# Planning application DZ23A/0423 > On lands (c.17.03 a) in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18 (Also Co. Dublin), Cherrywood, Dún Laoghaire–Rathdown. Granted (10 Aug 2023). - **Reference:** DZ23A/0423 - **Address:** On lands (c.17.03 a) in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18 (Also Co. Dublin) - **Status:** Granted (10 Aug 2023) - **Decision:** GRANT PERMISSION - **Application type:** Permission (SDZ) - **Applicant:** CWTC Multi Family ICAV Acting TC1 Fund, CW TC2 Fund, CW TC4 Fund & CW Mixed Fund - **Lodged:** 23 Jun 2023 - **Decided:** 10 Aug 2023 - **Location (lat, lng):** 53.243918, -6.146549 ## Proposal Development on lands. The proposed development is an amendment application to DZ17A/0862 (as further amended by DZ18A/1058, DZ18A/1178, DZ19A/0148, DZ19A/0458, DZ19A/1024, DZ20A/0002, and DZ20A/0824, DZ21A/0569, DZ21A/0713, DZ21A/0807, DZ22A/0138, DZ22A/0690, DZ22A/0846 & DZ22A/0747). The proposed amendments relate to the provision of 2 no. additional units within TC1, and comprises of works as follows: 1) The proposed development at Block A1 provides for a new localised mezzanine level located between ground and first floor level to provide for an additional 2 no. 2 bed residential units of 76 sq.m and 79 sq.m including an additional 20 sq.m of associated ancillary residential space also at mezzanine level for access. The overall increase residential gross floor space by 175 sq.m, to a total of 32,169 sq.m within TC1; 2) Utilisation of new windows along the northern external facade and the southern facade facing the internal courtyard permitted under Reg. Ref DZ22A/0690, with access via the existing stair core no. 8. The additional units are to be provided with associated private amenity space in the form of balconies along the internal and external facade; 3) Provision of designated parking at basement level for the two units; 4) Provision access to apartments from the existing stair core no. 8, through the provision of an access door to the permitted core from the proposed access hallway at mezzanine level. ## In plain English Amends the Cherrywood Town Centre permission to add two 2-bed apartments to Block A1. - **2** extra apartments - **175** sq.m added ### What's planned An amendment to the earlier Town Centre permission (DZ17A/0862) in plot TC1. ### Residential A new mezzanine floor in Block A1 creates **2** two-bed apartments (**76** and **79** sq.m) with balconies, adding **175** sq.m and bringing residential space in TC1 to **32,169** sq.m. ### Transport Basement parking is designated for the two units. _This summary was written by AI from the proposal text. Check the council record before relying on it._ ## Conditions ### Condition 1 First Schedule Reasons and Considerations Having regard to the ‘Town Centre’ land use of the site as set out in the Cherrywood Planning Scheme, as amended, and 2022-2028 Dún Laoghaire - Rathdown County Development Plan, it is considered that the proposed development would not seriously injure the amenities of the area and would not contravene materially the zoning of the application site or that of adjoining sites, subject to compliance with conditions below. Appropriate Assessment Screening The proposed development has been screened for AA by the Planning Authority (Planning Authority report on file), and it has been determined that the proposed development will not significantly impact upon a Natura 2000 site. Environmental Impact Assesment An Environmental Impact Assessment Report (EIAR) was prepared as part of parent application DZ17A/0862 which had regard to and built upon the Strategic Environmental Assessment prepared with the Cherrywood Planning Scheme. The EIAR considered the likely, significant and adverse effects on the receiving environment of the original Cherrywood Town Centre development proposal, of which this amendment application relates. Mitigation measures were incorporated into the design of the proposed development and the EIAR concluded that ‘There is no material or significant environmental issues arising (from the development) which were not anticipated by the Cherrywood Planning Scheme and considered in its Strategic Environmental Assessment.’ It is the responsibility of the competent authority (Dún Laoghaire-Rathdown County Council) to undertake a screening for Environmental Impact Assessment (EIA).Having regard to the nature and scale of the proposed development, there is no real likelihood of significant effects on the environment arising from the proposed development. Second Schedule Conditions General 1. (a)The development shall be carried out in its entirety in accordance with the plans, particulars and specifications lodged with the application, save for amendments granted on foot of this permission, the development shall otherwise be carried out in strict accordance with the terms and conditions of Planning Permissions DZ17A/0862,as amended,save as may be required by the other conditions attached hereto.No other development or amendments are permitted on foot of this planning permission. REASON: In the interest of the proper planning and sustainable development of the area and to ensure that the proposed development is consistent with the Cherrywood Planning Scheme. 2. Prior to the completion of development, the developer shall submit for the written agreement of the Planning Authority, all drawings in digital format (CAD/GIS) projected to ITM (Irish Transverse Mercator). These shall include those for DZ17A/0862 as amended and further amended by this permission. This information should include the following: Overall site plans in DWG format (ITM projection in metres) Ground floor plans of buildings in DWG format (ITM projection in metres) Site sections and elevations in PDF format. REASON: To ensure consistency with Section 7.4 of the Cherrywood Planning Scheme. 3. Within 1 month from the date of this permission, or as otherwise agreed, the Developer shall submit to the Planning Authority for written agreement a Schedule which confirms for each of the relevant blocks, A1, A2 and A3, the final number of dwellings; mix of dwellings by number of bedrooms, and the extent of floorspace for each use within the blocks. REASON: In the interests of clarity, and to ensure consistency with Chapters 2 and 6 of the Cherrywood Planning Scheme. 4. Prior to the commencement of development of the 2 new residential units the subject of this permission, the Applicant/Developer shall submit for the written agreement of the Planning Authority an architectural/engineering drawing that clearly identifies the provision and location of the additional 2 no. long term cycle parking spaces associated with the 2 new residential units. REASON: To ensure consistency with Cherrywood Planning Scheme specific objective PI 22 and in the interest of sustainable development and proper planning. 