road. - [D08A/1062](https://cherrywoodplans.com/application/D08A-1062.md): Unit 6, Block C, The Facilities Building, Cherrywood, Co. Dublin. Granted (13 Nov 2008). Adds lit signage to the front of Unit 6, Block C, at Cherrywood Business Park. - [D04A/1012](https://cherrywoodplans.com/application/D04A-1012.md): Cherrywood/Glebe, (ED Rathmichael), Wyvattville Link Road, Co. Dublin.. Refused or withdrawn (9 May 2005). Reshapes and drains an 8.6-hectare site at Cherrywood/Glebe and stores topsoil on a further 5.1 hectares at Laughanstown. - [D08A/0762](https://cherrywoodplans.com/application/D08A-0762.md): Unit 6, Block C, The Facilities Building, Cherrywood, Co. Dublin. Refused or withdrawn (25 Aug 2008). Adds lit signage to the front of Unit 6, Block C, at Cherrywood Business Park. - [D07A/0233](https://cherrywoodplans.com/application/D07A-0233.md): Cherrywood Science Technology Park, Loughlinstown, Co. Dublin.. Granted (27 Aug 2007). Extends and reworks the approved Block C leisure building, adding a double-height swimming pool hall. - [D06A/0268](https://cherrywoodplans.com/application/D06A-0268.md): Cherrywood Science & Technology Park, Loughlinstown, Co. Dublin. Granted (16 Jun 2006). Builds a four-storey leisure and retail building (Block C) with a fitness centre and 25-metre pool at Cherrywood Business Park. - [D05A/1715](https://cherrywoodplans.com/application/D05A-1715.md): Cherrywood Science & Technology Park, Loughlinstown, Co. Dublin. Refused or withdrawn (12 Jan 2006). Builds a four-storey leisure and retail building (Block C) with a fitness centre and 20-metre pool at Cherrywood Business Park. - [DZ16A/0816](https://cherrywoodplans.com/application/DZ16A-0816.md): Unit 4 Building 5 (previously Block C), Cherrywood Business Park, Cherrywood, Dublin 18. Granted (10 Jan 2017). Changes a vacant shop unit in Cherrywood Business Park into a bank with an ATM. - [D08A/0121](https://cherrywoodplans.com/application/D08A-0121.md): Block C, Cherrywood Science And Technology Park, Cherrywood, Loughlinstown, Co. Dublin. Granted (24 Jun 2008). Seeks to keep an extension to the Block C facilities building and sets out options for a front loading bay. - [D07A/1607](https://cherrywoodplans.com/application/D07A-1607.md): Cherrywood Science Technology Park, Loughlinstown, Co. Dublin.. Refused or withdrawn (24 Jan 2008). The top floor of Block C at Cherrywood Science & Technology Park changes from recreation use to offices. - [D07A/1503](https://cherrywoodplans.com/application/D07A-1503.md): Block C, Cherrywood Science And Technology Park, Cherrywood, Loughlinstown, Co. Dublin. Refused or withdrawn (18 Dec 2007). Keeping a 52 sq.m ground-floor extension and shopfronts at Block C, Cherrywood Science & Technology Park. - [D11B/0364](https://cherrywoodplans.com/application/D11B-0364.md): 105, Cherrywood Road, Loughlinstown, Co. Dublin. Granted (12 Jan 2012). Adds a single-storey extension to the rear and side of a house at 105 Cherrywood Road. - [DZ23A/0508](https://cherrywoodplans.com/application/DZ23A-0508.md): Unit 3 and Unit 1, Building 5, Cherrywood Business Park, Cherrywood, Loughlinstown, Co Dublin. Granted (22 Sep 2023). Two units in Building 5, Cherrywood Business Park, become a dental clinic and a café. - [DZ16A/0123](https://cherrywoodplans.com/application/DZ16A-0123.md): Units 1 & 2 Block C, Cherrywood Business Park, Cherrywood, Loughlinstown, Co Dublin. Granted (21 Apr 2016). Reconfigures two ground-floor shop units in Block C and turns one into a café/restaurant. - [D09A/0146](https://cherrywoodplans.com/application/D09A-0146.md): Cherrywood Science and Technology