为 Cherrywood Business Park 已获批的 G 办公楼加建一层,从三层变为四层。
Cherrywood Science and Technology Park, Cherrywood, Loughlinstown, Co. Dublin.
- 4
- 层
- 12,241
- 平方米办公
- 3,142
- 平方米新增面积
Cherrywood Science and Technology Park, Cherrywood, Loughlinstown, Co. Dublin.
为已获批的 G 办公楼加建一层办公空间,并作相关改动。
办公面积从 8,721 平方米增加到 12,241 平方米。新加的一层增加 3,142 平方米,另有 130 平方米分布在两层,用来连接新的消防楼梯。
建筑从 3 层增至 4 层。中央核心筒重新设计,设 4 部电梯;疏散楼梯移位;东侧设一座 ESB 变电站。
地下停车场改为两层完整的停车层,由一条坡道连接。
由 AI 根据议会的描述撰写。以文件为准。
An additional floor (second floor of gross area 3,142 sq.m) to approved Block G (Reg. Ref. D01A/0026, D02A/0430, D02A/0941 and D05A/0219) increasing the building in height from a three storey to a four storey office building; modifications also include the provision of a new fire escape stairs to the rear (south) side and consequent increase in floor level at first floor and third floor levels of 130 sq.m to link into new stairs; relocation of the escape stairs on the east and west elevations...
An additional floor (second floor of gross area 3,142 sq.m) to approved Block G (Reg. Ref. D01A/0026, D02A/0430, D02A/0941 and D05A/0219) increasing the building in height from a three storey to a four storey office building; modifications also include the provision of a new fire escape stairs to the rear (south) side and consequent increase in floor level at first floor and third floor levels of 130 sq.m to link into new stairs; relocation of the escape stairs on the east and west elevations to meet fire escape travel distances; location of ESB substation on east elevation; modifications to central core to provide 4 lifts; modifications to basement car park to give two full decks of parking with single access ramp between; office area to increase from 8,721 sq.m gross to 12,241 sq.m gross.