5. The Developer shall, prior to commencement or as otherwise agreed in writing with the Planning Authority, pay the sum of €675.00 to the Planning Authority as a contribution towards expenditure that was/or is proposed to be incurred by the Planning Authority in respect of the provision of Surface Water Public Infrastructure and Facilities benefiting development in the area of the Authority, as provided for in the Development Contribution Scheme made by Dún Laoghaire-Rathdown County Council on the 14th December, 2015 and as included in Table 2 of the Cherrywood Planning Scheme Development Contribution Scheme 2017-2020. These rates of contribution shall be updated effective from 1 January each year during the life of the Scheme in accordance with the SCSI Tender Price Index (See Article 12 of the Scheme ) commencing from 1st January, 2018. Contributions shall be payable at the index adjusted rate pertaining to the year in which implementation of the planning permission is commenced, as provided for in Note 1 to the Table at Article 9 of the Scheme. Outstanding balances may be subject to interest charges. REASON: It is considered reasonable that the payment of a contribution be required in respect of the provision of the Surface Water Public Infrastructure and Facilities benefiting development in the area of the Planning Authority and that is provided, or that is intended will be provided, by or on behalf of the Local Authority. Note on above Condition: Please note that with effect from 1st January, 2014 Irish Water are now the statutory body responsible for both water and waste water services. Accordingly, the contribution payable has been reduced by the amount of the contribution associated with these services. Further details/clarification can be obtained from Irish Water at Tel. 1 850 278 278. 6. The Developer shall, prior to commencement or as otherwise agreed in writing with the Planning Authority, pay the sum of €15,457.90 to the Planning Authority as a contribution towards expenditure that was/or is proposed to be incurred by the Planning Authority in respect of the provision of the Roads Public Infrastructure and Facilities benefiting development in the area of the Authority, as provided for in the Development Contribution Scheme made by Dún Laoghaire-Rathdown County Council on the 14th December, 2015 and as included in Table 2 of the Cherrywood Planning Scheme Development Contribution Scheme 2017-2020. These rates of contribution shall be updated effective from 1 January each year during the life of the Scheme in accordance with the SCSI Tender Price Index (See Article 12 of the Scheme) commencing from 1st January, 2018. Contributions shall be payable at the index adjusted rate pertaining to the year in which implementation of the planning permission is commenced, as provided for in Note 1 to the Table at Article 9 of the Scheme. Outstanding balances may be subject to interest charges. REASON: It is considered reasonable that the payment of a contribution be required in respect of the provision of the Roads Public Infrastructure and Facilities benefiting development in the area of the Planning Authority and that is provided, or that is intended will be provided, by or on behalf of the Local Authority. 7. The Developer shall, prior to commencement or as otherwise agreed in writing with the Planning Authority, pay the sum of €10,034.12 to the Planning Authority as a contribution towards expenditure that was/or is proposed to be incurred by the Planning Authority in respect of the provision of the Community & Parks Public Infrastructure, Facilities and Amenities benefiting development in the area of the Authority, as provided for in the Development Contribution Scheme made by Dún Laoghaire-Rathdown County Council on the 14th December, 2015 and as included in Table 2 of the Cherrywood Planning Scheme Development Contribution Scheme 2017-2020. These rates of contribution shall be updated effective from 1 January each year during the life of the Scheme in accordance with the SCSI Tender Price Index (See Article 12 of the Scheme) commencing from 1st January, 2018. Contributions shall be payable at the index adjusted rate pertaining to the year in which implementation of the planning permission is commenced, as provided for in Note 1 to the Table at Article 9 of the Scheme. Outstanding balances may be subject to interest charges. REASON: It is considered reasonable that the payment of a contribution be required in respect of the provision of the Community & Parks Public Infrastructure, Facilities and Amenities benefiting development in the area of the Planning Authority and that is provided, or that is intended will be provided, by or on behalf of the Local Authority. 8. The Developer shall, prior to commencement or as otherwise agreed in writing with the Planning Authority, pay the sum of €1,334.54 to the Planning Authority as a contribution towards expenditure that was/or is proposed to be incurred by the Planning Authority in respect of the provision of Surface Water Public Infrastructure and Facilities in the Cherrywood Planning Scheme Area. This Cherrywood Planning Scheme element of the Development Contribution shall be used solely to fund infrastructure identified in the Plan, as listed in Appendix III – Cherrywood Planning Scheme Projects List, as provided for in the Development Contribution Scheme made by Dún Laoghaire-Rathdown County Council on the 12/06/2017. These rates of contribution shall be updated effective from 1 January each year during the life of the Scheme in accordance with the SCSI Tender Price Index (See Article 12 of the Scheme) commencing from 1st January, 2018. Contributions shall be payable at the index adjusted rate pertaining to the year in which implementation of the planning permission is commenced, as provided for in Note 1 to the Table at Article 9 of the Scheme. Outstanding balances may be subject to interest charges. REASON: It is considered reasonable that the payment of a contribution be required in respect of the provision of the Surface Water Public Infrastructure and Facilities benefiting development in the in the Cherrywood Planning Scheme area and that is provided, or that is intended will be provided, by or on behalf of the Local Authority. 