Park, Cherrywood, Loughlinstown, Co. Dublin.. Granted (23 Apr 2009). Fills in atrium spaces in Building AA at Cherrywood Business Park, adding 269 sq.m and 5 parking spaces. - [DZ16A/0535](https://cherrywoodplans.com/application/DZ16A-0535.md): Hibernia House, Cherrywood Business Park, Loughlinstown, Dublin 18. Granted (9 Sep 2016). Puts up two high-level lit 'evros' signs on Hibernia House, Cherrywood Business Park. - [D02A/0424](https://cherrywoodplans.com/application/D02A-0424.md): Cherrywood Science & Technology Park,, Cherrywood, Loughlinstown, Co. Dublin.. Granted (10 Jul 2002). Allows two permitted three-storey science and technology buildings, AA and AB, to be used instead for office-based industry. - [DZ14A/0596](https://cherrywoodplans.com/application/DZ14A-0596.md): Unit 1 , Block C, Cherrywood Science and Technology Park, Cherrywood, Loughlinstown, Co Dublin. Granted (11 Dec 2014). Changes Shop Unit 1 in Block C, Cherrywood Business Park, into a dental clinic. - [DZ25A/0543/WEB](https://cherrywoodplans.com/application/DZ25A-0543-WEB.md): Dlr Properties Limited, Hibernia House, Cherrywood Business Park, Dublin 18, D18E440. Granted (28 Aug 2025). Hibernia House in Cherrywood Business Park changes from offices to a medical centre with a pharmacy. - [D06A/1660](https://cherrywoodplans.com/application/D06A-1660.md): Park One, Cherrywood Science And Technology Park, Loughlinstown, Co. Dublin.. Granted (6 Mar 2007). Completes the distributor road through Park One at Cherrywood Business Park, letting overhead power lines go underground. - [DZ17A/0862](https://cherrywoodplans.com/application/DZ17A-0862.md): Lands (17.01ha) in the townlands of Cherrywood, Dublin 18. Granted (29 May 2018). The original Cherrywood Town Centre permission: 15 blocks with 1,269 homes, shops, offices, two hotels and a library, plus Grand Parade. - [DZ19A/0255](https://cherrywoodplans.com/application/DZ19A-0255.md): Cherrywood Business Park (lands including & adjoining Bldgs 2-5 & 7 & basement level under Buildings 3, 4 & 5, Pond 4 & part of the linear park), Cherrywood, Co Dublin .. Granted (3 Dec 2019). Upgrades the public spaces of Cherrywood Business Park with raised meeting pods, a large canopy, a sunken garden and linear park improvements. - [DZ23A/0573](https://cherrywoodplans.com/application/DZ23A-0573.md): Lands (c. 17.03 ha) in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18 (also Co. Dublin). Granted (19 Oct 2023). Amends the Cherrywood Town Centre permission to add 4 apartments in Blocks F2 and F3, bringing plot TC4 to 524 homes. - [D06A/0289](https://cherrywoodplans.com/application/D06A-0289.md): 107, Cherrywood Road, Loughlinstown, Dublin 18. Granted (26 Sep 2006). Builds a new five-bedroom, two-storey detached house beside 107 Cherrywood Road. - [D06A/0065](https://cherrywoodplans.com/application/D06A-0065.md): 107 Cherrywood Road, Cherrywood, Loughlinstown, Co. Dublin.. Refused or withdrawn (23 Feb 2006). Builds a new five-bedroom, two-storey detached house beside 107 Cherrywood Road. - [DZ20A/0824](https://cherrywoodplans.com/application/DZ20A-0824.md): Lands (c. 17.01 ha), in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18, (also Co Dublin). Granted (11 Jan 2021). Changes the windows, balconies and frontage of Town Centre Block F2 on Cherrywood Avenue and Central Avenue. - [DZ19A/0148](https://cherrywoodplans.com/application/DZ19A-0148.md): 17.01 ha in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18 (also Co. Dublin). Granted (24 Apr 2019). Amends Town Centre plot TC2 to add 47 apartments, taking Blocks C1 and C2 from 384 to 431 