9. The Developer shall, prior to commencement or as otherwise agreed in writing with the Planning Authority, pay the sum of €8,556.40 to the Planning Authority as a contribution towards expenditure that was/or is proposed to be incurred by the Planning Authority in respect of the provision of the Roads Public Infrastructure and Facilities in the Cherrywood Planning Scheme Area. This Cherrywood Planning Scheme element of the Development Contribution shall be used solely to fund infrastructure identified in the Plan, as listed in Appendix III – Cherrywood Planning Scheme Projects List, as provided for in the Development Contribution Scheme made by Dún Laoghaire-Rathdown County Council on the 12/06/2017. These rates of contribution shall be updated effective from 1 January each year during the life of the Scheme in accordance with the SCSI Tender Price Index (See Article 12 of the Scheme) commencing from 1st January, 2018. Contributions shall be payable at the index adjusted rate pertaining to the year in which implementation of the planning permission is commenced, as provided for in Note 1 to the Table at Article 9 of the Scheme. Outstanding balances may be subject to interest charges. REASON: It is considered reasonable that the payment of a contribution be required in respect of the provision of the Roads Public Infrastructure and Facilities benefiting development in the Cherrywood Planning Scheme Area of the Planning Authority and that is provided, or that is intended will be provided, by or on behalf of the Local Authority. 10. The Developer shall, prior to commencement or as otherwise agreed in writing with the Planning Authority, pay the sum of €2,322.46 to the Planning Authority as a contribution towards expenditure that was/or is proposed to be incurred by the Planning Authority in respect of the provision of the Community & Parks Public Infrastructure Facilities in the Cherrywood Planning Scheme Area. This Cherrywood Planning Scheme element of the Development Contribution shall be used solely to fund infrastructure identified in the Plan, as listed in Appendix III - Cherrywood Planning Scheme Projects List, as provided for in the Development Contribution Scheme made by Dún Laoghaire-Rathdown County Council on the 12/06/2017. These rates of contribution shall be updated effective from 1 January each year during the life of the Scheme in accordance with the SCSI Tender Price Index (See Article 12 of the Scheme) commencing from 1st January, 2018. Contributions shall be payable at the index adjusted rate pertaining to the year in which implementation of the planning permission is commenced, as provided for in Note 1 to the Table at Article 9 of the Scheme. Outstanding balances may be subject to interest charges. REASON: It is considered reasonable that the payment of a contribution be required in respect of the provision of the Community & Parks Public Infrastructure Facilities & Amenities benefiting development in the Cherrywood Planning Scheme Area of the Planning Authority and that is provided, or that is intended will be provided, by or on behalf of the Local Authority. 11. No development on foot of this permission shall commence until security for the provision and satisfactory completion of services (including roads, footpaths, open spaces, public lighting, sewers, watermains and drains) in accordance with the Plans and particulars lodged with the application, has been given by:- a) Lodgement with the Council of an approved Insurance Company Bond in the sum of €5,800.00 which shall be kept in force by the Developer until such time as Roads, Open Spaces, Car Parks, Sewers, Watermains and Drains are completed to the satisfaction of the Council OR/... b) Lodgement with the Council of a Cash Sum of €3,600.00 to be applied by the Council at its absolute discretion if such services are not duly provided to its satisfaction on the provision and completion of such services to standard specifications. REASON: To ensure that a ready sanction may be available to the Council to induce the provision of services and prevent disamenity in the development 12. This development shall not be carried out without prior agreement, in writing, between the Applicant and the Planning Authority relating to the payment of development contributions. REASON: Investment by Dún Laoghaire-Rathdown County Council in Local Authority works has facilitated and will facilitate the proposed development. It is considered appropriate and reasonable that the developer should contribute to the cost of same. Note 1: That water supply and foul drainage shall be in accordance with the requirements of Irish Water. Note: 2: The attention of the applicant is drawn to Section 34(13) of the Planning and Development Act 2000, as amended, which relates as follows- ‘A person shall not be entitled solely by reason of a permission under this section to carry out any development’. ## Nearby applications - [DZ22A/0690](https://cherrywoodplans.com/application/DZ22A-0690.md): Townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18, (also Co Dublin). Granted (12 May 2023). Facade and balcony design changes to Cherrywood Town Centre apartment Blocks A1, A2 and A3. - [DZ22A/0747](https://cherrywoodplans.com/application/DZ22A-0747.md): Townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18, (also Co Dublin). Granted (30 Mar 2023). Changes of use and merging of units in Town Centre Blocks C1 and C2 to create a larger 723 sq.m shop with off-licence. - [DZ22A/0846](https://cherrywoodplans.com/application/DZ22A-0846.md): Lands (c. 17.03 ha) in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18 (also Co. Dublin). Granted (22 Dec 2022). Removes a planned viewing platform at Block F1 in Cherrywood Town Centre, replacing it with a glass balustrade. - [DZ22A/0138](https://cherrywoodplans.com/application/DZ22A-0138.md): (c. 17.03ha) in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18, (also Co Dublin). Granted (30 Aug 2022). Minor changes of use between shop and restaurant-type units in Town Centre Blocks C1 and C2, and a slightly larger crèche. - [DZ21A/0807](https://cherrywoodplans.com/application/DZ21A-0807.md): Lands (c. 17.03 ha), in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18, (also Co Dublin). Granted (8 Jul 2022). Amends the Cherrywood Town Centre permission to cut residential parking from 1,363 to 1,169 spaces and add 41 car-sharing spaces. - [DZ21A/0713](https://cherrywoodplans.com/application/DZ21A-0713.md): Lands (c. 17.01 ha) in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18, (also Co Dublin). Granted (3 Oct 2021). Design changes to the three apartment blocks A1–A3 in Cherrywood Town Centre, including taller windows and smaller roof terrace. - [DZ19A/1024](https://cherrywoodplans.com/application/DZ19A-1024.md): 17.01 ha in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18 (also Co. Dublin). Granted (9 Sep 2020). Amends the Cherrywood Town Centre plan to shrink the basement under Blocks A1–A3 and reassign parking. - [DZ20A/0002](https://cherrywoodplans.com/application/DZ20A-0002.md): Lands (c.17.01ha) in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18 (also Co. Dublin). Granted (9 Sep 2020). Makes minor changes to electrical rooms and landscaping in Town Centre Blocks F1 and F3. - [DZ19A/0458](https://cherrywoodplans.com/application/DZ19A-0458.md): 17.01 ha in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18 (also Co. Dublin). Granted (19 Jun 2020). Major redesign of Cherrywood Town Centre plot TC1, adding two supermarkets, an 11-screen cinema and much more retail space. - [DZ20A/0824](https://cherrywoodplans.com/application/DZ20A-0824.md): Lands (c. 17.01 ha), in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18, (also Co Dublin). Granted (11 Jan 2021). Changes the windows, balconies and frontage of Town Centre Block F2 on Cherrywood Avenue and Central Avenue. - [DZ19A/0148](https://cherrywoodplans.com/application/DZ19A-0148.md): 17.01 ha in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18 (also Co. Dublin). Granted (24 Apr 2019). Amends Town Centre plot TC2 to add 47 apartments, taking Blocks C1 and C2 from 384 to 431 homes. - [DZ23A/0573](https://cherrywoodplans.com/application/DZ23A-0573.md): Lands (c. 17.03 ha) in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18 (also Co. Dublin). Granted (19 Oct 2023). Amends the Cherrywood Town Centre permission to add 4 apartments in Blocks F2 and F3, bringing plot TC4 to 524 homes. - [DZ17A/0862](https://cherrywoodplans.com/application/DZ17A-0862.md): Lands (17.01ha) in the townlands of Cherrywood, Dublin 18. Granted (29 May 2018). The original Cherrywood Town Centre permission: 15 blocks with 1,269 homes, shops, offices, two hotels and a library, plus Grand Parade. - [DZ26A/0032/WEB](https://cherrywoodplans.com/application/DZ26A-0032-WEB.md): Block A1, The Tully Building, Civic Street, Cherrywood Town Centre, Dublin 18, D18WDK0. Granted (13 Mar 2026). Revised plan for 24 mobile phone antennas and 9 dishes on Block A1, The Tully Building, after an earlier compliance submission was rejected. - [DZ25A/0485/WEB](https://cherrywoodplans.com/application/DZ25A-0485-WEB.md): Block A1, Tully Buildings, Cherrywood, Dublin 18. Granted (1 Aug 2025). 24 mobile phone antennas and 9 dishes on the facade and roof of Block A1, Tully Buildings. - [D06A/1660](https://cherrywoodplans.com/application/D06A-1660.md): Park One, Cherrywood Science And Technology Park, Loughlinstown, Co. Dublin.. Granted (6 Mar 2007). Completes the distributor road through Park One at Cherrywood Business Park, letting overhead power lines go underground. - [DZ20A/0877](https://cherrywoodplans.com/application/DZ20A-0877.md): Bishop Street, Cherrywood, Dublin 18, Co Dublin. Granted (29 Jan 2021). Installs a small gas regulator building on Bishop Street near the Luas line. - [D04A/1013](https://cherrywoodplans.com/application/D04A-1013.md): Laughanstown/Cherrywood, With Access From N11, Wyattville Road, Co. Dublin.. Refused or withdrawn (9 May 2005). Seeks to keep modified land shaping and drainage works on a 36-hectare site at Laughanstown/Cherrywood and further alter them. - [DZ18A/1178](https://cherrywoodplans.com/application/DZ18A-1178.md): 2.2 ha in the townlands of Cherrywood, Laughanstown, Loughlinstown and Glebe, Dublin 18 (also Co. Dublin). Granted (17 Apr 2019). Amends Town Centre plot TC2 to add one apartment, expand retail and resident amenity space, and move the crèche. - [DZ22A/0952](https://cherrywoodplans.com/application/DZ22A-0952.md): The Hunt Building, Grand Parade, Cherrywood Town Centre, Dublin 18. Refused or withdrawn (1 Feb 2023). 6 mobile phone antennas and 2 dishes on the roof of The Hunt Building, Grand Parade. - [DZ22A/0796](https://cherrywoodplans.com/application/DZ22A-0796.md): The Hunt Building, Grand Parade, Cherrywood Town Centre, Dublin 18. Refused or withdrawn (23 Nov 2022). 6 mobile phone antennas and 2 dishes, finished to look like brick, on the roof of The Hunt Building, Grand Parade. - [DZ22A/0591](https://cherrywoodplans.com/application/DZ22A-0591.md): C. 3.71 in the Townland of Cherrywood, Block Town Centre 3 (TC3), Dublin 18. Granted (20 Jun 2023). 418 build-to-rent apartments in four blocks of up to 5 storeys at Town Centre 3, with shops, cafés and community space. - [ABP30342919](https://cherrywoodplans.com/application/ABP30342919.md): Site (c.3.06ha) in the townlands of Laughanstown, Dublin 18 (lands generally bounded by Bishop Street to the south, the Luas green line to the east and Tully park to the north. Granted (18 Apr 2019). Builds 184 homes, a mix of apartments, two-level units and houses, between Bishop Street, the Luas line and Tully Park. - [DZ24A/1030/WEB](https://cherrywoodplans.com/application/DZ24A-1030-WEB.md): In the Townlands of Laughanstown and Cherrywood, Cherrywood, Dublin 18. Granted (11 Jun 2025). Amends a permitted scheme off Tully Vale Road to add 59 apartments by raising four blocks by one or two storeys. - [DZ20A/0052](https://cherrywoodplans.com/application/DZ20A-0052.md): 1.86 ha in the townlands of Cherrywood, Dublin 18 (also Co. Dublin)--TC3. Granted (13 Apr 2021). A mixed-use block at Town Centre 3 with an 8-storey office building and 198 build-to-rent apartments. - [D04A/1012](https://cherrywoodplans.com/application/D04A-1012.md): Cherrywood/Glebe, (ED Rathmichael), Wyvattville Link Road, Co. Dublin.. Refused or withdrawn (9 May 2005). Reshapes and drains an 8.6-hectare site at Cherrywood/Glebe and stores topsoil on a further 5.1 hectares at Laughanstown. - [DZ22A/0093](https://cherrywoodplans.com/application/DZ22A-0093.md): Townland of Laughanstown, Dublin 18. Granted (1 Apr 2022). Seeks to keep two advertising signs for Cherrywood housing for 3 more years. - [DZ18A/0499](https://cherrywoodplans.com/application/DZ18A-0499.md): Lands (c.1.22ha) in the townlands of Cherrywood & Laughanstown, Dublin 18. Granted (11 Jan 2019). 146 apartments in four 4-storey blocks off Grand Parade on plot TC5. - [DZ25A/0325/WEB](https://cherrywoodplans.com/application/DZ25A-0325-WEB.md): In the Townlands of Laughanstown and Cherrywood, Cherrywood, Dublin 18. Granted (15 Jan 2026). 