homes. - [D07A/0654](https://cherrywoodplans.com/application/D07A-0654.md): Block AD, Cherrywood Science & Technology Park, Loughlinstown, Co. Dublin.. Granted (6 Jul 2007). Signs and a refuse store for the crèche in Block AD, Cherrywood Science & Technology Park. - [D06A/1722](https://cherrywoodplans.com/application/D06A-1722.md): Block AD, Cherrywood Science & Technology, Park, Cherrywood, Loughlinstown, Co. Dublin.. Granted (26 Jan 2007). Part of Block AD in Cherrywood Science & Technology Park changes from offices to a 952 sq.m crèche. - [DZ17A/0061](https://cherrywoodplans.com/application/DZ17A-0061.md): Building 4 (previously Block AD), Cherrywood Business Park, Cherrywood, Dublin 18. Granted (16 Mar 2017). Turns 1,035 sq.m of vacant office space in Building 4, Cherrywood Business Park, into a medical research laboratory. - [DZ19A/1022](https://cherrywoodplans.com/application/DZ19A-1022.md): On a site of 0.625ha, Dell Technologies, Block AB, Cherrywood Business Park, Cherrywood, Dublin 18. Granted (25 Feb 2020). Replaces two lit signs on the Dell Technologies building, Block AB, Cherrywood Business Park. - [DZ17A/0466](https://cherrywoodplans.com/application/DZ17A-0466.md): Block AB of CHerrywood, Science and Technology Park, Loughlinstown, Dublin 18. Granted (13 Jul 2017). Replaces signs at Block AB, Cherrywood Business Park, with two lit wall signs and a totem sign. - [DZ23A/0423](https://cherrywoodplans.com/application/DZ23A-0423.md): On lands (c.17.03 a) in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18 (Also Co. Dublin). Granted (10 Aug 2023). Amends the Cherrywood Town Centre permission to add two 2-bed apartments to Block A1. - [DZ22A/0690](https://cherrywoodplans.com/application/DZ22A-0690.md): Townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18, (also Co Dublin). Granted (12 May 2023). Facade and balcony design changes to Cherrywood Town Centre apartment Blocks A1, A2 and A3. - [DZ22A/0747](https://cherrywoodplans.com/application/DZ22A-0747.md): Townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18, (also Co Dublin). Granted (30 Mar 2023). Changes of use and merging of units in Town Centre Blocks C1 and C2 to create a larger 723 sq.m shop with off-licence. - [DZ22A/0846](https://cherrywoodplans.com/application/DZ22A-0846.md): Lands (c. 17.03 ha) in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18 (also Co. Dublin). Granted (22 Dec 2022). Removes a planned viewing platform at Block F1 in Cherrywood Town Centre, replacing it with a glass balustrade. - [DZ22A/0138](https://cherrywoodplans.com/application/DZ22A-0138.md): (c. 17.03ha) in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18, (also Co Dublin). Granted (30 Aug 2022). Minor changes of use between shop and restaurant-type units in Town Centre Blocks C1 and C2, and a slightly larger crèche. - [DZ21A/0807](https://cherrywoodplans.com/application/DZ21A-0807.md): Lands (c. 17.03 ha), in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18, (also Co Dublin). Granted (8 Jul 2022). Amends the Cherrywood Town Centre permission to cut residential parking from 1,363 to 1,169 spaces and add 41 car-sharing spaces. - [DZ21A/0713](https://cherrywoodplans.com/application/DZ21A-0713.md): Lands (c. 17.01 ha) in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18, (also Co Dublin). Granted (3 Oct 2021). Design changes to the three apartment blocks A1–A3 in Cherrywood Town Centre, including taller windows and smaller roof terrace. - [DZ19A/1024](https://cherrywoodplans.com/application/DZ19A-1024.md): 17.01 ha in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18 (also