121 apartments in two blocks of 3 to 5 storeys off Cherrywood Avenue in Macnebury. - [DZ25A/0102/WEB](https://cherrywoodplans.com/application/DZ25A-0102-WEB.md): In the Townlands of Laughanstown, in Cherrywood, Dublin 18. Granted (26 May 2025). Amends a permitted 200-apartment scheme in Macnebury to drop its basement and cut car parking from 241 to 160 spaces. - [DZ24A/1024/WEB](https://cherrywoodplans.com/application/DZ24A-1024-WEB.md): In the Townlands of Laughanstown and Cherrywood, in Cherrywood,, Dublin 18. Granted (1 May 2025). Amends a permitted Macnebury apartment scheme to cut car parking from 312 to 213 spaces and add bike, bin and storage buildings, with no change to the homes. - [DZ25A/0008/WEB](https://cherrywoodplans.com/application/DZ25A-0008-WEB.md): In the Townlands of Laughanstown and Cherrywood, in Cherrywood, Dublin 18. Refused or withdrawn (6 Feb 2025). Amends a permitted 200-apartment scheme in Macnebury to drop its basement and cut car parking from 241 to 160 spaces. - [DZ24A/1016/WEB](https://cherrywoodplans.com/application/DZ24A-1016-WEB.md): In the Townlands of Laughanstown and Cherrywood, in Cherrywood, Dublin 18. Refused or withdrawn (3 Jan 2025). Amends a permitted Macnebury development by removing its basement and cutting car parking from 241 to 160 spaces. - [DZ24A/0017](https://cherrywoodplans.com/application/DZ24A-0017.md): Townlands of Laughanstown and Cherrywood, Macnebury - Development Area 7 - Cherrywood, Dublin 18. Granted (11 Jun 2024). 200 apartments in three blocks of 4 to 5 storeys off Cherrywood Avenue in Macnebury. - [DZ23A/0811](https://cherrywoodplans.com/application/DZ23A-0811.md): In the Townlands of Laughanstown and Cherrywood. Macnebury, Development Area 7 , Cherrywood, Dublin 18. Refused or withdrawn (4 Jan 2024). 200 apartments in three blocks of 4 to 5 storeys off Cherrywood Avenue in Macnebury. - [DZ22A/1021](https://cherrywoodplans.com/application/DZ22A-1021.md): Lands within Development Area 7 - Macnebury, including part of the Res 3 plot known as M1 located south of Bishop Street, west of Cherrywood Avenue, east and north of the proposed Beckett Road, Laughanstown, Dublin 18. Granted (27 Jun 2023). 283 new homes, mostly apartments in four blocks of 4–5 storeys, plus a crèche, south of Bishop Street in Macnebury. - [D07A/1770](https://cherrywoodplans.com/application/D07A-1770.md): Cherrywood Science & Technology Park, Loughlinstown, Co. Dublin.. Refused or withdrawn (28 Jan 2008). Builds a multi-storey car park with 1,081 spaces and 10 ground-floor shops at Cherrywood Business Park. - [DZ21A/1017](https://cherrywoodplans.com/application/DZ21A-1017.md): Townlands of Laughanstown, Glebe, and Cherrywood, Dublin 18, (also Co Dublin). Granted (11 Nov 2022). About 1.6km of new roads including Beckett Road with an underpass below the Wyattville Link Road, plus a park around an ancient wedge tomb. - [D15A/0355](https://cherrywoodplans.com/application/D15A-0355.md): Site located in the green area at the entrance to, Druid Valley Estate, Cabinteely, Dublin 18. Refused or withdrawn (9 Jul 2015). Installs a small gas safety regulator unit on the green at the entrance to Druid Valley. - [DZ26B/0241/WEB](https://cherrywoodplans.com/application/DZ26B-0241-WEB.md): 17 Domville Court, Cherrywood, Dublin 18, D18WEK6. Granted (10 Jun 2026). Permission to keep a glass conservatory permanently in the back garden of a house on Domville Court. - [DZ26B/0073/WEB](https://cherrywoodplans.com/application/DZ26B-0073-WEB.md): 17 Domville Court, Cherrywood, Dublin 18, D18WEK6. Refused or withdrawn (13 Mar 2026). Permission to keep a glass conservatory built in the back garden of a house on Domville Court. - [DZ23A/0242](https://cherrywoodplans.com/application/DZ23A-0242.md): Townland of Cherrywood Dublin 18 The site is located in the Cherrywood Planning Scheme and forms part of the south eastern porti. Granted (7 Jun 2023). Changes to the permitted basement at Town Centre 3 so it can later connect to the wider TC3 basement. - [DZ21A/0785](https://cherrywoodplans.com/application/DZ21A-0785.md): c.0.95 ha townland, Cherrywood, Dublin 18 (also Co. Dublin). Granted (30 Mar 2022). An office building of up to 8 storeys with ground-floor cafés at the corner of Town Centre 3, beside the Bride's Glen Luas stop. - [DZ26B/0030/WEB](https://cherrywoodplans.com/application/DZ26B-0030-WEB.md): 17 Domville Court, Tullyvale, Cherrywood, Dublin 18, D18 WEK6. Refused or withdrawn (28 Jan 2026). Permission to keep a glass conservatory built in the back garden of a house on Domville Court. - [DZ25A/0489/WEB](https://cherrywoodplans.com/application/DZ25A-0489-WEB.md): 20, Domville Court, Tullyvale, Cherrywood, Dublin 18, D18VN3A. Granted (11 Aug 2025). Permission to keep a glass conservatory permanently at the back of a house on Domville Court. - [DZ25A/0480/WEB](https://cherrywoodplans.com/application/DZ25A-0480-WEB.md): 20, Domville Court, Tullyvale, Cherrywood, Dublin 18, D18VN3A. Refused or withdrawn (19 Jun 2025). Permission to keep a glass conservatory at the back of a house on Domville Court. - [DZ17A/0161](https://cherrywoodplans.com/application/DZ17A-0161.md): Lands (site area c.0.95ha) in the townland of Laughanstown, Dublin 18. Granted (12 Dec 2017). Sets up a temporary concrete plant for 7 years to supply the building of Cherrywood. - [DZ25A/0161/WEB](https://cherrywoodplans.com/application/DZ25A-0161-WEB.md): Lands in the townlands of Laughanstown, Dublin 18. The application relates to development in Cherrywood Strategic Development Zone. Granted (23 Apr 2025). Completion of a 145-metre stretch of Grand Parade from Tully Vale Road towards Bishop Street. - [D02A/0508](https://cherrywoodplans.com/application/D02A-0508.md): Building H, Cherrywood Science & Technology Park,, Cherrywood, Loughlinstown, Co. Dublin.. Granted (22 Jul 2002). Adds 15 parking spaces to the car park serving Building H at Cherrywood Business Park. - [DZ26A/0001/WEB](https://cherrywoodplans.com/application/DZ26A-0001-WEB.md): Cherrywood Avenue, (Adjoining Cherrywood Business Park), Cherrywood, Dublin 18. Granted (29 Jun 2026). Amends a permitted apartment scheme on Cherrywood Avenue to go from 67 to 70 apartments, with more parking. - [DZ25A/0983/WEB](https://cherrywoodplans.com/application/DZ25A-0983-WEB.md): Cherrywood Avenue ( adjoining Cherrywood Business Park), Cherrywood, Dublin 18. Refused or withdrawn (22 Dec 2025). Amends a permitted apartment scheme on Cherrywood Avenue to go from 67 to 70 apartments, with more parking. - [D10A/0701](https://cherrywoodplans.com/application/D10A-0701.md): Cherrywood Science and Technology Park, Cherrywood, Loughlinstown, Co. Dublin.. Granted (24 May 2011). A 197-space surface park and ride car park beside the Brides Glen Luas stop. - [D03A/0479](https://cherrywoodplans.com/application/D03A-0479.md): ESB, Plot M, Cherrywood Science And Technology Park, Wyatville Link Road. Granted (14 Jul 2003). Seeks to keep an ESB 38 kV line mast already installed at Cherrywood Business Park. - [DZ22A/0681](https://cherrywoodplans.com/application/DZ22A-0681.md): Cherrywood Avenue, (Adjoining Cherrywood Business Park), Cherrywood, Dublin 18. Granted (28 Jun 2023). A 5-storey block of 70 apartments on Cherrywood Avenue, beside Cherrywood Business Park. - [DZ18A/0854](https://cherrywoodplans.com/application/DZ18A-0854.md): site (c.2.62 HA) at Cherrywood Business Park, Cherrywood Avenue, Cherrywood, Co. Dublin (also Dublin 18) (lands to the south and west of Blocks G and G2, south of Cherrywood Avenue). Granted (31 Oct 2018). Builds a three-pond drainage system with a walking and cycling route south of Cherrywood Avenue. - [DZ19A/0808](https://cherrywoodplans.com/application/DZ19A-0808.md): Cherrywood Business Park, Cherrywood & Loughlinstown, Co. Dublin, (Also Dublin 18). Granted (17 Dec 2019). Installs a small gas pressure regulator building in Cherrywood Business Park. - [DZ19A/0647](https://cherrywoodplans.com/application/DZ19A-0647.md): Cherrywood Business Park, Cherrywood & Loughlinstown, Co. Dublin, (Also Dublin 18). Refused or withdrawn (18 Sep 2019). Installs a small gas pressure regulator building in Cherrywood Business Park. - [DZ19A/0523](https://cherrywoodplans.com/application/DZ19A-0523.md): Cherrywood Business Park, Cherrywood & Loughlinstown, Co. Dublin, (Also Dublin 18). Refused or withdrawn (23 Aug 2019). Installs a small gas pressure regulator building in Cherrywood Business Park. - [DZ17A/0171](https://cherrywoodplans.com/application/DZ17A-0171.md): Cherrywood Business Park, Cherrywood, Dublin 18. Granted (21 Apr 2017). Seeks to keep the existing entrance and wayfinding signs at Cherrywood Business Park. - [DZ24A/1007/WEB](https://cherrywoodplans.com/application/DZ24A-1007-WEB.md): ‘Red Zone’ temporary surface car park, and Blocks F1-F3, ‘The Campus’, Cherrywood Avenue,, Cherrywood (Glebe Townland), Co. Dublin, Dublin 18. Granted (18 Feb 2025). Shrinking the temporary Red Zone car park on Cherrywood Avenue to about 398 spaces for another 5 years, and opening 226 basement spaces at The Campus. - [DZ22A/0728](https://cherrywoodplans.com/application/DZ22A-0728.md): Red Zone car park, Cherrywood Avenue, Cherrywood (Glebe Townland), Co Dublin/Dublin 18. Granted (14 Mar 2023). Keeping the temporary Red Zone surface car park for about 740 cars on Cherrywood Avenue for another 5 years. - [DZ20A/0477](https://cherrywoodplans.com/application/DZ20A-0477.md): Blocks F1,F2 & F3 (3no. office blocks under construction), Cherrywood Business Park, Cherrywood, Co. Dublin (also Dublin 18) & at the temporary surface car park at Cherrywood (Glebe Townland) Co. Dublin (also Dublin 18). Granted (28 Aug 2020). Allows up to 229 spaces in the basement car park of office Blocks F1–F3 to be used for temporary parking for 7 years. - [DZ17A/0417](https://cherrywoodplans.com/application/DZ17A-0417.md): Cherrywood Glebe Townland, Co Dublin ( Dublin 18) (Lands within Dev Area 6-Bride's Glen-bounded by M50 west, Cherrywood Ave & undeveloped lands to north undeveloped lands & Glencarrig res. estate east & res prop. & undev. lands off Brides Glen to south. Granted (7 Nov 2017). Uses land off Cherrywood Avenue as a temporary car park for about 740 cars for 5 years. - [DZ17A/0326](https://cherrywoodplans.com/application/DZ17A-0326.md): Cherrywood, Glebe Townland, Co Dublin (Also Dublin 18) (Lands within Dev Area 7-Macnebury-bounded by M50 to west, Cherrywood Ave & undeveloped lands to north, undeveloped lands & Glencarrig res. estate to east & undeveloped lands off Brides Glen to south. Refused or withdrawn (26 Apr 2017). Uses land off Cherrywood Avenue as a temporary car park for about 740 cars for 5 years. - [DZ25A/0543/WEB](https://cherrywoodplans.com/application/DZ25A-0543-WEB.md): Dlr Properties Limited, Hibernia House, Cherrywood Business Park, Dublin 18, D18E440. Granted (28 Aug 2025). Hibernia House in Cherrywood Business Park changes from offices to a medical centre with a pharmacy. - [DZ16A/0535](https://cherrywoodplans.com/application/DZ16A-0535.md): Hibernia House, Cherrywood Business Park, Loughlinstown, Dublin 18. Granted (9 Sep 2016). Puts up two high-level lit 'evros' signs on Hibernia House, Cherrywood Business Park. - [D06A/0911](https://cherrywoodplans.com/application/D06A-0911.md): Block D, Cherrywood Science & Technology Park, Cherrywood, Loughlinstown, Co. Dublin. Granted (23 Aug 2006). Makes internal changes to the Block D office building, enclosing its entrance and adding a fire escape stairs. - [D04A/0232](https://cherrywoodplans.com/application/D04A-0232.md): Block H, Cherrywood Science & Technology Park, Loughlinstown, Co. Dublin. Granted (23 Apr 2004). Puts up a lit corporate logo sign at Block H, Cherrywood Business Park. - [D09A/0146](https://cherrywoodplans.com/application/D09A-0146.md): Cherrywood Science and Technology Park, Cherrywood, Loughlinstown, Co. Dublin.. Granted (23 Apr 2009). Fills in atrium spaces in Building AA at Cherrywood Business Park, adding 269 sq.m and 5 parking spaces. - [D02A/0424](https://cherrywoodplans.com/application/D02A-0424.md): Cherrywood Science & Technology Park,, Cherrywood, Loughlinstown, Co. Dublin.. Granted (10 Jul 2002). Allows two permitted three-storey science and technology buildings, AA and AB, to be used instead for office-based industry. - [D08A/0687](https://cherrywoodplans.com/application/D08A-0687.md): Cherrywood Science & Technology Park, Loughlinstown, Co. Dublin. Refused or withdrawn (7 Aug 2008). Replacing Block D with a 5-storey office building with a large ground-floor shop at Cherrywood Science & Technology Park. - [D06A/0630](https://cherrywoodplans.com/application/D06A-0630.md): Spar Retail Unit, Block D, Cherrywood Science & Technology Park, Loughlinstown, Dublin 18. Granted (12 Jul 2006). An off-licence counter added to the Spar shop in Block D of Cherrywood Science & Technology Park. - [DZ22A/1025](https://cherrywoodplans.com/application/DZ22A-1025.md): Cherrywood Avenue, Lands within the townlands of Glebe and Cherrywood, Dublin 18. Granted (2 Nov 2023). Builds 44 homes, houses and two-level units, off Cherrywood Avenue. - [DZ16A/0530](https://cherrywoodplans.com/application/DZ16A-0530.md): Units 2 & 4 Building 7 (previously 'Block D'), Cherrywood Business Park, Cherrywood, Loughlinstown, Co Dublin. Granted (9 Sep 2016). Changes two vacant units in Building 7, Cherrywood Business Park, into medical and dental use. - [DZ25A/0066/WEB](https://cherrywoodplans.com/application/DZ25A-0066-WEB.md): Building 