Co. Dublin). Granted (9 Sep 2020). Amends the Cherrywood Town Centre plan to shrink the basement under Blocks A1–A3 and reassign parking. - [DZ20A/0002](https://cherrywoodplans.com/application/DZ20A-0002.md): Lands (c.17.01ha) in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18 (also Co. Dublin). Granted (9 Sep 2020). Makes minor changes to electrical rooms and landscaping in Town Centre Blocks F1 and F3. - [DZ19A/0458](https://cherrywoodplans.com/application/DZ19A-0458.md): 17.01 ha in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18 (also Co. Dublin). Granted (19 Jun 2020). Major redesign of Cherrywood Town Centre plot TC1, adding two supermarkets, an 11-screen cinema and much more retail space. - [D03A/0626](https://cherrywoodplans.com/application/D03A-0626.md): Cherrywood Science & Technology Park, Cherrywood Business Park 1, Cherrywood, Loughlinstown, Co. Dublin. Granted (22 Sep 2003). A new office building of three storeys plus penthouse at Cherrywood Science & Technology Park, with 350 basement car spaces. - [D04A/1361](https://cherrywoodplans.com/application/D04A-1361.md): Cherrywood Science & Technology Park, Cherrywood, Loughlinstown, Co. Dublin.. Granted (12 Jan 2005). Extends the approved third floor of the Block AC office building over two terraces and moves all rooftop plant onto the roof. - [D04A/0335](https://cherrywoodplans.com/application/D04A-0335.md): Cherrywood Science & Technology Park,, Cherrywood, Loughlinstown, Co. Dublin.. Granted (26 May 2004). Builds a new office building of three storeys plus a penthouse over a basement car park at Cherrywood Business Park. - [D05A/0232](https://cherrywoodplans.com/application/D05A-0232.md): Cherrywood Science Technology Park, Loughlinstown, Co. Dublin.. Granted (20 Apr 2005). Adds two windows to the west side of the approved third floor of the Block AC office building. - [D04A/0915](https://cherrywoodplans.com/application/D04A-0915.md): Block AC, Cherrywood Business Park, Loughlinstown, Co. Dublin.. Granted (10 Nov 2004). Enlarges the approved link between office Blocks AC and AB, adding 990 sq.m of floor space. - [DZ18A/1178](https://cherrywoodplans.com/application/DZ18A-1178.md): 2.2 ha in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18 (also Co. Dublin). Granted (17 Apr 2019). Amends Town Centre plot TC2 to add one apartment, expand retail and resident amenity space, and move the crèche. - [D05A/1057](https://cherrywoodplans.com/application/D05A-1057.md): Blocks AB/AC, Cherrywood Science & Technology Park, Cherrywood, Co. Dublin. Granted (10 Oct 2005). Adds emergency exit doors and a screened rooftop plant room to office Blocks AB and AC. - [D13A/0117](https://cherrywoodplans.com/application/D13A-0117.md): Block AB Cherrywood Science & Technology Park, Loughlinstown, Dublin 18. Granted (8 May 2013). Puts up two lit Dell logo signs on Block AB at Cherrywood Business Park. - [D04A/1211](https://cherrywoodplans.com/application/D04A-1211.md): Cherrywood Road Bus Stop, (opposite Lucent), Loughlinstown, Co. Dublin. Refused or withdrawn (29 Jun 2005). Installs a steel and glass bus shelter with two lit advertising panels on Cherrywood Road. ## Links - [This page on CherrywoodPlans](https://cherrywoodplans.com/application/DZ17A-0731) - [Council record, documents and conditions (DLR planning portal)](https://planning.agileapplications.ie/dunlaoghaire/application-details/76092) - [All Cherrywood applications](https://cherrywoodplans.com/applications.md) _Source: Dún Laoghaire–Rathdown County Council planning data, refreshed daily. CherrywoodPlans is an independent site, not run by the council._