7 The Campus, Cherrywood Avenue, Cherrywood (Glebe Townland), Co Dublin, Dublin 18, D18T8Y6. Granted (20 Mar 2025). Part of Building 7 at The Campus changes from offices to medical and dental use. - [D05A/1672](https://cherrywoodplans.com/application/D05A-1672.md): Block D, Cherrywood Science & Technology Park, Loughlinstown, Co. Dublin. Granted (13 Feb 2006). Makes small changes to Block D, enlarging a ground-floor shop and trimming the offices. - [DZ24A/0291/WEB](https://cherrywoodplans.com/application/DZ24A-0291-WEB.md): Lands in the townland of Laughanstown, Dublin 18, located between Grand Parade and Tully Park., The application relates to development in Domville Development Area 4 of the Cherrywood Strategic Development Zone.. Granted (25 Mar 2025). Amends the Domville permission to raise four blocks on Grand Parade from 4 to 6 storeys, adding 58 apartments. - [DZ26A/0151/WEB](https://cherrywoodplans.com/application/DZ26A-0151-WEB.md): In the Townlands of Laughanstown and Cherrywood, in Cherrywood, Dublin 18.. Granted (24 Jun 2026). 188 new homes, a mix of apartments, two-level units and houses, beside Tully Park off Bishop Street. - [DZ22A/0133](https://cherrywoodplans.com/application/DZ22A-0133.md): Townlands of Laughanstown and Cherrywood, Dublin 18. Granted (22 Nov 2022). Builds 163 homes, a mix of apartments, triplexes, maisonettes and houses, beside Tully Park. - [DZ17A/0731](https://cherrywoodplans.com/application/DZ17A-0731.md): G3 (west of Block G2), Cherrywood Business Park, Cherrywood, Loughlinstown, Co Dublin (within the Cherrywood Strategic Development Zone (SDZ) and subject to the Cherrywood Planning Scheme 2014). Granted (26 Jan 2018). Builds a new four-storey office building, G3, on Cherrywood Avenue in Cherrywood Business Park. - [DZ24A/0485/WEB](https://cherrywoodplans.com/application/DZ24A-0485-WEB.md): Site Known as Block G3, Cherrywood Business Park, Cherrywood, Loughlinstown, Co. Dublin. Granted (19 Dec 2024). A 4-storey science and technology office building with labs on Block G3, Cherrywood Business Park. - [DZ21A/1038](https://cherrywoodplans.com/application/DZ21A-1038.md): site 1.85 ha at Castle Street and Bishop Street, Cherrywood, Dublin 18. Granted (8 Nov 2022). Builds a new 1,000-pupil secondary school at Castle Street and Bishop Street, Cherrywood. - [D08A/0952](https://cherrywoodplans.com/application/D08A-0952.md): Cherrywood Science & Technology Park,(Block D1), Cherrywood, Loughlinstown, Co. Dublin. Refused or withdrawn (15 Oct 2008). Design changes to the approved Block D1 office building at Cherrywood Science & Technology Park. - [D04A/1211](https://cherrywoodplans.com/application/D04A-1211.md): Cherrywood Road Bus Stop, (opposite Lucent), Loughlinstown, Co. Dublin. Refused or withdrawn (29 Jun 2005). Installs a steel and glass bus shelter with two lit advertising panels on Cherrywood Road. - [DZ21A/0029](https://cherrywoodplans.com/application/DZ21A-0029.md): Site of approximately 1,094 sq m at Building 8 (formerly known as Block E), Cherrywood Business Park, Cherrywood, Co. Dublin, c. Granted (29 Apr 2021). Rebuilds the front entrance of Building 8 at Cherrywood Business Park with a slightly larger lobby. - [DZ24A/0366/WEB](https://cherrywoodplans.com/application/DZ24A-0366-WEB.md): Building 8, Cherrywood Business Park, Dublin 18, D18W319. Granted (17 Jul 2024). Adds tenant signage and a wayfinding totem at Building 8, Cherrywood Business Park. - [DZ23A/0283](https://cherrywoodplans.com/application/DZ23A-0283.md): Building 8, Cherrywood Business Park, Cherrywood, Loughlinstown, Co. Dublin, D18 W319. Granted (11 Aug 2023). Turns Building 8 at Cherrywood Business Park from offices into a private medical clinic. - [D05A/0419](https://cherrywoodplans.com/application/D05A-0419.md): Block D, Cherrywood Science & Technology Park, Loughlinstown, Co. Dublin. Granted (26 Oct 2005). Extends the existing Block D building at Cherrywood Business Park, adding 790 sq.m of shop and office space. - [D07A/0604](https://cherrywoodplans.com/application/D07A-0604.md): Cherrywood Science Technology Park,(Block D1), Loughlinstown, Co. Dublin.. Granted (2 Apr 2008). Replacing a crèche with a 4-storey office building and restaurant (Block D1) at Cherrywood Science & Technology Park. - [DZ19A/0577](https://cherrywoodplans.com/application/DZ19A-0577.md): Cherrywood Avenue South adjacent to Building 11, formally known as Building G2, Cherrywood Business Park, Loughlinstown, Dublin, D18 DH50. Granted (23 Jan 2020). A new loading bay on Cherrywood Avenue South beside Building 11 in Cherrywood Business Park. - [DZ21A/0806](https://cherrywoodplans.com/application/DZ21A-0806.md): Lands in the townland of, Laughanstown, Dublin 18, located between Grand Parade and Tully Park. Granted (12 Aug 2022). Amends a permitted scheme between Grand Parade and Tully Park to add 60 apartments in three new 4-storey blocks. - [DZ26A/0580/WEB](https://cherrywoodplans.com/application/DZ26A-0580-WEB.md): Bishop Street (M3a), Laughanstown, Dublin 18 (Development Area 7 Macnebury - Res3 Plot). More information requested (22 Sep 2026). 32 new homes, mostly 3-bed two-level apartments, off Bishop Street in Macnebury. - [DZ24A/0236/WEB](https://cherrywoodplans.com/application/DZ24A-0236-WEB.md): Lands in the townland of Laughanstown, between Grand Parade and Tully Park, in Domville Development Area 4, Cherrywood, Dublin 18. Refused or withdrawn (15 Apr 2024). Amends the Domville permission to raise four blocks on Grand Parade from 4 to 6 storeys, adding 58 apartments. - [DZ17A/0714](https://cherrywoodplans.com/application/DZ17A-0714.md): Lands in the townlands of Lehaunstown and Cherrywood, Dublin 18. The application relates to development in the Cherrywood Strategic Development Zone.(Domville site). Granted (7 Aug 2018). Builds 322 new homes, 242 apartments and 80 houses, plus a crèche on the Domville site in Cherrywood. - [D03A/0735](https://cherrywoodplans.com/application/D03A-0735.md): Tullyvale, Druid Valley, Cherrywood, Loughlinstown, Co. Dublin.. Granted (22 Sep 2003). Changes the approved Tullyvale housing development by realigning its access road and adding a signalised pedestrian crossing. - [D06A/0116](https://cherrywoodplans.com/application/D06A-0116.md): Glencarraig, Rathmichael, Co. Dublin. Granted (18 Aug 2006). 19 homes and a new access road linking Brides Glen Road to Cherrywood Science & Technology Park at Glencarraig. - [D05A/1083](https://cherrywoodplans.com/application/D05A-1083.md): Glencarrig (site At), Rathmichael, Co. Dublin. Refused or withdrawn (12 Oct 2005). Builds 73 apartments in two blocks at Glencarrig, with a new road and cycle route from Brides Glen Road to Cherrywood Business Park. - [D06A/1497](https://cherrywoodplans.com/application/D06A-1497.md): Cherrywood Science & Technology Park, Loughlinstown, Co. Dublin. Granted (14 Dec 2006). Builds a new four-storey office building, Block G2, over a two-level car park at Cherrywood Business Park. - [DZ19A/1022](https://cherrywoodplans.com/application/DZ19A-1022.md): On a site of 0.625ha, Dell Technologies, Block AB, Cherrywood Business Park, Cherrywood, Dublin 18. Granted (25 Feb 2020). Replaces two lit signs on the Dell Technologies building, Block AB, Cherrywood Business Park. - [DZ17A/0466](https://cherrywoodplans.com/application/DZ17A-0466.md): Block AB of CHerrywood, Science and Technology Park, Loughlinstown, Dublin 18. Granted (13 Jul 2017). Replaces signs at Block AB, Cherrywood Business Park, with two lit wall signs and a totem sign. - [DZ25A/0197/WEB](https://cherrywoodplans.com/application/DZ25A-0197-WEB.md): Located to the north end of the Valley Drive public road, which is a cul-de-sac, opposite the corner apartment building 97-106 E. Refused or withdrawn (18 Mar 2025). Provides a paved bin collection area at the end of Valley Drive for the Tullyvale apartments. - [DZ20A/0611](https://cherrywoodplans.com/application/DZ20A-0611.md): Site of approximately 4,730 sq m at Building 11, (formerly known as Block G2), Cherrywood Business Park, Cherrywood, Co. Dublin, D18 DH50. Granted (19 Oct 2020). Expands the day hospital in Building 11, Cherrywood Business Park, to 1,220 sq.m. - [DZ18A/1131](https://cherrywoodplans.com/application/DZ18A-1131.md): Site of approx. 4,730 sqm at Building 11 (formerly known as Block G2), Cherrywood Business Park, Cherrywood, Dublin D18 DH50. Granted (5 Feb 2019). Turns part of the ground floor of Building 11 at Cherrywood Business Park into a 922 sq.m day hospital. - [D13A/0292](https://cherrywoodplans.com/application/D13A-0292.md): Site at Glencarrig, Brides Glen Road, Rathmichael, Co. Dublin. Granted (1 Aug 2013). Amends the earlier Glencarrig permission with a revised design for 10 five-bedroom detached houses. - [DZ17A/0649](https://cherrywoodplans.com/application/DZ17A-0649.md): Block G2, Cherrywood Business Park, Cherrywood, Co Dublin. Granted (8 Sep 2017). Adds louvred screening around rooftop plant on Block G2, Cherrywood Business Park. - [DZ16A/0935](https://cherrywoodplans.com/application/DZ16A-0935.md): Block G2, Cherrywood Business Park, Cherrywood, Co. Dublin. Granted (17 Feb 2017). Adds landscaping, a drop-off area and a sign at Block G2, Cherrywood Business Park, and keeps three glass canopies. - [DZ20A/0946](https://cherrywoodplans.com/application/DZ20A-0946.md): Lands known as Tully Park (c12.9HA), Laughanstown, Dublin 18. Granted (18 Feb 2021). Revises part of the permitted Tully Park, moving the café kiosk, redesigning the playground and adding a raised boardwalk. - [DZ15A/0813](https://cherrywoodplans.com/application/DZ15A-0813.md): Laughanstown, Dublin 18, (Tully Park). Granted (13 Jul 2016). Creates Tully Park, a 12.9-hectare public park with a playground, café kiosk and nature trails. - [DZ16A/0123](https://cherrywoodplans.com/application/DZ16A-0123.md): Units 1 & 2 Block C, Cherrywood Business Park, Cherrywood, Loughlinstown, Co Dublin. Granted (21 Apr 2016). Reconfigures two ground-floor shop units in Block C and turns one into a café/restaurant. - [DZ14A/0596](https://cherrywoodplans.com/application/DZ14A-0596.md): Unit 1 , Block C, Cherrywood Science and Technology Park, Cherrywood, Loughlinstown, Co Dublin. Granted (11 Dec 2014). Changes Shop Unit 1 in Block C, Cherrywood Business Park, into a dental clinic. - [DZ16A/0816](https://cherrywoodplans.com/application/DZ16A-0816.md): Unit 4 Building 5 (previously Block C), Cherrywood Business Park, Cherrywood, Dublin 18. Granted (10 Jan 2017). Changes a vacant shop unit in Cherrywood Business Park into a bank with an ATM. - [D07A/0233](https://cherrywoodplans.com/application/D07A-0233.md): Cherrywood Science Technology Park, Loughlinstown, Co. Dublin.. Granted (27 Aug 2007). Extends and reworks the approved Block C leisure building, adding a double-height swimming pool hall. - [D06A/0268](https://cherrywoodplans.com/application/D06A-0268.md): Cherrywood Science & Technology Park, Loughlinstown, Co. Dublin. Granted (16 Jun 2006). Builds a four-storey leisure and retail building (Block C) with a fitness centre and 25-metre pool at Cherrywood Business Park. - [D05A/1715](https://cherrywoodplans.com/application/D05A-1715.md): Cherrywood Science & Technology Park, Loughlinstown, Co. Dublin. Refused or withdrawn (12 Jan 2006). Builds a four-storey leisure and retail building (Block C) with a fitness centre and 20-metre pool at Cherrywood Business Park. - [DZ23A/0508](https://cherrywoodplans.com/application/DZ23A-0508.md): Unit 3 and Unit 1, Building 5, Cherrywood Business Park, Cherrywood, Loughlinstown, Co Dublin. Granted (22 Sep 2023). Two units in Building 5, Cherrywood Business Park, become a dental clinic and a café. - [D07A/0229](https://cherrywoodplans.com/application/D07A-0229.md): Cherrywood Science Technology Park, Loughlinstown, Co. Dublin.. Granted (28 May 2007). Adds a temporary vehicle ramp to the basement car park serving Blocks G and G2 at Cherrywood Business Park. - [D08A/0121](https://cherrywoodplans.com/application/D08A-0121.md): Block C, Cherrywood Science And Technology Park, Cherrywood, Loughlinstown, Co. Dublin. Granted (24 Jun 2008). Seeks to keep an extension to the Block C facilities building and sets out options for a front loading bay. - [D07A/1607](https://cherrywoodplans.com/application/D07A-1607.md): Cherrywood Science Technology Park, Loughlinstown, Co. Dublin.. Refused or withdrawn (24 Jan 2008). The top floor of Block C at Cherrywood Science & Technology Park changes from recreation use to offices. - [D07A/1503](https://cherrywoodplans.com/application/D07A-1503.md): Block C, Cherrywood Science And Technology Park, Cherrywood, Loughlinstown, Co. Dublin. Refused or withdrawn (18 Dec 2007). Keeping a 52 sq.m ground-floor extension and shopfronts at Block C, Cherrywood Science & Technology Park. ## Links - [This page on CherrywoodPlans](https://cherrywoodplans.com/application/DZ23A-0423) - [Council record, documents and conditions (DLR planning portal)](https://planning.agileapplications.ie/dunlaoghaire/application-details/96464) - [All Cherrywood applications](https://cherrywoodplans.com/applications.md) _Source: Dún Laoghaire–Rathdown County Council planning data, refreshed daily. CherrywoodPlans is an independent site, not run by the council._